Dump IW31 after assigning several people to the work order

I get the following dump when trying to add several people to a WO with IW31:
Runtime Errors         RAISE_EXCEPTION
Date and Time          24.04.2008 09:46:51
Short text
Exception condition "DATA_INCONS_IN_EXIT_MANAGEM" raised.
What happened?
The current ABAP/4 program encountered an unexpected
situation.
Error analysis
A RAISE statement in the program "CL_EXITHANDLER================CP" raised the
exception
condition "DATA_INCONS_IN_EXIT_MANAGEM".
Since the exception was not intercepted by a superior
program, processing was terminated.
Short description of exception condition:
For detailed documentation of the exception condition, use
Transaction SE37 (Function Library). You can take the called
function module from the display of active calls.
Trigger Location of Runtime Error
Program                                 CL_EXITHANDLER================CP
Include                                 CL_EXITHANDLER================CM001
Row                                     155
Module type                             (METHOD)
Module Name                             GET_INSTANCE
Source Code Extract
Line
SourceCde
125
IF is_impl = 'X'.
126
      ok at least one implementation found
127
act_imp_existing = 'X'.
128
ENDIF.
129
130
ENDIF.
131
ENDIF.
132
ELSE.
133
134
check how many implementations exist for an exit
135
CALL METHOD cl_badi_flt_data_trans_and_db=>act_imps_per_flt_val
136
EXPORTING
137
runtime_call                  = seex_true
138
exit_name                     = exit_name
139
EXCEPTIONS
140
singular_exit_multiply_active = 1
141
no_active_implementation      = 2
142
only_default_implementation   = 3
143
OTHERS                        = 4.
144
CASE sy-subrc.
145
WHEN 0.
146
act_imp_existing = seex_true.
147
WHEN 1.
148
RAISE single_exit_multiply_active.
149
WHEN 2.
150
act_imp_existing = seex_false.
151
WHEN 3.
152
act_imp_existing = seex_false.
153
def_impl = seex_true.
154
WHEN 4.
>>>>>
RAISE data_incons_in_exit_managem.
156
ENDCASE.
157
158
new parameter considered for performance purposes
159
IF act_imp_existing = seex_true OR
160
def_impl = seex_true OR
161
null_instance_accepted = seex_false.
162
163
ok, then do your job
164
CREATE OBJECT exit TYPE (abs_type_classname).
165
CATCH SYSTEM-EXCEPTIONS move_cast_error = 1.
166
instance ?= exit.
167
ENDCATCH.
168
IF sy-subrc = 1.
169
RAISE cast_error.
170
ENDIF.
171
172
ENDIF.
173
ENDIF.
174
ENDMETHOD.                    "
Does anyone have the solution for this?
Thanks!

I am using SAP ECC 6.0.
SAP Basis Component and Cross-Application Component: release 700, level 013
Is there any other information you need?
Could I still use this OSS note with this version?
Also, the issue is not about the response time like mentioned in the OSS note.

Similar Messages

  • Modification of the Work Order Program TCode IW31

    I need to do a modification to the work order program. Tcode IW31
    When creating a work order with reference to an old work order, we want to clear any PRT data that might be in any item of the operations tab of the old order.
    My question is:  Which method should I use to get this change done?
    I looked at the badi = IWO1_ORDER_BADI --> the method REFERENCE_ORDER_CHK, but I do not think this is the right one.
    Please help me...
    Thanks.
    Regards,
    Francisco.
    Message was edited by:
            Francisco Alonzo

    To check for the suitable badi, Go to transaction SE24 and give the Object type as CL_EXITHANDLER and click on Display button.
    Double click on method GET_INSTANCE, put a break point on case statement.
    Execute your transaction and look for variable EXIT_NAME at your scenario then It will show the available badi's.
    Reward if it is useful.
    Thanks,
    Srinivas

  • Scheduled start and finish dates in the Work order.

    Hi Friends,
    I am facing peculiar issue that once the Work order has been released schedule start and finish dates should be derived from the control key and
    operation hours and work center capacity,infact in my case while releasing the Work order,these dates (scheduled start & finish) are not been
    populating in the Work order,(but SAP standard behavior is while releasing WO,the dates should be populated).
    though i have maintained proper configuration
    could you please light up some thing on it.
    Regards,
    Srinika

    Check Scheduling Parameters assignment to order type, Scheduling option in Control key.

  • Get Lastest date of the Work Order confirmation

    Hi experts,
    I want to write a report to get the lastest date of Work Order confirmation.Pls give me some logic solution. How to do?
    I know the work order can be cofirmed partly,So there are maybe several date for work order confirmation,I only want get the latest one.
    Edited by: Bean Dou on Jan 5, 2009 8:24 AM

    SORT BY DATE FIELD
    DATA:CNT TYPE SY-TABIX VALUE 0.
    SORT ITAB BY ERDAT. --->SUPPOSE THIS IS THE DATE FIELD
    LOOP AT ITAB.
    CNT = CNT + 1.
    ENDLOOP.
    READ ITAB  INDEX CNT.
    ****NOW YOU CAN GET THE LATEST DATE ROW******
    ITAB-ERDAT.

  • STO creation against the Work Order

    How to specify the source plant or source storage location within PM Work Order for the components/materials.
    Currently on the components page of work order, we can specify the material and vendor. In our case the vendor is other storage location within same plant or diff. plant.
    How can we specify the source in components page so that PRs and reservations are created correctly.
    In details here is the problem-
    During work order (PM Order) creation user is specifying a non-stock material and issuing storage location "0002". The material will be issued by sto. loc. 0002.
    Storage location "0002" sources this material from other storage location "0001".
    So we want to generate a Purch Req. with item category "U", account assignment 'F" (with work order) and ability to specify the source plant-storage location.
    But the system is creating a normal expense PR with account assignment "F" to the work order. This PR is having grayed out item category so not able to convert into Stock Transport STR by specifying the source plant and storage location.

    Hi MM
    Have you solved your problem? What did you do to create the STR?
    Regards
    Eduardo Chagas

  • Display construction type on the structure list within the work order

    I have a work order written against an equipment which has a construction type assigned to it.  When using the structure list from the components tab of the work order, the construction type does not display under the equipment in the list.  If I run the same structure list from transaction IH03, the construction type does display under the equipment.  How can I add the construction type to display on the structure list within the work order?  We are on release 4.7
    Thanks,
    Terry Gaskin

    Thanks PeteA, we know we can do that, but we are looking to get it consistent with IH03, where the construction type shows without being added to the BOM.  The construction type is listed immediately below the equipment in IH03.
    Thanks

  • Approval for material return issued against the Work Order

    Hello,
    We are using PM module and issuing materials against the work order.  Many times users are returning the un-used material back to stores.  This un-used material may come back <b>with or without</b> work order reference.  i.e. Sometimes they just return bunch of material but don't know the work order # against it was issued initially.
    We need to control this flow of un-used return material through proper system approval.
    How can do this.
    Thanks,

    Hi,
    In standard SAP There is no approval process to return the material.
    I have one work around , you can create one PM order to return the material & instruct your store people to receive the material only with reference to PM order.
    With out releasing a PM order, system will not allow to post the goods return.
    I hope it may help you.
    Regards,
    Manish

  • How to refer the work order status value from a different transaction in the step handler?

    Hi All,
    I have a requirement to check the status of the work order from a different transaction before doing some logic in the current transaction. The following transactions are done to replicate the issue
    1)changing the status to ONSITE to edit the work order (transaction 1)
    2)Adding some information which will do some logic (transaction 2)
    3)Completing the work order (transaction 3)
    The transaction 2 will have some logic and will be executed only if the status is COMP but even though the status is COMP now (transaction 3) my condition check in the logic is showing as ONSITE status(transaction.status=ONSITE) and it fails. How can i get the latest status of the work order in the device? Please advice

    Hi Jason,
    The CompleteWorkOrderFinish sub action does have Apply action (screenshot 1) and the transaction definition (screenshot 2)of CompleteWorkOrderFix transaction with the only property Status which has the following settings (screenshot 3)
    Also I am trying to add a status property in EditMeterFitDetaisl transaction and update this value with the current status of the work order using object collections filtering with key value. Please let me know if that approach can be followed. Thanks

  • Generating the RM requirement based on the work order?

    Does Oracle Disceret MFG has the provision of generating the RM requirement based on the work order?

    Hi,
    If you mean RM requisition as Material indent from Stores , then Yes, Component Pick Slip is the form
    Regards
    S

  • How do determine the work orders for a sales order?

    I'm forced to calculate our costs by sales order.  So for a given sales order number, how is this linked to the work order that created the items on the sales order?
    Thanks

    Hi,
    Check this:
    Re: Open Production Orders List with a Field from Sales Order
    Thanks,
    Gordon

  • Final issue indicator on the general data button on the work order

    Hi Gurus,
    can anybody please let me know why the final issue check box is checked automatically even before the goods are issued via migo against the work orders. This check box is on the general data tab of the material entered on the components tab of the work order. Please help. As a result of this, the store room clerk cannot issue the material againsth the work order, because this check mark is checked. I want to understand what is causing the check mark to be checked automaticallu even before tthe materials are issued out
    Thanks
    ANusa

    Hello!
    This might have occured due to completion confirmation of order before goods issue. Generally this happens if final issue indicator is set as default in completion confirmation tab. Please check and reply if problem is something else.
    Regards,
    Vaibhav Mishra
    Edited by: Mishra_Vaibhav on Jan 27, 2011 5:23 AM

  • Performing resource transaction at the work order completion in Oracle

    Hello Guru's
    Is there any way to have Oracle 11g to perform the resource transaction at the work order completion? Currently a resource transaction is performed when work order is scanned in a scan point. What we want to see is resources transactions at the end of life of work orders most likely a wip assy completion transaction. We are seeing that this happens only for bill of material with just one level. We would like see this behavior on BOMs set up using phatom as supply type for the subassemblies (with more than 1 level structure).
    Regards,

    I am using SAP ECC 6.0.
    SAP Basis Component and Cross-Application Component: release 700, level 013
    Is there any other information you need?
    Could I still use this OSS note with this version?
    Also, the issue is not about the response time like mentioned in the OSS note.

  • How do I lock the work order number on my form to not change

    Thanks to everyone who helped on this form.  The work order number is setup to generate according to the date and time, only problem is that it changes everytime it gets opened, can it be setup somehow to lock it in automatically when I send it or the customer sends it back?   Form is attached
    Thanks
    Mike

    Simply put a condition in to test if there is anything in the field .....if it is empty then go ahead and calculate your number if there is something in it then do not calculate the number. Also you shodul not use teh Calculate event for this script. I moved it to the docReady event. It will work on the calculate event but the calc event is fired many times in the normal operation of the form where as teh docReady event is only fired once (when the form loads). This is a much more efficient way to use your form.
    See the modifed attachment.
    Paul

  • BAPI or FM to get the work order number

    Hi
    Kinldy let me know if there is any BAPI or FM to get the work order number (aufnr)  from to Purchase requisition number (banfn) & Item number of the purchase requisition in the order(bnfpo).
    Thanks ,
    Arun

    Table EBKN will help you.

  • Why the "Work Orders" Menu Item is hided in 2005 Edtion?

    David:
      Thank you!
      The "Work Orders" menu item in 2004 edtion is must useful, But it be hided in 2005,Why ?
      and whether can I show it and use it?
      help me, please!
      thank you!

    Fu
    in the SAP help the following is written:
    Work Order Window
    Definition
    The Work Order Window, from earlier versions of SAPBusiness One, has been replaced by the Production Oder. However, if you had open Work Orders when upgrading, the old Work Orders can still be viewed.
    When a Production Order is open, click on the base document icon  on the toolbar to display the Work Order on which it is based.
    i recommend you to use F1 in your sbo client
    and search for "work orders"
    than select title "Work Order Window" and there is everything in Detail !
    regards
    David