FICO month-end?

Hi,
if i only use FICO module; do i need to run month-end?
regards.

Hi,
some of teh month end activities
1) All the expenses including amortization, prepaid expenses, Preliminary expenses and accruals have been booked.
2) Complete Bank Reconciliation
3) Make sure that Sum of Inter company balances is Zero
4) Suspense Accounts should be cleared regularly.
5) Ensure that all documents related to MM & SD have been entered in system.
6) Ensure that all billing documents are released to accounting.
7) Calculate Overheads on all process Orders (CO43)
8) Technically complete all process orders which are fully processed (CORM).
9) Calculate Variance (KKS1)à (Relevant only if Standard cost is calculated).
10) Settle all process orders which are technically complete (CO88).
11) Close All settled Process Orders
12) Close MM period (Transaction Code: MMPV).
13) Carry out GR/IR clearing (F.13) transaction
14) Depreciation Run (AFAB) has been carried out for the month
15) Close FI Posting period after the month end closing activity is over.
chandra

Similar Messages

  • Month End Activity

    Hi All,
    What are the month end activities in FICO ?
    Thanx
    Andy

    Hi,
    . All the expenses including amortization, prepaid expenses, Preliminary expenses and accruals have been booked.
    2. Complete Bank Reconciliation (T.Code: FF67)
    3. Make sure that Sum of Inter company balances is Zero
    4. Suspense Accounts should be cleared regularly.
    5. Ensure that all documents related to MM & SD have been entered in system. (T.Code:F-22 & F-43)
    6. Ensure that all billing documents are released to accounting.
    7. Calculate Overheads on all process Orders (CO43)
    8. Technically complete all process orders which are fully processed (CORM).
    9. Calculate Variance (KKS1)à (Relevant only if Standard cost is calculated).
    10. Settle all process orders which are technically complete (CO88).
    11. Close All settled Process Orders
    12. Close MM period (Transaction Code: MMPV).
    13. Carry out GR/IR clearing (F.13) transaction
    14. Depreciation Run (AFAB) has been carried out for the month
    15. Close FI Posting period after the month end closing activity is over (T.Code:OB52)
    Year end closing Activities:
    1. Calculate production work in progress on process orders which are not technically complete. (CO88).
    2. Carry out Assessment cycle for Cost Centers.(T.Code: KSUB)
    3. All month end closing Activities should be carried out.
    4. Carry Forward Balances to next year
    With TC: F.16 we can carry forward the balance to next year.
    With TC: OBH2 copy the number ranges to next year
    Open next year periods by selecting the Posting Period Variant.
    then test by posting the transaction in F-02)
    SAP FI Month End and Year End Activities
    1 - Maintain Activity prices - KP26
    2 - Release of Standard Cost Estimate - CK40N
    3 - MM period close and open - MMPV
    4 - FI period open
    5 - Parked documents to be posted - FBV0, MIRO
    6 - Reposting of Inter Office CC - KB61
    7 - Bank Reconciliation
    8 - Update Section Code where missing - J1INPP
    9 - Maintain GRIR clearing - F.13
    10 - Provision for current month - FB50
    11 - Depreciation entry - FB50
    12 - Exchange rate - To be Updated
    13 - Revaluation of foreign currency open items - F.05
    14 - Recognition of Inventory at Bonded warehouse - FB50
    15 - Maintain Statistical Key Figures - KB31N/KP46
    16 - Variance Calculation of Process Orders - KKS1
    17 - Settlement of variances - CO88
    18 - Assessment cycles - Aux/WH CC to Main CC - KSU5
    19 - Assessment cycles - Functional CC to SBU CC - KSU5
    20 - Assessment cycles - SBU CC to COPA - KEU5
    21 - Profit Center Reposting - 9KE0
    22 - Balance Sheet Adjustment calculation - F.5D
    23 - Transfer Profit Center to AR & AP - 1KEK
    24 - Transfer Inventory to PCA - 1KEH
    25 - Assessment Cycle - Dummy PC to SBU PC - 3KE5
    26 - Check for u201CDelivery made, not Invoicedu201D  - VF03
    27 - Match GL and PCA - KE5T
    28 - Match PCA and PA
    29 - Top Down Distribution in COPA - KE28
    30 - Reclassification of GL balances
    31 - Balance Carry forward (Year End Only) - F.16
    32 - PCA Balance Carry forward  (Year End Only) - 2KES
    33 - Transfer to FI - 1KE8
    Thanks
    Prasada

  • Month end and year end closings

    hello guys,
                  Can anyone explain me about the series of steps that we have to do for month-end and year-end closings (FICO).
    Thanks in advance..

    Hi,
    Below are the month end activities
    1. Recurring Documents.
    a) Create Recurring documents
    b) Create Batch Input for Posting Recurring Documents
    c) Run the Batch Input Session
    2. Posting Accruals or Provisions entries at month end
    3. Managing the GR/IR Account-Run the GR/Ir Automatic Clearing
    4. Foreign Currency Open Item Revaluation-Revalue Open Items in AR.AP
    5. Maintain Exchange Rates
    6. Run Balance Sheets –Run Financial Statement Version
    7. Reclassify Payables and Receivables if necessary
    8. Run the Depreciation Calculation
    9. Fiscal Year Change of Asset Accounting if it is year end
    10. Run the Bank Reconciliation
    11. Open Next Accounting Period
    Assign points if useful
    regards
    genie

  • Month-end

    Hi friends,
    I have some knowledge of month end acivities.
    here i mentioned ....
    1)Open and close posting periods in FI….OB52
    2)Close MM period…………..MMPV
    3) Collect and post all outstanding vendor Invoices……F-43
    4) Collect and post all customer Invoices……F-22
    5) Post accruals/deferrals ……FBS1
    6) Generate Recurring entries….F.14
    7) Run the interest calculation…..F.52
    8) Maintaining Exchange Rates …… OB08
    9) Run the foreign currency valuation….F.05
    10) Run depreciation run……..AFAB
    11) GR/IR clearing account ….F.13
    12) Complete Bank Reconciliation………FF67
    Please any mistakes rectify and any another acivities mentioned  the with T.codes.
    pls let me know.
    Regards,
    Chandra.

    Hi
    Other few activities given below:
    FI
    1. Depreciation Run - AFAB
    2. F.5D Balance sheet adjustment calculation
    3. F.5E Balance sheet adjustment Post
    4. F.05 Foreigh Currency Valuation.
    CO
    1. CO43 Overhead calculation
    2. KKAO - WIP Calculation
    3. KKS1 - Variance Calculation
    4. CO88 - Settlement
    If you think it helpful kindly assign the points
    Thanks & Regards
    Mahesh

  • Doubt in mm, where to transfer gr/ir balance in month ending

    In the month end if Gr/Ir Account is showing some balances due to pending of invoice verification. What we will do at this situation. Is there any configuration needed, to deal with the situation.
    Thanks in advance.

    HI G.Kiran ,
    Its a normal process, if it is invoice is penditng then month end GRIR Accounts will have the balance.  Need not to do any things.  If you want to do manual Calaring for GRIR Clearing Account after inovice being generated then  do F.13/F-44.
    Regards

  • GR/IR at the month end

    Hello,
    What we have to do with GR IR account for clearing at the month end.
    Regards
    Ravi

    Hi Ravi,
    GR/IR clearing is the month end activity. To do this first you should maintain gl accounts under open item managment.
    the GR/IR Clearing account is used to account for Goods Receipt and Invoice entry for the vendor invoices. The GR/IR clearing account program reclassifies the entries in GR/IR account as either assets or liabilities for reporting purpose. At the period end which goods receipt has been done and for which Invoice has not been recd or goods for which invoice has been done and GR has not been done. During the time between invoice being created and delivered the goods. To accommodate this timing difference a gr/ir clearing account is maintain temporarily to record the flow
    hope it will useful and pl assign points
    thanks
    venkat

  • Regarding Month End reports

    Hello SAP Experts
    I got a requests from SAP user that
    for SAP report (T-Code for report) List of GR IR Balances to be part of the month end processing. Can this report be automatically scheduled as part of month end.

    Hi ,
    Please use see below reprot
    MB5S - Display List of GR/IR Balances
    EWM6 - Reconcile GR/IR Clearing Account
    S_P6B_12000135 - List of GR/IR Balances
    Amd MR 11  to clear any dis cripancey in GR and Clearning is F.13
    Many Thanks

  • I can't be the only person who has this problem - when a month ends on a Saturday I can't drag events into the next month and instead have to cut and paste - a real pain in the butt. I thought there was something called "scroll" but I can't find that

    I can't be the only person who has this problem with iCal- when a month ends on a Saturday I can't drag events into the next month and instead have to cut and paste - a real pain in the butt. I thought there was something called "scroll" but I can't find that.

    Yeah that works, but, it involves a click on the event, a click on edit, a click on the date, keystrokes, plus, since you can't see the next month you have to have a calendar in front of you so as to put it to the right date. It's easier just to cut it and advance the month and paste it, once you are in the right month you can move it around helter skelter willy nilly no problems. Although now that you mention it I will try it, maybe it is easier than cut and paste as I don't really care about the date, as long as it gets moved into the right month I can drag it around all I want.

  • Delivery Block at PGI level based on GI date and Month end date

    Business need a check on delivery processing based on the Planned GI date, Month end date and transit period. This transit period is a custom field and dependent on customer. Also it is not maintained anywhere in system. Business store it in some excel format.
    The logic needed is: For any given month, the delivery order MUST be goods issued in the same month, i.e. once the order is delivered, the Post goods issue should ONLY be allowed if and only if , the PLANNED GI date ( as maintained in delivery ) + transit time ( at customer level ), falls within the month end date. If not, a block should be applied at PGI and only authorized personnel should be able to release that block.
    Also, there will be no check at invoicing VF01 level. Once the PGI blocked is removed, there will be no check on invoicing. The month end date may vary month to month and need to in combination of Sales Org / Plant as mentioned
    In addition, the business need an exception report where the information of releasing the block should appear for release date, user id of the responsible person, time sales order no etc. and it should be downloadable.
    We can have a custom table to maintain the month end day in given combination.
    But I need your expert inputs as-
    1-     Can we add this transit period in at customer master data as it is dependent on customer and there are huge no of customers for the sales unit? If not, then how to maintain it; may be a z table?
    2-     Based on this logic, what should the code/logic to be written for block at PGI.
    3-     How to control the authority check for removing the block.
    4-     The source fields for exception report.
    Pls revert accordingly.
    Many thanks in advance.

    Hello,
    Please refere the answers to your questions:
    1- Can we add this transit period in at customer master data as it is dependent on customer and there are huge no of customers for the sales unit? If not, then how to maintain it; may be a z table?
    You can either use some un-used Feild in Customer Master or maintain a Z-Table. I believe maintaining a Z-Table would be easy as you have huge number of Customers. You can also write a dmall program to Pick the Customer-wise transit dates from a excel file & store in Z-Table.
    2- Based on this logic, what should the code/logic to be written for block at PGI.
    You have explained the requirement well in your thread, you need to explain the same to your ABAPer & Basis person & they would do the needful.
    3- How to control the authority check for removing the block.
    Basis person would create & assign a Z-Authorization object which the ABAPer would use in his program.
    4- The source fields for exception report.
    Once you do the above development, your ABAPer will easily pick the required feild in Report as he has already used all the feilds somewhere in his development.
    Hope this helps,
    Thanks,
    Jignesh Mehta

  • Month end accrual posting date- Last day of the month

    Hi Experts,
    I have set up month end accruals for PY US by configuring posting dates, LDCD, WageType accrual processing class, Schema changes. I have also set the closing dates as the end of the month.
    Now after I do the posting , there are three documents getting generated.
    1. Accrual posting document with first day of the current month
    2. Normal Payroll posting  document with payroll period posting date
    3. Accrual reversal document with first day of the following month.
    My Question is:  As per standard SAP configuration, the month end accrual will have first day of the month. Can we customize this to end of the month for doc#1 - accrual document?
    Please do let me know your suggestion and ideas.
    Thanks,
    Amosha

    Hello,
    I have a similar question and I hope to have more details on how to change the posting date.
    The point is that I have an amount of 1200 and I have to post 100 for each month.
    Key Date for Accruals: 31.01.2011
    I posted 100 with Document date: 31.01.2011 and Posting date 31.01.2011
    Key Date for Accruals: 28.01.2011
    I posted 200 with Document date: 28.02.2011 and Posting date 28.02.2011
    Also I reversed the amount posted in the previous month (100) with Document date: 31.01.2011 Posting date 28.02.2011
    And so on...
    The problem are the dates because I need to post the amount at the end of each month (28/02) and to reverse the previous amount at the beginning of the next month (01/02).
    How can I change these dates?
    Thanks a lot in advance
    Kind Regards,
    E.

  • Direct Posting of Sales in FI and month end closing

    Dear Experts
    I learnt that :
    Sales Direct Entries may be posted in FI without posting in SD/MM.
    Sales entries must always be posted only through SD process. If this is NOT done (for example freight rate received from third party freight forwarders), then only FI people should know how to reconcile and NOT sd people. Hence I recommend posting your query in FI forum after closing this thread.
    Regards,
    My question is , during month-end closing how should FI or accounting address the above direct posting issues?
    Apparently, such practice is not right.
    There is no trace of the sales in SD MM. There is no corresponding billing doc in SD MM but found in FI .
    How should this situation be handled as best practice?
    I am BI person but found this issue with FI data not reconciled with SD MM.
    I am not sure how the month-end closing was done when there is such data. Yes, the problem was found AFTER month was closed and I loaded the data to BI.
    best regards
    Pascal

    Dear Sirs
    What is the fastest easiest way to find out which FI direct entries were posted without corresponding Sales / Billing documents created ?
    Is there any standard report or reports available in oss?
    Currently, our other interfacing systems are having problem with data due to direct entries where there is no corresponding Sales / Billing docs posted. This is causing a lot of time investigating what entries caused the reconciliation problem.
    Your help would make my life easier.
    Thanks!
    Regards
    Pascal

  • ICR Process 003 Month-End Cut-off

    We have implemented ICR process 003 in the 5.0 system.  It seems that "posting period" relates to the period that the document was posted in ICR not necessarily to the customer account.  How can we get a good month-end cut-off when new documents are posted all the time.  For instance, when we run FBICS3, FBICA3, and FBICR3 after the new period begins, it will pull in documents created in the new period and all still open before in previous periods.

    Hello Staci,
    The period and year you enter on the selection screen is combined with the fiscal year variant maintained in your process customizing to derive a key date for open item selection. The open items are then selected in the sender system and stored in the year and period specified on the selection screen in the ICR database. This is also explained in the first message that is displayed in the log of data selection.
    Best regards,
    Ralph

  • Asset Under Construction(AUC),During month end settlement run(via KO8G)

    Hi Guys ,
    please hlep on this AUC :
    During month end settlement run (via tcode KO8G), if there are -ve (credit) values to be settled to an Asset Under Construction (AUC) asset which does not have sufficient +ve value in the current FY, the settlement run will prompt an error message "Balance for transaction type group 10 negative for the area 01". The TT posted via the settlement run is TT115. To get around, user has to raise a manual journal (via doc type AT) to post the -ve value to the same AUC asset via TT101. TT 115 and 101 are configured differently (see attached).
    Since the Fixed Assets system does accept credit posting to AUC via a journal, is there a solution to make posting go through via the settlement run?
    Regards,
    Narra

    You can settle the AUC value in one period and posting can be made in another period. in the same you can give the different asset value date in KO88 screen. The only limitation is this possible only if the fiscal year is same.
    Give the asset value date as 15.07.2007 in KO88
    Hope this will work
    Radha

  • Month End Payment Batch

    Greetings to All,
    In AP, we are looking for concurrent request called: Month End Payment Batch, which is supposed to find any eligible payments to be created.
    We are using 11.5.10.2 and can not find this process.
    We have checked ML and can not find any notes on this process, but when we search the web, we get alot of hits saying that this process is availabe.
    http://it.toolbox.com/wiki/index.php/Period-End_Processing_in_Oracle_Payables_(Release_11i)
    "Optionally Run a Month End Payment Batch
    By running a month end payment batch, you may arrange a payment for as many due invoices as possible."
    Has the process been renamed in 11.5.10.2?
    Any help would be greatly appreciated.

    Hi
    There is no any specific concurrent request to run payment batch or there is no renaming of any process within this version.
    You are actually required to follow a series of steps to create your payment batch. You initiate each step from the Payment Batch Actions window, or, for payment batch sets, from the Submit Batch Set window. You can also schedule payment batch sets to automatically submit at regular intervals.
    Major steps that are required to create payment batches:
    1 Initiate the payment batch by entering criteria for invoices you want to pay. Payables selects invoices and builds the payments; it determines which invoices will be paid on each payment document and lists this information for you on the Preliminary Payment Register.
    At any time before formatting, you can optionally modify the payment batch. You can prevent payment to a supplier, prevent payment of a particular invoice, change the invoice amount, or add an invoice that Payables did not originally select.
    2 Format payments to have Payables produce an output file.
    3 Print checks from the output file, create electronic payments, or deliver the output file to your bank to disburse electronic payments.
    4 Confirm the payment batch by recording the document numbers associated with each payment. During this step Payables updates the invoice status to paid and associates a payment number with the invoice and invoice payment. Do not send checks to suppliers before confirming the payment batch.
    Payables creates a Final Payment Register which you can review to verify the completed payment batch.
    After confirming the payment batch, you can review the Payment Batch Control Report to verify the accounting of the invoices you paid. You can submit this report after every payment batch to compare it with actual payment information. You can also use this report to provide your check signer with comprehensive information about each payment document, eliminating the need to review paper invoices. The
    report displays payment, supplier, invoice, and expense information.
    You can check the status of a payment batch at any time during the payment batch process by checking the Status field in the Payment Batches window. You can also check the status of payment processes in the Requests window...
    Refererence:
    online document liabrary:
    http://download.oracle.com/docs/cd/A60725_05/html/comnls/us/index.htm
    Hope this clarifies
    Shanks

  • How to define payment term - Net due 45 days after month end

    Anyone have experience of payment terms such as "Net Due 45 days after Month End"?
    I'm trying to define payment terms where the amount is due X days after month end.
    Terms such as 10 days after month end are OK because I can set "Months Ahead" = 1 and "Day of Month" = 10
    However, I can't exceed a value of 31 in the "Day on Month" field. I could assume that a month is 31 days and therefore set "Months Ahead" =1 and "Day of Month" = 14. However, this won't always be true (depending on the month) and it will impact aging buckets.
    Anyone encountered this before? (These payment terms seem to common in France and Denmark)

    Hi Supriya,
    In OBB8, create a new payment term with the following settings -
    Default for baseline date = No default
    Payment terms/Term 1/Fixed date = 1
    Payment terms/Term 1/Additional months = 2
    This payment term will ask you for a baseline date on document entry. You can give the delivery date as the baseline date. If required, this date can be changed after posting the document also.
    Hope this helps.
    Regards,
    Mike

Maybe you are looking for

  • "unable to delete" file on 6267

    I have a Nokia 6267 S40 phone made for Malaysia and I am in the US. I've got a file that I cannot delete from the phone memory (no mem card) which seems to be causing problems in other applications. It is a downloaded video file with the extension .3

  • How do I Install Classic on 10.3.9?

    I already have Classic on my wife's computer internal HD. I'm now setting up an external drive from scratch with the DVD install that came with the computer 10.3.7 . + updates 10.3.9 I'm not sure (don't remember) if OS9 classic came with OSX 10.3.7,

  • IS IT POSSIBLE TO CHANGE THE DEFAULT WEB PRESENTATION OF IFS?

    We have a web application that has links to specific documents and directories stored in IFS. For example, there could be a link that resolves to this URL within IFS: http://oraifs-pd.nbme.org:8002/ifs/files/home/ads/systems/CLOP/Minutes/Inventory/ W

  • Upgraded to Snow Leopard/lost all iCal previous info and Firefox bookmarks

    I had previously had a major problem with an Apple automatic update and went thru lots of time and trouble, especially with Safari. After more time than I wanted to spend with Applecare...finally having to do a clean install...I was told all was okay

  • TIMEZONE question on 10.2.0.1.0

    Hi Experts, Env: Sun Solaris 8 DB 10.2.0.1.0 -- Single instance a) I did set env variable as TZ=UTC b) When I check SQLPLUS from server, it is fine. i.e. It shows time in GMT SQL> select to_char(sysdate,'DD-MON-YYYY HH24:MI:SS') from dual ; TO_CHAR(S