   we have a scenario where imported goods are purchased from a trader in Bombay. The vendor passes the client the  ADC(additional duty of customs) and CVD what he has paid while purchasing goods from germany.
the client takes the cenavt credit of ADC and CVD. I have maintained the condition types for ADC as JADC and using jexc to capture to capture CVD in PO pricing procedure.
my issue is that these values are getting loading in stock account. the requirement is to take the cenvat credit of ADC and CVD.
please help what settings are required to be done so that ADC and CVD doesnot get loaded in stock account.
regards
Ajay

Hi Ajay,
If you do not want any condition to be loaded to Material account than make an account key and like FR1 and assign one GL for that account in OBYC. This account key you need to define in your pricing Procedure.
Just exploer above suggestion.
Thanks
Sanjay

Similar Messages

  • ADC on domestic purchase of imported goods

    Hi Experts,
    This is regarding the ADC applicable wherein if imported material in procured from domestic market.Dealer passes on CVD and ADC part to maufacturer at the time of purchase so to map this scenario i am following the instruction mentioned in the SAP NOTE 964190.
    I have introduced JADC condition in MM pricing as per instruction.As per note we will refer JEXC condition as CVD condition and its value will go in excise duty GL account through TAXINN customizing setting
    .*Now my query is what condition to be put in TAXINN to pass on value of JADC and where should i maintain GL code for ADC in the system*.
    Kindly share if anybody has done configuration related to this scenario
    Thanks in advance
    Regards
    Vivek

    Hi George,
    I am referring your mentioned notes, only apprehension is regarding condition type AED which in mentioned in SAP note as it should be activated in tax code.
    This AED condition i am not able to find in TAXINN secondly its also not mentioned how to maintain this condition in the TAXINN.
    Seeking your advice on this
    Regards
    Vivek

  • Sequencing of Purchase order and Good Issue acc. to Production order date

    Hello ,
    We are using Direct procurement scenario ,During MRP run we generate a Plan order(which have dates); which converted into Production order later.For these production order material is needed (components). And for procuring components we need to create purchase order.
    Assumption :- Each component have same Procurement lead time
    Our requirement is Purchase order and GI in Production order should be done sequentially, means Based on Production order date ,FIFO based Purchase orders are created and GI done in Production order. Production order with earlier production date have purchase orders earlier and we do GI in production order accordingly.
    Kindly suggest

    Hello Dario
    Thanks for your reply. Our requirement is to put a check on system that GI for production order should be done FIFO wise
    means as MRP generate 3 production order of same material each at different date , we want issance of components to be done on FIFO wise in production order
    Regards
    Rajeev

  • Additional duty of custom in domestic purchase

    Hi Friends,
    My Client purchases import material in domestic market also. So at the time of purchasing this material client pays ADC to the vendor.
    So in domestic pricing i want to maintain this condition of ADC.
    I want to clear following points in this regard:-
    *1. To create this ADC condition type which condition should i refer.
    2. This ADC amount is claimable and its value is debited into BED register how can i do this*
    Waiting for your response !!
    Regards
    Vivek

    Hi,
    Refer SAPNote 964190 - ADC on domestic purchase of imported goods
    This occurs in case if a trader will pass on Additional duty of Customs paid while importing the goods. In case of capital goods, the credit for ADC can be fully availed.The credit for this ADC can be availed.
    Configurations:
    Create a new condition for ADC(JADC) by referring to the attachement in SPRO -> Materials management -> Purchasing -> Conditions -> Define Price Determination Process -> Define Condition Types. Give the short text as "ADC in Pricing".
    Add this condition type (JADC) to the pricing procedure at SPRO -> Materials management -> Purchasing -> Conditions -> Define Price Determination Process -> Define Calculation Schema. Set the SubTotal as 2 for this condition type(JADC). No ActKy is required.
    JEXC shall be used for countervailing duty and ECS amount need not be entered in the pricing procedure.Only ADC amount will be entered against
    this new condition type(JADC).
    1. The Excise Registration Is Liable to AED.i.e. In the transaction SM30, for Table / View:J_1IREGSET, AED must be checked.
    2. AED% is NOT required to be maintained J1ID for that material.
    3. The AED(Additional excise duty)condition in the tax code has to be active if sub-routine based tax procedure(TAXINJ) is being used.
    4. For  ADC, either the setoff or inventory exists.Both conditions cannot exist simultaneously.
    5. The condition record for AED has to exist (in transaction FV12) if  condition based tax procedure(TAXINN) is being used.
    Refer to the attached document 'J_1I4_GET_MANUAL_EXCISE.zip' for changing the import and export parameters.
    Add the parameters listed in the document to respective function modules.
    Procedure to add new parameters:
    Run transaction SE37, enter the function module name as J_1I4_GET_MANUAL_EXCISE and click on 'Change' button. To add import parameters, click on 'Import' tab, else to add export parameter click on18.03.2008 Page 2 of   3 Note 964190 - ADC on domestic purchase of imported goods
    'Export' tab. Add new parameters according to the details given in the attached document. Save and activate the changes.
    Apply the code corrections once the parameters have been added.

  • Goods Issue with reference to Purchase Order

    Hi MM Gurus,
    Is there any settings to do Goods Issue with reference to Purchase order?
    I want to capture the material price in purchase order during goods issue instead of standard price or moving average price.
    Thanks in advance
    Dinesh

    Hello Dinesh,
    Batch valuation is similar to split valuation. Here is the link on how batch valuation works.
    http://help.sap.com/saphelp_47x200/helpdata/en/25/283db54f7811d18a150000e816ae6e/content.htm
    Please check in sandbox environment before using.
    Hope this helps.
    Regards
    Arif Mansuri

  • Goods Issue with Purchase Account Management

    Hi,
    in one of our foreign subsidiaries we have to run the MM-Purchase Account Management. These subsidiaries will be delivered by Cross-Company Replenishment deliveries with intercompany-invoicing. Every Goods receipt for such an replenishment delivery will be posted in the receiving subsidiary, besides the normal bookings on the u2018Goods/Invoice Received clearing accountu2019 and u2018Stock accountsu2019, on additional purchasing accounts. Now itu2019s possible that the goods have to be returned to the delivering plant due to any problems. To send back the goods we use again a SD-delivery (triggered also by an MM-IC-Purchase order) and with this SD-delivery we want also to post the goods issue in the subsidiary. But as the goods receipt has been posted on these special additional purchasing accounts, the goods issue has also to be posted on these special additional purchasing accounts (The target is to correct these purchasing accounts to the ammount of the returned goods). But it seems that this is not possible because of the MM-Account determination which doesnu2019t allow to post on these special purchasing accounts with an SD-transaction. Iu2019m no MM-expert but is there any possibility to post on this purchase accounts also when posting a goods issue in SD? If not in standard, are there any User-Exits in the account determination?
    Regards
    Stephan
    Edited by: Stephan Nadler on Aug 12, 2008 1:20 PM

    Hello Dinesh,
    Batch valuation is similar to split valuation. Here is the link on how batch valuation works.
    http://help.sap.com/saphelp_47x200/helpdata/en/25/283db54f7811d18a150000e816ae6e/content.htm
    Please check in sandbox environment before using.
    Hope this helps.
    Regards
    Arif Mansuri

  • Purchase order message Re-determination after goods issue is posted

    We have a requirement to trigger special function message type (which creates a flat file) in a purchase order when goods issue for all items are posted. We have created a requirement routine for message type to check if goods issue is posted for all line items. Goods issue is posted using BAPI which uses transaction MIGO. When goods issue is posted, we want output to be triggered in purchase order. Requirement is working fine but is there any way to trigger output automatically without going to PO?
    After goods issue is posted, if we go into purchase order using ME22N then we see output proposed or if we make any changes in PO then output is proposed. This will not happen in real life though.
    Any suggestion will be highly appreciated. Thanks.
    Sanjay

    Hello,
    You can create a new output message record in NAST using RV_MESSAGE_UPDATE:
    CALL FUNCTION 'RV_MESSAGE_UPDATE'
          EXPORTING
            msg_kappl = 'EF'
            msg_objky = w_objky
          TABLES
            msg_xnast = itab_nast
            msg_ynast = itab_nast_old
          EXCEPTIONS
            no_update = 1
            OTHERS    = 2.
    Once the record is created, you may submit the program RSNAST00 to output the message.
    Thanks,
    Venu

  • Storage Location from USERTEMP1 not picked during Goods Issue

    Hi All,
    We had populated the USERTEMP field in FMDERIVE with the Storage Location using the steps mentioned in the following thread
    Fund Center not getting populated through FMDERIVE
    The problem is that during a Goods Issue made from MIGO, this particular field is not getting picked up in the USERTEMP (trace was set up in FMDERIVE, which showed that the USERTEMP is empty).
    But in the case of PR/PO and other purchases, the USERTEMP is getting derived properly with the storage location.
    Why is that the USERTEMP behaves differently for a Goods Purchase and a Goods Issue ?
    Requesting help from the experts on this issue,
    Thanks,
    Wy.

    Hi Eli,
    We replicated the development we did for procurement (copying from storage location into USERTEMP) by finding out the enhancement point and the code worked fine here.
    One important thing to note is that the buffer need to be cleared everytime, before a value is entered here - the USERTEMP field is static otherwise.
    Thanks for your inputs,
    Wy

  • Balance sheet differecess while goods issue business ara wise

    Dear all
    here we are going to use two business areas A1 and A2 in one company code 1000
    1) some times we are going to purchase for business area A1.
    2) Some times we are going to purchse for businessa rea A2.
    here my question is some times we are going to purchase company code level 1000 then in goods issue we are going to issue business area wise plese help me out how to get Balance Sheet and Profit and Loss Account businessa rea wise.
    because purchase made without referece of purchase area and goods issued with reference of business areas.
    regards
    sadiq

    Hello
    Since you have 1 company code and 2 business areas, the catch here is the assignment.
    It all depends on the MM integration settings where the account determination is set.
    It depends on how many stock accounts you have.
    Whether it is segregated between business areas.
    GR/IR can be one account.
    Assign business areas to business area plants and storage locations.
    You can make transfers from CC plant to BA plant.
    For balance sheet preperation, ensure a clearing account is created / execute readjustment programs and generate BS
    Reg
    suresh

  • Goods Issue to Subcontractor at MAP or Price of Purchase which ever is high

    Dear Sir/Madam,
    The scenario is like this :
    I have raised a Purchase Order  for a material (say ABC) to be kept in stock and to be issued as and when requisitioned by the user.
    Quantity of PO 100 nos. Unit Price : Rs. 10 per no. and Total Price of PO = Rs. 1000/-.
    I prepare a Goods Receipt for these 100 nos. hence GR value will be Rs. 1000/-.
    Stock will be 100 nos. and the Moving Average Price will be Rs. 10/- and Value of Total Stock will be Rs. 1000/-.
    I have prepared another PO for a material (say ABC).
    Quantity of PO 100 nos. Unit Price : Rs. 8/- per no. and Total Price of PO = Rs. 800/-.
    Goods Receipt is prepared for these 100 nos., hence GR value will be Rs. 800/-.
    Stock will be (100 nos. + 100 nos.) = 200 nos., Value of Total Stock will be (Rs. 1000/- + Rs. 800/- = Rs. 1800/-) and the Moving Average Price per unit will be Rs. 1800 / 200 = Rs. 9/-.
    I have to issue the material to the Sub-contractor for executing a particular job.
    The requirement is to issue the material to subcontract at the highest price (i.e. Rs. 10 per unit) instead of issue of Material at the Moving Average Price (i.e. Rs. 9/-). This is required to ensure that the contractor does not report loss of materials in order to avail benefit of difference in market price and price at which the company issues material to the contract (i.e. the contract the may sell the material at a cost of Rs. 10 per unit and repay the issuing company Rs. 9/- per unit (MAP at which the material is issued to him).
    This requirement is audit point and has come as an audit compliance for us.
    The problem is my Stock Value is Rs. 1900/- so I can book a consumption of only Rs. 1900/-, but if I am able to issue goods of Rs. 2000/- where will be a negative consumption of Rs. 100/-.
    Please suggest if it is possible and if possible advisable and what should be the accounting entries that will be posted and to make goods issues at market price or price which is higher in the SAP. How can this be achieved.
    Thanks in advance.
    AJ

    Dear Deepak,
    Thanks for your prompt and useful answer. This would be ideal if i am using the Item Category as "L", but here the material is being issued to the subcontract for a service order with a customized Z.. movement type and consumption is booked with a customized Z.. movement type. The payment of the subcontractor is being processed through a service entry sheet.
    Please suggest how to handle the same if material is issued against a service order.
    Thanks in advance.
    AJ

  • Error during Post Goods Issue of Material in VL02N for STO Purchase Order

    I am getting one error message during Post goods issue of Material for STO Purchase order.
    I am doing the Post goods issue in T code VL02N
    Error is " Account type D is not defined for Document type WL"
    What is the settings required to be done.
    Thanks,
    Shailendra

    Please check Plant customer master reconsilation account properly maintained or not in XD03 transaction.

  • Unit of measure for stock , Goods issue , Purchase.

    Dear All Experts,
    How we can maintain different unit of measure for Stock, Goods Issue, Purchase?
    Regards,
    Sandeep.

    Hi,
    The UOM qualifies the quantity you enter on the
    purchase order line. This will default in if you entered an item number, if not enter
    a UOM of your choice using the List of Values.
    Please Refer the following links...hope it helps you....
    http://help.sap.com/saphelp_45b/helpdata/en/c6/f83bb94afa11d182b90000e829fbfe/content.htm
    http://www.admin.cam.ac.uk/offices/finance/training/manuals/inv_training_stores_user.pdf
    Regards,
    Udaya.

  • How to change Purchase Order currency after Good receipt and Good issue?

    Hi,
    I've a PO created last year. The PO currency has been entered wrongly.
    My store colleague has been performed good received and consumed it.
    Now, I am not able to change PO currency to correct one, due to this message:-
    Currency can no longer be changed
    Message no. 06489
    Diagnosis
    As a basic rule, the currency cannot be changed if there has already been a goods receipt against a document.
    If the document contains external service and/or limit items, or if an invoicing plan has been assigned to an item, the currency cannot be changed following the receipt of an invoice either.
    If external service items exist, the currency also cannot be changed if services that have actually been performed have already been recorded or if the item in question has been assigned to a preventive maintenance (servicing) plan.
    Is there anyway to change PO currency after Good receipt and Good issue? Thanks !

    Diagnosis
    As a basic rule, the currency cannot be changed if there has already
    been a goods receipt against a document.
    If the document contains external service and/or limit items,
    or if an invoicing plan has been assigned to an item,
    the currency cannot be changed following the receipt of an invoice either.
    If external service items exist, the currency also cannot be changed if
    services that have actually been performed have already been recorded or
    if the item in question has been assigned to a preventive maintenance (servicing) plan.
    Answer in question itself,need to cancel all documents of wrong currency in order of LIFO,
    Create a new purchase order.

  • Create service Purchase Order automatically at goods issue in VL02N.

    Hi Friends,
    Please give me steps on how to write the ABAP code To Create  service PO automatically at goods issue.
    Technical Info
    •     BAPI BAPI_PO_CREATE1 is to be used for creating the service PO.
    •     The service PO will be only created for YLF deliveries.
    •     The PO will be created only if the shipping conditions field ( LIKP-VSBED ) has any value except 3rd party or Customer pick-up.
    •     The PO needs to be created when goods issue is performed on the delivery.
    •     The PO needs to be created with the following values :
    1.     Purchase order type : YB
    2.     Vendor : Header partner function SP, Carrier
    3.     Plant : LIPS-WERKS
    4.     Material : 10
    5.     Account Assignment Category : K
    6.     PO Quantity : 1      
    7.     Net price : LIKP-NETWR
    8.     Cost Center : 54434
    •     On failing to save the PO, the error message should be generated so that the user knows the error and can fix the error and create the PO manually.
    Please help for this urgent req.
    thanks.
    Message was edited by:
            anjan
    Message was edited by:
            anjan

    Sure. Here it is:
    Go to SPRO.
    Logistics Execution
      Transportation
        Shipment cost
          Shipment cost document
             Shipment cost type and Item category.
    For the shipment cost item category you are processing, lets say standard 0001 (Transportation costs). double click on it.
    You will find all you need in the tab SETTLEMENT.
    There, there is a field GENERATE PO.
    Select one of the options:
         Do not generate purchase order
    A     Generate purchase order for validity period of 1 day
    B     Generate purchase order for validity period of 1 week
    C     Generate purchase order for validity period of 1 month
    Once the shipment cost is created and transfered to MM(settled), if there no open PO for the carrier, the system creates one.
    Good luck,
    Leonardo De Araujo

  • Purchase order delivery shedule tabl , no Good issue date, loading date.?

    Hi Experts
      We found some Purchase order, in po item, it is without goods issue date, loading date and so on.
    Material has set ATP check on mrp3. what's possbile wrong? something wrong for matieral setup or others?
    Thanks
    Alice

    Hi
    Really thanks for your help. You mentioned " SD delivery of the sending plant is created and processed."
    Do you mean in material master , the sales view -delivery plant will impact this po GI date and Loading date? It maybe something wrong?