Generate External Service PR from Process order

Hi,
i want to generate a PR for external service on an operation fro the process order and then make a service entry sheet against it, is this possible in SAP? I set the control key accordingly, a PR is generated but it is not for external service, it is working well for subcontracting. It is possible to generate PR for external service manually but i want to automate the process.
Thanks

Hi Muhammad Naveed,
In PP cycle we do not use the concept of taking external services. External services is hiring a vendor to come to your plant and do the servicing for your equipment. This is followed in plant maintenance module.
In PP cycle, we only send the material outside to vendor for doing a certain operation using PR - PO (subcontracting scenario).
Hope you are clear.
Regards,
Naren

Similar Messages

  • Automatic Transfer Order for GR from External vendor and from Process Order

    Hi Expert
    We need to implement the logic for automatic transfer order,
    the Idea when we Receive the Goods from Vendor and while posting goods via Migo we want that the system create automatically the TO.
    the same approach to be implemented for GR from Process Order we need that the system create TO directly to the right Bin
    Your support is higly recommanded
    Olfa

    Many thanks for your support
    I made what you illustrated in your previous message for the Mvt type 501:
    There is a pop up screen which displayed asking me to create TO for Material Document
    Please find attached the related screens
    And please note that the Material Master was updated accordingly
    Please note
    Please correct me if I made a wrong step
    Regards

  • External Number gneration for process order creation

    Hi,
       I need to generate external number range for process order creation and at the time of goods receipt.
       How can I do this in the include ZXVBZU02.
    Regards
    SAi

    You might want to try search first:
    http://www.google.com/search?hl=en&source=hp&q=externalnumberrangeforprocessordersite%3Asap.com

  • Total Quantity generated from Process Order

    Dear Experts,
        Can you help me on how to find the total quantity generated from process order.
    Example: I want to see for a particular material what is the total quantity converted in COR6N for a particular period.
    Thanks

    Got the report from COOISPI items list. Thanks

  • Partial reversal of a goods receipt from process order

    Dear All
    Could anyone please help me with explaining how to do a partial reversal of a goods receipt from process order? If Iu2019m using trans CORS I have to cancel the entire operation, which I donu2019t want to do. If Iu2019m using MIGO and MT 102 I only reverse the goods receipts of the produced material, the corresponding components from the BoM is not reversed with MT 262 as they are if I cancel with CORS, and I donu2019t want to do a second MIGO transaction in which I cancel the components with MT 261. I have also tried to create an operation with a negative quantity, but without any success.
    Itu2019s not an option for the business to reverse the entire quantity and then perform a new goods receipt with the right quantity.

    Hi again,
    I have been trying to do the reversal with CORR but Iu2019m getting the error message u201CMixed confirmation types (time ticket/time event) are not allowedu201D, message number RU179.
    Anyone who can help me on the way?
    /WM consultant on unknown territory

  • CRM- Find Service contract from Internal Order Number

    Hi Friends,
    I would like to know how to get service contract from internal oredr number.
    From service contract we can find internal order number by using CRM_ORDER_READ function module- table et_document_flow, but my requirement is how to find service contract from Internal order number.Any function module or BAPI available for this requierement ?
    Regards
    Vinayak Sapkal

    Hi,
      when the costs are transferred from CRM to R3, they are posted to an internal order. When a service order or incident is transferred to R3, we have to create an internal order for it, regardless of whether or not a contract has been assigned.
    This is all linked to the logic used in CO to find the appropriate internal order. It works as follows:
    The internal order is stored in the table IAOM_ASSIGNMENTS. This is accessed by a guid (the account assignment guid).
    To get this guid, there is a second table IAOM_EXT_OBJ_INF. This table links the GUIDs coming from CRM, dependent on the CO Customizing for CRM (Mass Controlling, Header level, item level controlling etc.)
    This is how we manage to link a service order to the internal order of a contract in the first place.
    When we call CO, CO first looks for an assignment for the object guid passed. If a service order has been linked to a contract, nothing will be found for the object guid. CO will then check for assignments to the reference guid and find the contract entry.
    If no contract has been assigned, CO will create an internal order based on the service order guid.
    From a CRM point of view, costs are assigned directly to an item, and so it makes no sense to have a reference guid for the costs or the possibility to change the guid via BADI.
    regards
    Waman

  • Deletetion of  service PR from maintenance order

    Hi Experts ,
    Is it possible to delete service PR from maintenance order. If it is created from order due to some problem I want to delete it ,so is it possible ?
    With best regards,
    AVI DDS.

    Hi
    Deletion of PR from Maintenance Order is not possible because the PR is created automatically
    This PR will get deleted automatically when you cancel//teco/complete the order
    Otherway around is you can always block the PRs
    Regards
    Kartik

  • Goods receipt from Process order

    Dear experts,
    when you made GR from process order it doesn't appear in the report KKBC_ord or any report related to the comparison between actual and target for Orders I don't know the reason so because of that there is not target costs in the report So please I need your advice for this issue.
    thanks
    Nassar

    Hi
    Kindly check that a valid standard cost is available in the material master.
    Real target cost comes when you do the variance calculation so you need to do that.
    Regards
    Rajneesh Saxena

  • Auto generated service PR from maint, order

    Dear Experts,
    As you know while processing external services using control key PM03, a service PR will be generated for the service selected from the agreement or contract & from there we will create PO.
    Here in my case while creating PO from auto generated PR it is not carrying the condition type ( Discount entered the contract).Instead of that it gives the option to enter the condition type in the drop down list.Then we can select the condition type as discount & process the order.
    where as for the same service from the same agreement,if we create the PO from the manually created PR (not the auto generated from maintenance order) it carries the condition type of agreement (discount) to PO & the discounted price will be displayed automatically.
    Why it is not happening to auto generated PR? is there any particular settings are available? is there any notes available?
    Please help me out to come out of this problem.
    Thanks & best regards,
    Praveen

    Dear,
    I am extremely sorry for this issue. there was some problem with the program & rectified the same.
    Thanks & Best regards,
    Praveen

  • Service PR from PM order

    Hi gurus,
    Is threre any way to stop PR generation from PM order, when i select any service with control key PM03 , because i am not interseted in planned cost, but need to book service required in PM Order at the time of planning.
    Any standard config or any customisation.
    thanx in advance

    you can do teh folowing change in SPRO , then yu will not get the PR from maintenance order;
    Go to
    Maintenance and service processing-->Maintenance and service orders>Functions and settings for order type->Define change document,collecctive PR indicator,operation no interval.
    Inside this there Select PR never.
    But as Pete said what you means by planning . Your query is not cleard. what you want to do.anyway by this PR will not be created.

  • Can we create service po from sales order

    HI
    can we create sales order from service po. if yes then how can we do so.

    Hi,
    we can create po from sales order in cross docking functionality.
    The steps are
    Sales order > Purcahse requistion > Purchase order > Inbound delivery with reference to purchase order and PGR > Outbound delivery with refernce to sales order and PGI > Invoice and billing.
    Br,
    Tushar Patankar

  • Batch number determination from process order

    Dear Gurus,
    I need when I'm receiving on a process order, the batch number is copied from the batch of the process order.
    Regards,
    MaX

    Yes, it is possible depending on the setting of your order type (IMG -> Production Planning for Process Industries -> Process order -> Master data -> Order -> Define Order Type-Dependent Parameters)
    If here, in the combination plant - order type, there is the setting in Process data documentation area on "Batch record required", then batch can not be changed in process order after the release.
    If the setting is in one of the other two options, then you can change the batch after release.
    Bye

  • Change the resource from process order

    Hi All,
    I have 60 to 70 process order i want to change the resource of operation 0010 for all the process orders. Is there any transaction i can do the  change of resorce from all process order?
    satish kapartiwar
    Edited by: satish kapartiwar on Jun 20, 2008 11:39 AM

    Hy Satish,
    As Mr. Prashobh has said there is only two ways two do the same.
    One is change by BDC or LSMW and
    Second is by capacity leveling.
    One more option is don't change the Resorce in Process orders , but during the Phase Confirmation by Current Confirm Resource.
    Regards,
    Dhaval
    Edited by: Dhaval on Jun 21, 2008 11:43 AM

  • Passing 'Service Level' from Forwarding order to Freight order

    Hi All,
    If I create a Forwarding order with Service Level "XYZ" and create a freight order from it,
    the service level 'XYZ' is not passed on to the Freight order Service Level field.
    Instead of 'XYZ' it is empty.
    When investigated found out that, freight order will take Service Level defined in the corresponding Freight order type.
    In my case, the Service level in Freight order type is left Empty.
    Is there any workaround to bring the Service level from FWO to FO?
    Thanks & Regards,
    Michael.

    Hi Michael,
    It depends how you are creating a FO from forwarding order. Do you have FUs as linkage or you are creating FO directly by using FUBR?
    Thanks & Regards,
    Tarun Kumar

  • Goods receipt from process Order, different plants same warehouse

    Hi All,
    Would really apreciate guidence on my issue below.
    We plane to implement the following Org Structure:
    Plant A                 Plant B
        Warehouse 0001
    warehouse 001 shared by both plants
    I execute a process order in plant A, when I perform Goods Receipt against the process order will it show under Plant A or both Plants A & B.
    Plant A executes for Plant B as Plant B is new and all master data is set up in Plant A.
    My hope is to get the business to execute Plant B process orders in Plant B but this will require huge effort I think as masetr data will need changing etc.
    Thanks
    Stuart

    Hi,
    If you post GR in Plant - A, then the stocks in the warehouse will reflect for Plant - A & not in Plant - B.
    Although the warehouse is the same, it is linked to the combination of Plant & Storage location. You can check the warehouse stocks using LS26, just specify the warehouse number & material number.
    But there is also a concept of planning plant & production plant, so Plant A can be where the planning takes place, while Plant B is where the actual production takes place. In this case, although you produce in Plant B, the GR will be done in Plant A.
    Hope the above clarifies.
    Regards,
    Vivek

Maybe you are looking for

  • Excise duty credit in custmore sales return

    Hi Experts When we receive the sale return from customer we follow the below process. Create sales order with order type sales return Create return delivery. It create stock for return material. VF01 Accounting entry pass in customer account. J1IH fo

  • Add a link to an image in iBooks?

    Is this possible? I can't seam to add any links to an image that I placed in the document.

  • Attach a digital signature to SQL mail

    How do I use an email certificate to sign email sent using SQL Mail? I have a certificate installed so that I can sign email sent from Outlook. This is on SQL Server 2005 using either Database Mail or SQL Mail.

  • How do I empty iTunes cache.. what is a .plist?

    Hi, I am using iTunes v7, I have updated my cover-flow and now I keep getting the spinning beach ball, fairly regularly... about every two minutes, and it will spin for a minute or so before coming back... I have read in the forums that emptying the

  • Interactive Form Help

    Hi All, I created a Interactive Form, but I do not want anyone to have the ability to save their data on the original form; they can "Save As" and rename it anything else with their data, but I want to keep the original form blank...not sure if this