Fabrication Industry

Hi All
We are currently working for a Fabrication industry , the scenario is like
FG-1 - Some big structures like Pillars , Joints etc  (UOM - KG)
          similar to this FG-2 , 3
RM-1 - Plates size like 2500X5000X8mm thick     (UOM - KG)  500 Kg approx./plate
RM-2 - "C' Channels sections like 500X500X8     (UOM - KG)
Now the process is like in first operation (cutting) the RM-1 is cut into different small segments like 50x50x8 and so on having different shapes and sizes
In the second operation (Welding) RM1 & 2 are welded together to create FG-1 , also the rest of pcs/kg of RM1/2 are used for FG2 or 3
After that the finishing process like paint etc
Now,
there are no semifinished generated in the whole process
Please tell about the BOM structure to be used , if it like FG =01 >> RM01 - 20kg and further the operation are marked as whole ie cutting >> welding >> painting
Now the client want the stock of RM as in our BOM structure the plates are issued as whole for cutting but in SAP we are only issuing as req. KGS

Dear,
you can use by product concept for process sunk or scrap bridge. In this way, system will update stock of process sunk material and then these material will be part of FG-2 BOM.
Kindly check and revert back
Thanks
Muhammad Ashfaq
Edited by: Muhammad Ashfaq on Sep 9, 2011 9:07 AM

Similar Messages

  • Advance material planning for projects

    Dear All,
    We have a scenario for fabrication industry. Where client want to plan material procurement in advance for manufacture FG. But BOM of FG will come in later stage when design phase get finished in phases. Initial for cost planning and material procurement planning, they are finding out requirement of material quantities and costing happened on it. This material is planned for procurement, while the BOM will prepared in later design stage. FG are assigned to project activities, and project MRP will give planned orders. these material bom will rolled cost to activities, cost will get doubled and material too. How to handle this scenario, Any standard solution.

    Hi Shrikant,
    The advance procurement material list should be prepared and then it should be attached in initial stage to project.
    Header(X)
    Line item 1
    Line item 2
    This advance procurement BOM should be attached such that
    the header(X) will become text item after attachment and
    for the line items the Preq will be generated.
    For this line item should be make to stock procurement type
    and this should behave as dependent and independent requirement
    and there will be no duplicacy of the requirements.
    You need to dicuss this with PP consultant.

  • Industry error while doing replication of customer from R/3 to CRM

    Hi,
    We have production system already implemented and going for roll out for another company both R/3 & CRM.
    We have generated conditional objects while doing roll out phase. From then we are getting this error.
    Problem:
    Customers are not getting replicated to CRM. And in SMW01 the error log says
    "Industry 300 not defined for industry system SAPS
    Validation error occurred: Module CRM_BUPA_MAIN_VAL, BDoc type BUPA_MAIN."
    Since we are going for roll out we have done initial load of all conditional objects
    like 'DNL_COND_A002' etc.
    After running we did checked in R3AM1 - everything was DONE - in green colour.
    But in SLG1 - Display log - there are several entries in Red colour.
    Message text says -
    "It is not possible to change client-independent Customizing objects
    Diagnosis:
    Change of client-independent Customizing objects is not permitted in the client in which the transfer of data for table T682 is executed.
    System response:
    As table T682 contains client-independent Customizing, data transfer is interrupted.
    Procedure for System Administration
    Provide users with the appropriate authorization to execute data transfer in a client in which changes to client-independent objects is permitted."
    Now queues are pilled up with the industry error and don't know how to correct these errors.
    Please help.
    Regards,
    Dhanraj Dange

    Hi pankaj,
    Step 1:After completing Initial Download tranfer of data takes place from R/3 to CRM system in the form of Customers or employess.
    Bulk data will be flown in the first step.
    I f there are any errors ,we solve the errors and replicate them manually by using CRMM_BUPA_map.
    Step2:There are few customers which are created daily in SAP SD or R/3 and these customers are transfered from R/3 to CRM .
    So my question is  Is this b'cos of Delta Download or Bcoz of some other Reason.
    If so "Is there any specific name for this.
    Regards,
    divya

  • Issue in creating a dropdown for Industry sector field

    Hello Gurus,
    Am trying to create a dropdown for Indusry field. 3 dropdown should come up for Industry sector field namely primary,secondary and tertiary.Corresponding to the value selected in primary,data should come up in Secondary and corresponding to value selected in secondary ,data should up in tertiary.Am only able to fetch the value at first instance but corresponding values are not coming up secondary and tertiary.I have followed the procedure that had to be followed in order to make a field as dropdown.Can anyone Please help.
    In get_v , i have added this code.
    DATA:  lt_ddlb  TYPE          bsp_wd_dropdown_table,
               wa_ddlb  LIKE LINE OF  lt_ddlb.
    DATA:
              lr_entity1         TYPE REF TO if_bol_bo_property_access,
              lv_index           TYPE sytabix,
              lr_collection      TYPE REF TO cl_bsp_wd_collection_wrapper,
              lv_high_ind_sector TYPE string,
              lv_istype          TYPE string.
        CLEAR: wa_ddlb, lt_ddlb
        lr_collection = me->GET_COLLECTION_WRAPPER( ).
       lv_index =   lr_collection->get_current_index( ).
      IF lv_index = 1.
    lr_entity1 ?=  lr_collection->find( iv_index = lv_index ).
            lv_high_ind_sector = lr_entity1->get_property_as_string( iv_attr_name = 'INDUSTRYSECTOR' ).
          lv_istype = lr_entity1->get_property_as_string( iv_attr_name = 'INDUSTRYSECTORKEYSYSTEM ' ).
          CLEAR: lv_high_ind_sector.
    ELSE.
          lv_index = lv_index - 1.
          lr_entity1 ?=  lr_collection->find( iv_index = lv_index ).
          lv_high_ind_sector = lr_entity1->get_property_as_string( iv_attr_name = 'INDUSTRYSECTOR' ).
          lv_istype = lr_entity1->get_property_as_string( iv_attr_name = 'INDUSTRYSECTORKEYSYSTEM ' ).
        ENDIF.
        SELECT aspras aind_sector atext INTO CORRESPONDING FIELDS OF TABLE GT_IND_SECTOR FROM tb038b AS a INNER JOIN tb038a AS b ON  bistype = a~istype
    AND bind_sector = aind_sector
    AND b~istype = lv_istype*
    AND b~father_sec = lv_high_ind_sector.
      Loop at GT_IND_SECTOR into wa_ind_sector.
          wa_ddlb-key   =  wa_ind_sector-ind_sector.
          wa_ddlb-value =  wa_ind_sector-text.
          Append wa_ddlb to lt_ddlb.
        endloop.
        IF lt_ddlb IS NOT INITIAL.
          INSERT INITIAL LINE INTO lt_ddlb INDEX 1.
        ENDIF.
        IF GR_DDLB_INDUSTRY_SEC IS NOT BOUND.
          CREATE OBJECT GR_DDLB_INDUSTRY_SEC
            EXPORTING
              iv_source_type = 'T'.
    IF sy-subrc = 0.
            GR_DDLB_INDUSTRY_SEC->set_selection_table( it_selection_table = lt_ddlb ).
    ENDIF.
    ENDIF.
    rv_valuehelp_descriptor =  GR_DDLB_INDUSTRY_SEC.

    Hello,
    Not sure I understood your requirement 100%, but kindly check the following thread where a question on How-to make dropdown list values dependent has already been answered:
    How to link the first Drop down values witht the second Drop down Values
    Regards,
    Nicolas Busson.
    PS: also it would be good to know your CRM version... because I thought this thread was posted in the WebClient forum, but it's not.

  • Industrial Design & CAD -- Switching to Mac (Within A Company)

    Hi all.
    With the stalled global economy, our IT budget is frozen here at my company, probably for at least a year. So, what better time to ressurect my case for Macs at work to replace our Dells? If you can help, please read on...
    I'm an industrial designer in a small group (8 persons full-time in North America, with an additional 5-or-so contractors) within a large manufacturing company (3000+ employees globally). We use mainly Photoshop, Autodesk Sketchbook Pro and Illustrator as our 2D apps, which are all available for OSX. We also use Microsoft Office, and there is an OSX flavor of that, too. Unfortunately, we also use Autodesk AutoStudio, which is currently available only for Irix, Linux & Windows. I'm not even sure if it supports Vista or 64-bit. That's our main 3D app, though. A couple of virtual showroom apps, but we're more flexible on that (while we network our AutoStudio licenses, something like Autodesk's Showcase would, I believe, run just fine with a locall license under bootcamp).
    My Dell Precision 690 is a good machine, actually. What I don't care for is the "long arm of the law" our IT group has put in place in terms of how it piecemeals out applications.
    For example, I cannot open Illustrator documents out of Bridge, as one would expect. I must view the file in Bridge to know what I want, go back to Illustrator and manually search by filename. This is due to the odd installation process they've put in place here. Illustrator should be installed along with the rest of CS(2, in our case) in order to function properly, something we're unable to do with our setup. Also, I have been having major file-renaming issues with Illustrator that our IT department is both unable and unwilling to solve, as well as what appears to be an expired support contract with Adobe.
    It seems that we overpay IT for every last piece of hardware & software, with very little benefit in terms of warranty or service. One example is when we paid $1000 for a (then, now cheaper) $500 Wacom tablet. I figured that "double-the-price" setup ensured us some sort of replacement warranty, but when I did have technical problems, we paid for both the service call AND the replacement hardware. Gadzooks! Despite the perception of Macs as being more expensive than Window-boxes, not only was this Dell box I'm using pretty pricey, but all the IT charges, I'd like to think we could offer a cost improvement by "breaking out" of the system.
    So, my motivation is political. But it is also that I have a preference for OSX when it comes to networking, using Adobe applications & overall appearance (both the interface and also of my physical workspace!)...
    Anyone here ever had to make an IT case to "break away" a creative department from the parent? Any hints in terms of business case of maintenance costs of Macs vs PCs? Service contracts with Mac people? Any helpful links or books you could recommend? I've been Googling some terms with no luck.
    I think my ultimate proposal would be to keep on "company" Dells over in the (shaded, depressing) corner of the room for email & CAD work, but to use Mac Pro (or MacBook Pros) for our 2D work. Until Autodesk lists Macs as "approved hardware" on their site, we'll never convince to company to go the bootcamp route (even though I know a colleague who's been using AutoStudio on Windows on a Mac Pro 17". Says it works flawlessly).
    Anyway, any help or words of wisdom would be appreciated. Also, please feel free to share your own experiences with proposing a "switch." Things to watch out for, etc. Also, if there is another place (either here at Apple or elsewhere) you'd suggest I post, please let me know that, too. It's a bold new world, baby.
    Thanks & apologies for the length.
    -Chris H.
    ps/ Below it says I use a PowerBook G4. This is my personal computer. At work, I'm using a 2-year old...
    Dell Precision 690
    Intel Xeon CPU
    5160 @3.00 Ghz
    3 GB RAM
    Windows XP Professional, 2002 , SP2
    We have networked (floating) profiles using a locked-down flavor of XP (nothing but bright blue task bars, all day long. When it comes to Windows, I'm a "classic" man. No such luck here...).

    Hey Chris,
    I'm also an industrial designer but switched over to exhibit design from product design years ago. I was lucky to develop the dept. when the need for computers was new. (12 years ago) I went Mac all the way and we still maintain a strong Mac presence in the design dept. We have detailers still on ACAD on there PC's. Our outside IT guys are difficult to work with and high priced. The Macs never need the amount of attention the PC's get from the IT guys. We use FormZ as our 3d modeler and it exports and imports dwgs nicely. I've heard of Solidworks and Vellum for the Mac for more detailed work. Lightwave, Modo, Formz, Cinema 4D and Maxwell for renderings. (the pretty pictures that sell)
    Are you guys able to switch apps? After a few new hires to our dept, they came in w/ 3DS experience and pushed that. It was easy to say it would be a lateral move and all the money to invest in that direction would only give us the same results at the end of the day. BUT, our IT bills would have been more if we did move to the PC side. Maybe if windows7 is ok, i may load it, but have no reason too.
    I found it interesting that if you get a virus on the windows side, while using a mac, you can use TimeMachine to go back before the virus; what I was told from someone at an Apple store. I thought that was big and shocked APPLE doesn't sell that more.
    Anyway, keep us posted on your progress.
    Good luck.
    Mark

  • Best Practice for manufacturing Industrial Machinery in batch size

    Dear Sir,
    We have a scenario where we need to manufacture Industrial Machine in a Batch Size of 10 nos . These machines have multi level BOM and total manufacturing cycle time is approx 3 months .
    We request you to kindly suggest us about the best manufacturing practices related process we should follow to address this scenario .
    At present , we have been manufacturing these Machines on individual basis ( It means MRP run is done for individual machne and production orders generated are also on individual machine manufacturing basis) .
    We would be highly greatful for the suggested solution pl .
    Rgds
    Sonia Agarwala

    Dear ,
    Please use the following functionality in your case :
    1.If you are particualr to have 10 pc in each batch qty then keep the Lot Size as Fixed Lot Sixe -FX with Fixed lot size qty as 10 in material master MRP1 view .
    2.As your approximate manufacturing cycle is 3 motnhs , then you can have MRP run once three months for FG   and plan your dependent accordingly through MRP .
    3.If you are following MTS cycle , then create demand in MD61 or you can create direct Sales Order in VA01 for MTO process
    4.Run MRP with NETCH ,1,1.3,3,2 , planned order with FG qty 10 pc will be generated  and you can convert them into Production Order in MD04-Planned order-convert to PO
    Regards
    JH

  • Processo de recebimento de mercadorias em consignação industrial

    Bom dia amigos,
    Alguém tem o processo de entrada de mercadorias em consignação industrial implementado e funcionando no SAP ?
    Pelo que vimos, ele trata tudo na mesma conta de estoque da empresa, e também não tem um processo standard para devolução simbólica dos itens.
    Vimos que o movimento 821 não trata também esta entrada como estoque especial.
    Alguém pode por favor nos dar algumas dicas de como foi tratado este cenário, as contabilizações aceitáveis no SAP, entre outros.
    Grato a todos,
    Alessandro

    Oi Alessandro.
    A devolução é feita via NF writer (J1B1N).
    Você chegou a dar uma olhada na documentação disponível no marketplace?
    Visão geral do processo
    Procedimento
    Guia de configuração
    Abraço
    Eduardo Chagas

  • Inventory Management for Airlines Industry

    Does Oracle offir a solution that allows an airlines to manage its inventory? I have a customer who has heard and read that Oracle's Inventory Management module will work with the special requirements of the airline industry. Is this true?

    Hello,
    Currently they are havingSAP-HR.But i want to integrate HR with inventory management(Like issue,receipt,scrap,consumption)

  • Daily Stock Report for a trading industry

    Hi,
    I want a daily stock report for a trading industry. In this i want date wise opening stock, closing stock, outward quantity and inward quantity. How to get it?
    Thanks,
    Niranjan

    Hi,
    This is not easy as you think you have to develop this report by using SQL Query / Crystal report...
    Regards
    Chidambaram

  • Relationship Between BP, Contract, Contract Account and industry

    Hi,
      Anybody can send  the relatonship diagram between BP,Contract, Contract Account, and Industry , with Relation ship fields,
    Regards,
    Sivakumar.

    Can u send me your mail id, So that i can mail u.
    These relation is your business specific.....
    If u want i can send you.......
    Regards,
    Shiv

  • Relationship between material type and industry sector

    Hi experts
    when using t-code mm01,there are two fields material type and industry setor in screen.Is there any relationship between material type and industry sector? I want to know if user be able to see the material type related to particular industry sector?
    thanks in advance!

    Hello
    There is no direct relationship between the material type and the industry sector.
    The industry sector is used only for field sttus maintenance (fields in display/optional/requierd entry) in transactions.
    We will assign seperate field reference groups to industry sectors and deopending on how we configure the field references, the fields will appear for the materials created for that industry sector.
    regards

  • What is the scope of Live Customer Support in the Software and IT Industry?

    The Software and IT Industry is growing at a pace of 9.0% per year, with employment at Software consultancy and service firms projected to grow making it the second best industry to start and grow a business. With this pace of growth in the ruthless world of online business, only companies which succeed in creating their own niche will survive and make it big.
    Surviving this kind of competition demands a change in business strategy to create a loyal customer base, i.e. a solid investment in repeat visitors. One tool that can bring about this change in business strategy is the use of Live Chat.
    A Live Chat Operator’s role is a Software and IT Company website can be from navigation help and customer service to expert consultancy and making direct sales. Behind all of these roles though, is the constant element of the human touch on a website. Chat with a Live Operator can create an experience for web visitors which will make them come back. This creation of repeat web visitors will create a loyal customer base. This industry particularly relies on customer loyalty, since in the computers and electronics category repeat visitors are nearly 16 times more likely to make a purchase than new visitors with conversion rates of 23.12 percent and 1.49 percent respectively.
    Apart from creating repeat visitors on Software Company’s website, Live Chat Operators can do the following:
    1.     Win loyalty by providing top level service on your online store
    2.     Provide real-time answers about models, year and price of the electronics or computers that visitors are looking for.
    3.     Show items; push pages and take visitors directly to the model/price range they are looking into.
    4.     Use three dimensional images to show products.
    5.     Generate leads.
    6.     Provide consultancy on items keeping in view customer needs and price range
    7.     Update visitors on Promotional Offers,
    8.     8. Improve Multitasking in Customer Service and Sales Staff.
    Live Chat is a medium which takes online customer service to an unparalleled level; the days of static web information and the email black hole are long gone.
    Source:
    http://www.liveadmins.com

    Hi Dkdinesh,
    Excelent links provide by M.R.AshwinPrabhu!
    In 2014, Microsoft will release BizTalk Server 2013 R2 (release date will be soon) and also will keep investing and improving Microsoft Azure BizTalk Services-
    Microsoft goal in terms of Release Cadence of BizTalk Server is to have one major release every alternate year (the last one was BizTalk Server 2013, so you may expect a new major release in 2015) and one minor release every alternate year (that will be
    designated R2, so the next on is BizTalk Server 2013 R2). The major release will have new features and themes and minor releases will have bug fixes, platform alignment and customer asks.
    Sandro Pereira
    DevScope | MVP & MCTS BizTalk Server 2010
    http://sandroaspbiztalkblog.wordpress.com/ |
    @sandro_asp
    Oporto BizTalk Innovation Day | 14th March 2013 – Oporto, Portugal
    Please mark as answered if this answers your question.

  • Industry sector field for display only.

    Dear All,
    Does anybody know the setting to make Industry sector for display only, so that the enduser cannot change industry sector while creating material.
    I know to hide industry sector from DEFAULTS menu, but i need to freeze that field for display only.
    Regards
    Rang

    Hello Ranganath,
    You can use transaction exit. for more information check this thread.
    Industry sector (MBRSH) field in display mode.
    Hope this helps.
    Regards
    Arif Mansuri

  • How to change material type and industrial sector of the exsisting material

    Hi,
    There is an issue where user wants to change material type and industrial sector of the exsisting material .Is  it posible to do so??
    IF not ,how can we delete that material from material master so that another material with same number and required material type and industrial sector  can be created.
    Points will be definitely rewarded.
    Thanks
    Rohit

    Hi Rohit,
    You can change the material type in MMAM trxn code if the material dosenot conatain any open purchase requisitions, open reservations & open purchase orders. Also material stock should be zero.
    Remember the new material type should have same attributes same as old material type.
    OLD Material New Material
    1) Standard Price 1) Standard Price
    2) Manufacture part 2) Manufacture part
    profile actvated profile actvated
    3) Quantity & Value 3) Quantity & Value
    Updation in all areas Updation in all areas
    4) should have same GL 4) Should have same GL acs
    acs
    It is not possible to change Industry sector once created.
    If you want to delete the Material, you can flag it in MM06 trxn code.
    Reg,
    Ashok
    Dont forget to Assign points if useful.

  • Hyper-V as User on Windows Embedded 8.1 Industry Pro

    I believe I'm having permission issues when attempting to use Hyper-V on Windows Embedded 8.1 Industry Pro.  Hyper-V seems to install cleanly, and from an admin account I can use the Hyper-V Manager without issue and connect to a running VM.  However
    if I attempt to use the Hyper-V Virtual Machine Connection application from the same account, it reports "You do now have the required permission to complete this task..." And attempts to run either the Manager or the Virtual Machine Connection result
    in the same on a standard user account.  
    Standard wisdom seems to be to add the user account to the "Hyper-V Administrators" group but when I've looked in the Computer Management utility and the group "Hyper-V Administrators" does not exist. I've tried manually adding full
    permissions to the WMI interfaces for CIMV2, StandardCimv2 and Virtualization namespaces through the WMI Control Properties interface. I've also added the user to the "Administrator" role for Hyper-V services in AzMan as a long shot.  Beyond
    this, I'm not sure where to go next.
    The end goal is to be able to run the Hyper-V Virtual Machine Connection Utility from a non-administrative user. Any advice is appreciated.
    -Matthias

    Your question might be more general to Hyper-V and not specifically embedded. WE8.1 is Windows 8.1 with lockdown features so there is nothing special. Account level (Administrator vs. non-administrator) does effect what permissions are granted to access
    certain OS features.
    Maybe the Hyper-V forum can address the account level -
    https://social.technet.microsoft.com/Forums/windowsserver/en-US/home?forum=winserverhyperv
    Sean Liming - Book Author: Starter Guide SIM (WEI), Pro Guide to WE8S & WES 7, Pro Guide to POS for .NET - www.annabooks.com / www.seanliming.com

Maybe you are looking for

  • QM IDI integration with xMII

    HI Guys, We are looking for the options of integrating QM IDI interface with xMII. Anubody has experience with this type of integration ie integrating xMII with QM IDI. Any help or suggestions would be appreciated. Thanks, Srini

  • My imac has been experiencing power shutdowns.

    I have paid for a power supply and logic board but still experiencing shut downs. Apple is now stating it might be a software issue. If this is a software issue can I ask for my money back for the power supply and logic board?

  • Encoding issues sending accentuated characters

    Hi, My company operates in a French market within North America and a lot of people from our sales department use accentuated characters (é,à, û, etc.) within their emails. Some complain about characters being translated into ? (question mark) signs

  • Message deleting and tablespace size

    I have run deleting job for xml messages and history. But the size of Oracle tablespace is not reduced. Is it my mistake or tablespace will be clean later?

  • Tabs keep opening on their own even though I only work in new windows.

    Since the last Thunderbird update I'm having trouble with random(?) emails opening in tabs, even though I don't use tabs. It's annoying to have to keep closing all these tabs that I didn't open and don't even use in any way. It's a distraction. I'd j