Discontinued parts get no function in Plan order

Dear experts :
     my  Problem is:
         When i creat the production order , the requirement of follow -up group replace the discont. group. but when i creat plan order,  it does not work, even after i run MRP,MPS.(Creat the PR for part "a").
        and when i tranferred the Plan order to production order, it works again.
    My scenario is:
         I set the discontinuation indicator:(1),  followed parts (b), effective-out date(in the past) in master of main item(a) for discontinuation.  and matained the Discont. group(a,a1,a2 total 3parts),Follow-up group in BOM(b,b1 total 2parts). and the mrp type, units of  these 5 parts are same.
      now part 'a' still have some stock, but are reserved.
     Can you kindly tell me the reason?
     Tks.
Edited by: ZP Liu on Jan 9, 2009 10:23 AM

Can anybody give me an advise?  The discontinued setting (Material and BOM) seems have no effect in Plan Order.

Similar Messages

  • Pegging gets broken after conversion planned order to production order

    Hi All,
       I am getting pegging of finish product and dependent product planned order in MRP after taking MRP run.......But after converting the planned order to production order all order gets start from today by breaking the  relationship of each other..........can anybody explain me why this is happening.............your answer will be appreciate ........thanks in advance.........waiting for reply........
    Best Regards
    Sharad

    If it is backward scheduling, system takes the requirement date and starts going back…
    If the start date calculated is less than today date, then there are two ways system will do the adjustment.
    If in scheduling setting for production order, if there is a setting – start date allowed in past and you have entered some days, then system will go back to that date and schedule so that production order will start from past i.e. from today.
    Now if past days are not allowed then system will switch over to today scheduling I.e. the start date is today.
    In your case production order start date is today….this may be your case.
    Just for the case of testing see what is the production lead time and calculate the start date manually and see whether it is going beyond today?
    What is the exception message you have in the production order line in MD04…this also will give some idea…

  • Discontinuation: calculation of remaining stock in planned orders

    Hi Experts,
    In discontinuation component A is followed by component B. Component B will be used when stock of component A is depleted.
    In our system we now see that the calculation of available stock for component A is different for planned orders than for production orders. Planned orders switch 2 months earlier to the new component B than production orders. It seems that the system doesn not include shipping notifications in the calculation for planned orders.
    Does anyone know where this is configured?
    Thanks for your thoughts,
    Albert-Jan

    AJ,
    It is possible that your ship notifications are not relevant for MRP.  You can check this in ME23N, select item details, select the confirmation tab, select the relevant confirmation, look at the contents of "M" (relevant for MRP) checkbox.  You can changes the default behavior of your confirmations in IMG > MM > Purchasing > Confirmations > Set up confirmation control.  Select the control key being used in these orders.  Select the confirmation sequence.  Look to see if the 'MRP relevant' checkbox is selected.
    Before you decide to change this, reflect on what it will mean.  If it is currently un-set, then your PO schedule lines are relevant for MRP, rather than your confirmations.  Don't change it unless you want the confirmations to take precedence over the schedule lines in planning.
    In most instances I have seen, if the ShipNots have been made relevant for ATP, they are also made to be relevant for MRP.   Less confusion.
    Below, a couple of notes that do a pretty good job explaining how discontinuation works.
    https://service.sap.com/sap/support/notes/43636
    https://service.sap.com/sap/support/notes/513874
    Rgds,
    DB49

  • Difficult question?? Discontinued Parts with replace function????

    Hi Experts
    In our company ,there is a requirement very emergent , as follow example:
    In the BOM of material CDE, there is a component material A.
    And for some reasons(for example: product development with new technique) ,we want to replace
    material A with material B in the BOM. And because the stock of A in the warehouse is not zero,so we
    want to continue use material A for a period.
    And when the stock of A in the warehouse is zero 0 ,means that A has use out, we want to the SAP system automatictlly replace material A with material B in the BOM.
    I konw I can use "discontinued Parts" , but with "discontinued Parts",the system only can transfer
    all the dependent requirements of the discontinuation material  to the follow-up material, not replace the  discontinuation material with the follow-up material in the BOM really! 
    We want with "discontinued parts", the system can replace the discontinuation material with the follow-up material in the BOM really ?
    How to achieve this?? Or if there is some other functions can achieve this??
    Thanks for any reply!!

    Dear Fei,
    What's your exact doubt?
    If you want to stop using a component from a certain date and instead you would like to replace the
    same using another followup material which has the same unit of measure,then you can do the
    necessary settings in MRP4 view of the material master.
    One more concept is alternative Item concept,where in some period material A will be available for some
    period and in some other period B may be available and in sometimes a combination of both will be
    used.
    Then in that cases in the BOM an alternative item group will be created to combinae these 2
    components along with their priority,usage probability and strategy.
    Regards
    Mangalraj.S

  • MD06  Issue - Planned orders not getting displayed

    Hello,
    Planned order with the exception "Newly created order proposal" does not get displayed in MD06 with the option "Only Unprocessed MRP Lists" in the processing indicator.
    I am running MD06 report with the following parameters:
    Plant
    MRP Controller
    Exeception Group - All exception selected except 8-Terminations
    Processing indicator - Only unprocessed MRP LIsts, Only with new exceptions
    My material which has a newly created planned order thorugh MRP run with exception "1 - Newly created order proposal" does not get displayed.
    Only when I specify Only processed MRP lists or All MRP LIst in the processing indicator, this material gets displayed. The planned order is for a Stock Transfer order to this plant (receiving plant). How is the MRP LIst processed?
    Please help me out with this issue.
    Sincerely,
    Ketan

    Hi Ketan,
    When you execute the MD06 report, you would find a column with the heading CI, if am right it would be just after the MRP cntlr, here you would find a Pencil & a tick mark. If you find them both, it means the row is unprocessed, but if you find only a tick mark it means that the row is processed.
    So now check for the planned order, it would be just a tick mark & hence would be showing only for the processed MRP list or all MRP lists.
    To process a row or unprocess, just click on the icon & it changes.
    Check & revert if it answers your query.
    Regards,
    Vivek

  • Get the supply source of planned order and process order.

    Hi experts,
    I would like to display production version (supply source) on prduct view.
    But, I don't know that how to get supply source of planned order and process order.
    APO  table is complax.
    Do you know that?
    Regards,
    Satoru

    Hello Tushar,
    Are components also plan in APO with MRP type X0?
    Does PDS or PPM contain all the components?
    Verify if the component is maintained properly in the PDS.
    Check whether there is an active integration model for the components, also execute the RAPOKZFX report for all the materials in question.
    When you convert the PPDS order to process order then conversion happens in ECC/R/3 system. This is the place BOM has to be reexploded in ECC. Please check if you have any enhancement which restrict BOM explosion. 
    Also check OSS note 1576703 suggested by an expert Caetano.
    Best Regards,
    R.Brahmankar

  • Conversion of planned orders to prod orders in background

    hi All
    Is there any program for mass conversion of planned orders in production orders which we can schedule in background.
    Amit

    Hi Amit,
    Try below method
    TCode: COHV (tab selection --- plant and etc...,, tab mass processing --- function - conveted planned order, order type - PP01, collective orders - do not collective orders)
    after Menu -- Program --- Excute in background -- set properties -- to set send SAP spooler --- click button immediate then check box periodic job and periodic values after save
    to monitor and get spool request bcackground this job
    TCode SM37
    or
    you can create background job using TCode SM36
    pls create varient for COHV
    PRG: PPIO_ENTRY with Varient
    Regards,
    Sankaran

  • Collective deletion of Planned Orders

    Hi,
    We want to delete MRP generated planned orders collectivily. However we are using MD16 for it, but it is very slow process to get rid of unwanted planned orders. Our limitation is we can't go for re-generative planning.
    Please help with any BAPI, function module or transaction code.
    Regards,
    Amol

    Dear Amol,
    Check this BAPI BAPI_PLANNEDORDER_DELETE in SE37.
    Regards
    Mangalraj.S

  • How can I set a fixed scrap qty on planned orders created by MRP?

    During production of some specific subassemblies, destructive testing is done that requires us to scrap two pieces per production order.  I know I can set an assembly scrap percent, but what I need instead is a way to set a fixed assembly scrap quantity that will get loaded onto every planned order created by MRP for these subassemblies.  If we can't do this, we can't plan the correct order quantity and eventually end up being short of parts.  I know we can set a safety stock or safety time, but I'd rather just plan the right quantities if possible.
    Is there a user exit, configuration option, or master data setting that will allow me to do this?
    Thanks,
    Randy

    Hi Randy
    This can be solved by one solution. _You can try this._
    You define the same item in BOM again with qty 2 nos. Double click on the item no. Then it will take you to item detail. There in Basic data tab page at quantity data  ( Tick the fixed quantity. ).
    When ever BOM explodes for the header material automatically The item will be exploded 2 nos extra.
    Ex
    The header is Mat X and items is Mat Y. While creating BOM for X give item Mat Y in item no 10. give the quantity as per the requirement.
    And again give item Mat Y in items no 20. give quantity 2 nos and activate the fixed quantity tick as instructed above.
    When ever requirement for Mat X is 100 nos. The plan order for Y will be 102 nos .
    Hope this will clear.
    Regards
      J .Saravan

  • Reservation against planned order

    Hi...
    I have one issue with reservation against planned order.
    We have REM & after MRP run generates planned order with order type PE.When i check planned order in table PLAF.
    I found reservation no. & same has been passed to RESB , I got the reservation details but it is not allowed for goods movement XWAOK field in RESB. So no question of goods movement through MB1B with movement type 311.
    My question is that is there any customization related to above scenario so that reservation is allowed for goods movement?
    Regards
    Tushar

    Dear ,
    In REM , you will recieve reservation against planned order .But GI always happens during GR or after GR along with back flashing .I do not think so you can issue material against reservation as like normal PP Order reseravation  in the production order .
    1.Goto -SPRO->production-> Rep Manufacturing->Define Rem MAnufaturing profile(OSP2) --->Control data, in the Control data 1 tab select the "GI back flush at GR posting".
    2.Check in  the REM profile assigned in MRP view of material Master (MM03)
    Based on this above set up , you can make Goods Issue for Planned order in REM .If you deselect that option execute material staging transaction code is MF60 and then go for REM backflush. In materil staging the components issue is carried out for the planned order.After that you can execute the REM backflush in MFBF
    In rem scenarion components placed on the production lines anonomously (without ref to planned order)...you cannot issue materials like in production orders scenario. if you want to have track on the good issues before the GR then use the pull list concept...there will be no movement type but you will have track on quantities issued to header parts/production lines not to planned orders.
    Hope this clarifies your doubt .
    Regards
    JH

  • Re: More than one planned order on same day

    Dear All,
    I am getting more than one planned order for the same day in MD04 after I run MRP run. My requirement is that the planned order should get clubbed.
    My lot size is WB & 2: collective requirement setting.
    Please advice.
    Regards,
    Vivek Sharma

    Karthick,
    I am getting more than one planned order on same date.If I check any of the planned order for pegging requirements I find that the planned order has been created after clubbing all the requirements( the Raw material is being used in morethan one FG )
    Now the issue Is :
    09.06.2010     PldOrd     0019211763/STPO     13.02.2010     30     159.500
    09.06.2010     PldOrd     0019211764/STPO     18.02.2010     30     1,536
    09.06.2010     PldOrd     0019211765/STPO     25.02.2010     30     787.500
    09.06.2010     PldOrd     0019211766/STPO     11.03.2010     30     2,536.755
    09.06.2010     PldOrd     0019211767/STPO     29.03.2010     30     862.500
    09.06.2010     PldOrd     0019211768/STPO     13.04.2010     30     108.750
    09.06.2010     PldOrd     0019211769/STPO     27.04.2010     30     1,678.500
    09.06.2010     PldOrd     0019211770/STPO     30.05.2010     30     980.745
    So I dont understand how is this happening.
    Regards

  • Table For Planned Order Details From PP Module

    In our organisation we are taking Plan Vs Acheivement from Production. So, intialy we taken Plan details from "PLAF" Table and Acheivement details from "S225" Table. But After running MRP at month end. Previous month plan get deleted and new order create.
    how to get history data for Planned order.
    Please help us.
    Regards
    Naga

    I don't think that there is any history in regard to planned orders.  PLAF will get rebuilt according to your MRP parameters and I don't believe that the data is stored.
    Regards,
    Rich Heilman

  • Conversion of Planned order into a Production Order.

    Hi All,
             I have one ticket in which I have to change the format of generating serial no.s.This format has to consider
    Basic Start Date while generating it.In our project Serial No is getting generated at the time of Production Order.
    So I have to pass this start date before Prod Order is getting created from a Planned Order.What i want to know is it possible to pass a start date when a Planned Order is getting converted into Prod Order as i think it will be a standard SAP program which will convert a Planned Order into Prod Order.Any suggestions on how to achieve this is most welcome.
    Thanks in Advance,
    Saket

    Hi,
    I am not able to get what is passing the start date.
    Second thing is how you are generating the serial number - manually or automatic?
    If you are generating serial number automatic, then it is not possible to generate it considering the basic start date.
    But if you are entering the serial number manually, then there should not be any problem as system will accept that serial number which you enter at the time of conversion of planned order to production order.
    Regards
    Amit parkhi

  • Deletion of Planned Orders

    Dear all,
    At the end of every week, we want to delete all the planned orders available in system.  I tried COHVPI, but there is only two mass processing functin available, Convert Planned Orders and Material Availabilty Check.
    So, can any one tell me which transaction code I can use?
    Thanks and regards,
    Devang

    Hi
    There is afunctionality called "Roll forward period"
    The function of this:
    To automatically update the master plan, you can set the system so that firmed planned orders that were scheduled before the roll forward period can be deleted during the planning run. With this function, all planned orders, for which there are no longer any requirements, are deleted.
    For this you have to have some config settinglike:
    In step "check MRP types", you can maintain the indicator "Delete out-of -date planned orders" which is used to set the system so that firmed order proposals, that lie beforethe roll forward period, are deleted in in the planning run. At the same time, new planned orders are created that are adjused to the current situation. (Or depending on the fixing type the old order proposals are displaced to the end of the planning time fence.)
    This is available in the IMG step:
    Production >MRP>planning>MRP calculation>Define planning timefence& roll forward period.
    Pl. try this & come back.
    Regards
    YMREDDY

  • Variant configuration - Configuration Simulation for Planned Order

    Hi,
    I am using the configuration simulation to check the configuration results for BOM and Routing. However, I am unable to get the simulation of the Planned Order. What are the requirements to get simulation of the Planned Order in configuration simulation? I have set the configuration parameters - Process to Plnd/Prod Order and BOM explosion to multi-level. The BOM for my KMAT material also have semifinish goods which requires MRP. I am confused how come no components was selected during the simulation of Planned Order.
    I would really appreciate if anyone has any input on why this happened.
    Thank you very much.
    Cheers,
    Sue

    Dear,
    Please check the following
    Material type =Kmat
    Super BOm and depedency is maintained for BOM item selection
    Super routing with dependency is maintained
    you have maintained - conf profile with following setting
    process- pl/prod order
    bom exlposion - multi level
    BOm explosion - PP01
    explosion level - <b></b>NO<b></b> check box tick for only conf meterial
    Profile is released.
    now try in cu50, confi result=BOM radio box
    please come back if you still have problem