Fixed Scrap Quantity In Production

Im using SAP ECC 6.0 now.
Is there any place I can set a fixed scrap quantity in BOM or PP related?
The situation is like this: While producing Semi-finishegoods A we alway need extra 10 Raw-mateiral B for scrap.
That means 100 A needs 110 B ; 10 A needs 20 B;
How can I configure it so that when I create the procution Order for 10 A, it will put 20 B in the components automatically;
I can only find scrap ratio in percentage.
thanks alot for looking into my problem.
Edited by: Liang Shi on Aug 25, 2010 7:08 AM

Hi
As you rightly mentioned ,  to my knowledge, as of now in standard SAP
All the SCRAPS are maintained in %  only.
1) Component Scrap >>>>> Maintained in MRP4 in % & also in BOM General data tab
2) Assembly Scrap >>>>>> Maintained in MRP1 in %
3) Operation Scrap >>>>>>Maintained in BOM item detail  General Tab in %
Regards
BRSR

Similar Messages

  • Fixed Scrap quantity

    Hi Experts,
    We have "Fixed Scrap Quantity" field group in the opeartion details of routing in SAP Mill Products.
    Can any body please explain the siginificance of Each Length, First Length and Last Length.
    Regards,
    Jejesh

    This option works with APO only

  • Fixed Scrap

    Dear All,
    We are manufacturing bolts. In every production order we create there is a loss of exactly 5 bolts, where do I define this fixed scrap quantity (not percentage)

    Rafik,
    As you said the quantity is fixed for every order i.e. 5 pcs each & not the percentage then better you maintain the same in the order itself, in the scrap field.
    Because that is the output of the different percentage you maintain in material master or in BOM.
    There is no other alternative I can thought to tackel the problem.
    Hope this helps you.
    SmanS

  • Scrap Quantity component  in the production order

    Dear gurus,
    in the material master of a component i insert the scrap % ( view mrp4) = 10 %.
    The field is read by planning Mrp and explosion of bom , but when i inseert this component in the production order manually the system don't read this % and the field "scrap quantity in the component detail of the production order is blank.
    Are there a setting for uograde this field ( in the production order ) when i insert MANUALLY the component in the production order?
    Example:
    1) material master of the component  > scrap % (view MRP4 ) = 10 %
    2) production order created
    3) insert this component quantity 100 pc and the system after read the material master  insert 110 pc , and upgrade the field automatically 10 % (as material master)?
    Thansk a lot
    Daniele Pistilli
    PP TEAM

    Hi Danielepistilli,
    Well there is a lot of difference is there: see you are creating production order for header material which is FG. If you maintained component scrap in material level it will be dependent on BOM quantity which you maintained for the header material.
    For example say component x quantity is 50 in BOM. How it will calculate when you run the MRP.
    component scrap % is 5% then:
                                     ===>            (5/100) * 50 + 50
    Formula is: Percentage of scrap quantity x original quantity + original quantity
      So                           ===>           52.5 quantity should be come for component
    So, the order quantity for the header material will not take this quantity or scrap but if you see individually in MD04 screen for X material you can find this quantity ok.
    I hope it clears your doubt and helps you any queries please revert me back.
    Regards,
    Madhu.G

  • How can I set a fixed scrap qty on planned orders created by MRP?

    During production of some specific subassemblies, destructive testing is done that requires us to scrap two pieces per production order.  I know I can set an assembly scrap percent, but what I need instead is a way to set a fixed assembly scrap quantity that will get loaded onto every planned order created by MRP for these subassemblies.  If we can't do this, we can't plan the correct order quantity and eventually end up being short of parts.  I know we can set a safety stock or safety time, but I'd rather just plan the right quantities if possible.
    Is there a user exit, configuration option, or master data setting that will allow me to do this?
    Thanks,
    Randy

    Hi Randy
    This can be solved by one solution. _You can try this._
    You define the same item in BOM again with qty 2 nos. Double click on the item no. Then it will take you to item detail. There in Basic data tab page at quantity data  ( Tick the fixed quantity. ).
    When ever BOM explodes for the header material automatically The item will be exploded 2 nos extra.
    Ex
    The header is Mat X and items is Mat Y. While creating BOM for X give item Mat Y in item no 10. give the quantity as per the requirement.
    And again give item Mat Y in items no 20. give quantity 2 nos and activate the fixed quantity tick as instructed above.
    When ever requirement for Mat X is 100 nos. The plan order for Y will be 102 nos .
    Hope this will clear.
    Regards
      J .Saravan

  • No Data in Field Scrap quantity (AMGLG) after Append DataSource 2LIS_04_P_COMP (Component View from PP/PP-PI)

    Hi experts,
    we enhanced the BI Content standard DataSource 2LIS_04_P_COMP "Component View from PP/PP-PI" with the field AMGLG (Scrap quantity) per maintenance of the relevant extract structure MC04P_0COM via LBWE:
    The enhancement of the extract structure worked fine.
    Unfortunately the enhanced field is not filled after the Statistical Setup of the LIS Application 04 "Production" (t/code OLI4BW).
    RSA3 -> 2LIS_04_P_COMP:
    Any ideas or experiences?
    Many thanks in advance and regards,
    Michael

    Attached one example:
    BW DataSource 2LIS_04_P_COMP:
    ERP Summarized BOM Multilevel (t/code CS13) Component 456:
    ERP Summarized BOM Multilevel (t/code CS13) Component 301:
    Any ideas why there are no values for the field AMGLG extracted?
    Thanks and regards,
    Michael

  • Fixed Days Supply & Fixed Order Quantity

    Hi,
    in certain cases we use the Fixed Days Supply & Fixed Order Quantity attributes in the Item Master to influence our ASCP plan calculation (size of planned orders etc.)
    We need this because we do discrete production (semiconductor industry) and with the fixed order quantity we to ensure that the system plans with full Lots.
    However I am not sure what the impact of the Fixed Days Supply is, especially in combination with the Fixed Order Quantity.
    Unfortunatly the Manuals do not tell very much about this. Does anyone have experience with this and wants to share some knowledge? I would like to know what these parameters really do and maybe there are better ways for our setup...
    Thanks,
    David.

    Hi,
    thanks for the reply. I found the detailed explanation in user guide you mentioned.
    I am not sure that we made the setup in an optimum way.
    We use for example fixed days supply = 5 for many buy items, because we place weekly Purchase Orders for these items and want to have the planned orders combined instead of having a planned order for every day.
    And we use the fixed order quantity to prevent two things:
    1) The size of the planned order gets below a typicall Lot size and the calculated leadtime for this planned order is too short. We define item based resource usage rates so it will calculate the exact lead time for the small planned order, but in reality our production has to run the full Lot which takes more time of course.
    2) without the fixed order quantity the planned orders might become too big, which makes scheduling of them more difficult, because finding a free time-slot on the machines for a huge quantity must be more difficult than for a smaller planned order.
    But unfortunatly Oracle does not provide some business cases, especially for our semiconductor industry so it is more trial-and-error what we are doing...
    regards,
    David.

  • Fixed Order Quantity

    Hi,
    we are using ASCP together with SFM. We do descrete manufacturing for our products. The products flows look like this:
    - asssembly item A (finished good item)
    => is make item (has routing), uses component3
    - component3 is make item, uses component2
    - component2 is make item, uses component1
    - component 1 is buy item
    So the flow of material looks like this:
    component1 -> component2 -> component3 -> assembly4
    (buy) (make) (make) (make)
    In production we typically process only full Lots/Batches with a certain quantity depending on the component1.
    We want that ASCP plans always full Lots, because the leadtime of the full Lot is always needed in reality. If ASCP plans with partial quantities, then the estimated/calculated leadtime for the planned orders will not be realistic.
    To achieve this we want to use the Fixed Order Quantities, however it turned out that we run into several other problems if we use this parameter. For example it happens that system recommends to buy material (component1) just for the sake of the fixed order quantities.
    We are running into issues if we enter the Fixed Order quantities, and we get other issues if we leave this empty.
    I am looking for someone who has experience with this parameter and can give some recommendations. Maybe we use the wrong approach and there are other paramters that we should use to achieve what we want.
    Big Thanks in advance,
    David.

    Sub: "We want that ASCP plans always full Lots, because the leadtime of the full Lot is always needed in reality. If ASCP plans with partial quantities, then the estimated/calculated leadtime for the planned orders will not be realistic."
    Oracle ASPC has some more meaningfull logic in Lead time calcualtion. It is not that Lead time will be wrong when you Process the low batch. On the other hand lead time goes up when you use Fixed order Quantity , irrespective of Demand. It also files up your inventory.
    See for example, If you have fixed order quanitity for an item say 1000 numbers;assume that you have on hand for 500. and need to refill balance 500.
    What will ASCP recommend you ?..1000 numbers.It files your invenotry...Does this mean that lead time for producing 1000 is less as compared to 500!!! also is it acceptable to produce extra 500..
    .It also make you to plan low levels adversly with case cade effect...
    You issue is not lead time...You are talking about setup time. If you produce more batches, you are occuring the more setups for same items. it makes lead time more lengthy considering the setup time. This is your problem and wanted to limit this or wanted to make it optimization. (Is it right my observation of your problem??)
    How to control...?. Rather than speaking about lead time , let us talk in other way ...what is the Planning perid do you want want to conisder while planning a batch or lot size?. In other words let us take an example,,,
    Component2 has a lead time of say 30 days for 1000 numbers. At the same time, I am able to accamadate only max 1000 numbers. If the demand goes up ,say for example, 2000, then I need to have two batches. If the goes less than 1000 and demand split in time gap ...for exmaple, 500 in first of week of may and 200 in last of week of may, still I want to consolidate 500+200 into one batch and want to Plan 700 as it is less that 1000.
    If the above condition matches..you need to use Min Order/Max orde qunatity and Fixed days supply together. This is the wonderful way it controls the objective as stated above.In this example you will set min 1 , max 1000 and fixed days supply to 20 days.
    How ever in some cases if the demand comes likes this, say for exmaple 2000 and 2000, then there is a recommendation to produce 1000,1000,1000,1000 with due date as equal to first lot. However, if you use constranied based planning, APS will reshdule and give you best possible time slot. Other wise, if there is enoguh capacity you are still able to produce 4 batches in first due date. The result of this behaviour depends on EDD and ECC and will vary.Make it understand this and do test case..go ahead..
    Thanking you,
    dr

  • Scrap quantity

    Hi,
       we doing cofirmation in co11 with auto goods receipt(last operation).
       Is it possible to get production order list which having scrap quantity in COOIS
    thanks in advance

    Dear,
    Once you have entered scrap in CO11N no material movements are automatically posted in the system. By confirming scrap you are only reducing the balance confirmable qty in the order. The order costs would increase since you would have posted goods issue for input material without goods receipt for finished goods
    Now you want to realize the value of the scrap produced then you would have to do a goods receipt of the scrap as a by-product using movt type 531 in MB1C for the scrap material number
    In COOIS,I dont think you will get all your required details.
    In case if you want to confirm scrap then enter only scrap qty and confirm the production order,
    the production order show the status as
    REL CNF DLV.
    Regards,
    R.Brahmankar

  • Scrapped quantity and malfunction breakdown time

    Hi SAP Gurus,
    How can I determine the scraped quanity and Malfunction breakdown time for the order number in production planning?
    Suppose I have the order number and I need to search for the scrapped quantity and from TCODE IW29 I need to determine from MALFUNTION BREAKDOWN TAB.
    Please throw some light on this....
    Regards,
    Hemal

    Hi,
    In IW23 for the display notification, in maintainace data tab page check the required date and time is entered. if so remove that and save it.
    now u see in iw29 the down time.
    Thanks & regards.

  • SCRAP QUANTITY IN ORDER CONFIRMATION

    Hi,
        When i confirm an order there is a field called scrap quantity. Supposse there is an order for 10 qty. Now while confirming the order i give in the yield field as 10 & 10 in scrap quantity where will it effect...
    Will it effect costing of the order.
    Can i do like this because my order is for 10 quantity & i am confirming & scarping the same quantity.
    Please guide as i want to use the same field..
    I am in go live satge.Please help.
    regards
    jimmy

    Hi JIMMY 
    As per your question smiltensly you can't book both as yield and scrap with same order quantity.Either you book 10 in yield or in scrap or total of this yield and scrap is equal to production order quantity.That means if order quantity is 10 then you may book 6as yield and 4as scrap.Once you have entered scrap in CO11N no material movements are automatically posted in the system. By confirming scrap you are only reducing the balance confirmable qty in the order. The order costs would increase since you would have posted goods issue for input material without goods receipt for finished goods.
    Now  you want to realize the value of the scrap produced then you would have to do a goods receipt of the scrap as a by-product using movt type 531 in MB1C for the scrap material number.
    It can also automate posting of this if a percentage scrap is know. You can do this in BoM by specifing a negative qty against the scrap material number. Then if the backlash is activated every time confirmation is done the 531 movement line will come automatically in goods movements screen. If no scrap arises then you have to delete that line and post the confirmation.
    Hope this helps ...if so reward points and close this thread.
    regards
    Rajesh

  • Fix date/Quantity in the sales order schedule line

    Dear SD Gurus,
    When we select the fix date/quantity in the lsaes order item schedule line, what happen? Hhow does it imapact the MD04,V_V2 and can this item be seen in CO06 to change the item date manually?
    Thanks
    J.Black

    With fix/date and qty, you can't use rescheduling and back order processing. The setting assumes that you want to fix the date at the time of initial confirmation and therefore these functions are not relevant, and ignore anything with fix/date and qty.  If you want to use those functions then don't use fix/date and qty.
    Rgds
    Richard

  • Report that list stock quantity by product code or stock group

    hi,
    any one has code similar to this logic that lists stock quantity by product code or stock group?
    Thanks & regards
    Ruban

    hi,
    I am closing this thread

  • Calculate fixed order quantity by using econmoic order quanity

    Hi experts,
    i have one requirement
    price of pen is 2/-
    order costs per order is 6/-
    holding costs per year is 15%
    the demand forecast is 5,00,000 pen per year. SAP ECC offers more detailed information for the next two weeks:
    days        week day          demand forecast
    1            mon                1300
    2            tue                 1400
    3            wed                1200
    4            thu                 1000
    5            fri                    1000
    6            sat                  1300
    7            sun                 1400
    8            mon                1500
    9            tue                  1400
    10          wed                 1400
    11          thu                  1300
    12          fri                    1400
    13          sat                  1400
    14          sun                 1400
    in that
    question a:
    calculate the fixed order quantity by using economic order quantity model for this material! outline the general EOQ formula and show how you apply it to this example.
    <b>points will be rewarded..</b>
    its an urgent..
    regards,
    priyanka reddy.

    Hi experts,
    i have one requirement
    price of pen is 2/-
    order costs per order is 6/-
    holding costs per year is 15%
    the demand forecast is 5,00,000 pen per year. SAP ECC offers more detailed information for the next two weeks:
    days        week day          demand forecast
    1            mon                1300
    2            tue                 1400
    3            wed                1200
    4            thu                 1000
    5            fri                    1000
    6            sat                  1300
    7            sun                 1400
    8            mon                1500
    9            tue                  1400
    10          wed                 1400
    11          thu                  1300
    12          fri                    1400
    13          sat                  1400
    14          sun                 1400
    in that
    question a:
    calculate the fixed order quantity by using economic order quantity model for this material! outline the general EOQ formula and show how you apply it to this example.
    <b>points will be rewarded..</b>
    its an urgent..
    regards,
    priyanka reddy.

  • Fixed operation Quantity- Execution factor

    Dear All
    SAP NOTE:
    Use of Execution Factor
    Use the execution factor to indicate how many times an operation or sub-operation is to be carried out during processing of an order.
    The execution factor refers to the work, the operation duration, the operation quantity and the material quantity.
    If the indicator fixed operation quantity was set, the execution factor has no effect. If the indicator fixed lot was set, the material quantity remains unchanged.
    Where i can find Fixed operation quantity and fixed lot indicator field in project builder.
    Thanks
    Shobana

    Please refer this SAP link:
    http://help.sap.com/saphelp_erp2005/helpdata/en/0f/28b904c3e511d194f900a0c93033d8/frameset.htm
    i.e.
    If the indicator Fixed lot quantity is set (in the component item under General data), the execution factor of the components is not taken into account for the component quantity.
    If the indicator Fixed op.quantity is set (on the external processing screen of the operation), the execution factor is not taken into account.
    Hope this will help you.
    Regards,

Maybe you are looking for

  • No data in Daily Activity Report

    Hi expert, There was no data in Daily Activity Report. But I changed the interval to 'Hourly', it displayed normally. Why? the version is 7.0 SP17 Regards, Sidney

  • Error message when downloading ebooks

    I cannot open any downloaded books on my computer- I am getting an error message c:users/mom/downloads/(name of book) .acsm application not found I unistalled adobe and reinstalled but it keeps happening I have gone through all the programs on my com

  • How to connect steps in business scenario

    Hello, After creating a project in Solution Manager, creating a business scenario in that project and creating a custom business process in my scenario, Iu2019ve defined the necessary steps that I want in my process. These steps involve 2 different l

  • I think I get a malware in my iMac and Ipad

    When I look for a website in Safari and then I clic to get in another link in the same website, safari get me into this website http://dca14d4e.megaline.co/url/http://www.unav.edu/web/facultad-de-filosofia-y- letras The same thing happens with my Ipa

  • Workflow vs. assignment engine

    Is there any advantage of using the assignment engine vs. equivalent workflow rules? I find the workflow more powerful in terms of use of expressions and flexibility.