Goods movement from Maintenance order

Hi Experts
I have the following scenario,
I have a component ( with Material master) in the maintenance order  and i use Item category N to trigger  a Purchase requisition. The Pur Req is converted to Purchase Order and then the GR is done directly to the order .
Now i have not used this Component  and want to make a goods movement to place it in stock. So the requirement is to move the material from Maintenance Order to the Storage location .
How and which movement type can i use to do this ?
Please help
KK

Hi,
Click the below link for more information
http://sap-img.com/plant/in-pm-how-to-return-material-backflushed.htm
regards,
Venkatesan Anandan

Similar Messages

  • Automatic Reservation from Maintenance Order

    Hi,
    I have a problem. Generally from Maintenance Order type PM01 under Order Category 30, when we give some materials requirement, SAP automatically generate reservation for those materials and take the GL as Consumable Item.
    But in my case, that GL has to be changed depending on what perpose we are using the material. But Manual reservation is not allowed for the order category 30 and no GL can be changed for automatic reservation.
    Can anybody suggest any way-out so that we can give our desired GL No. for the reservation for Maintenance order (say Order type PM01 under category 30 which is SAP internal).
    Thanks in advance,
    Satadal

    Thanks for your answer. Actually I found that place, it is determined from OBYC transaction with a combination of GBB (A/c Key) and VBR (A/c Modifier).
    But for same movement type261, I need manual G/L allocation at runtime. i.e. depending upon case to case, the G/Ls will be different. So, different movement type perhaps would not serve the purpose.
    Basically I need to over-write the G/L for automatic reservation created from PM in the PM01 order type with category 30 where manual reservation is not allowed.
    Can you suggest any way out so that I can actually over-write the G/L for automatic reservation- through SPRO or some kind of development...
    Thanks
    Satadal

  • GR from Maintenance Order

    Hi All, Please help in the below issue,
    there's a spare part material valuated with split valuation as follows:
    Defected avg price 10/EA
    Used      avg price 20/EA
    New       avg price 30/EA
    From PM module, one EA from defected valuation type issued and the accounting doc shows value of 10 (correct), after finishing maintenance work on this part it will receipt in the same sloc but with valuation type Used,
    the issue is when GR from order the accounting doc shows value of 20 (debit stock with 20) the current price in master data while the actual cost from maintenance order is 200 how to make the GR valuated with actual cost from maintenance order which is 200.
    Your help will be highly appreciated, Thanks in advance.

    Greetings Hossam,
    Looks like what you are trying to achieve is to implement the Refurbishment Order process.
    In the standard system, you can use the Order Type configured as a refurbishment order to settle the actual cost to your stock value.
    Say that you have the material master created with split valuation, as you mentioned.
    Defective avg price 10/EA
    Refurbed avg price 20/EA
    New       avg price 30/EA
    Say you have 1 EA of Defective material at €10 , your refurbishment Order actual cost total is €15 , your material price is Moving Average, and you have no other stock. You would then issue the Defective part to the order with mvt type 261 (Order total cost goes up to €25). Then you would receive the 1 EA Refurbed part from the refurbishment Work Order with movement type 101. (Order total cost drops to €5). You would subsequently settle the Work Order total to the stock of the Refurbed valuation, raising the moving price from €20 / EA to €25 / EA.
    Please refer to the documents on Refurbishment process, search the SCN, and feel free to ask any specific questions.
    Refurbishment Order - Customer Service (CS) - SAP Library
    Creating a Refurbishment Order - Customer Service (CS) - SAP Library

  • Goods receipt from PP order

    I need to make the goods receipt in Standard price. When I change for example time operation in routing PP order this changing price for goods receipt from PP order.
    I create PP oder from SD. I need if urgently.
    Thanks.

    Hi,
    While you do a goods receipt ( thru confirmation or thru MB31) an accounting document will be created in the back ground.
    To find this,
    In MB51 transaction give your user ID,posting date, movement type (101 for GR for a pp order)  as selection .
    Double click on the relevant document ( posted by you).
    In the next screen you ll find a "Accounting Documents" button. Click on that , it ll give a pop up..select the G/L document in that.. It ll take to you the account document..there verify the price.
    And check whether it matches with the material master.
    Thanks & regards
    Mahesh Babu

  • Tick for goods movement in production order

    Hi,
    I have one query with reference to tick for goods movement in production order.
    Where it comes from as soon as i released the order.
    Is there any customized setting or it is stanadard functionality?
    Tushar

    Hi,
    I am not sure about which tick you are talking. So pls clarify exactly which check boxes you are talking in Production Order.
    If you are talking about check boxes of Goods Receipt,  GR Non valuated & Delivery Completed check boxes then those are standard SAP functionality which comes automatically at the time of creation / release of the order.
    Revert with more details in case your query is not resolved.
    Regards,
    Tejas

  • Partial reversal of a goods receipt from process order

    Dear All
    Could anyone please help me with explaining how to do a partial reversal of a goods receipt from process order? If Iu2019m using trans CORS I have to cancel the entire operation, which I donu2019t want to do. If Iu2019m using MIGO and MT 102 I only reverse the goods receipts of the produced material, the corresponding components from the BoM is not reversed with MT 262 as they are if I cancel with CORS, and I donu2019t want to do a second MIGO transaction in which I cancel the components with MT 261. I have also tried to create an operation with a negative quantity, but without any success.
    Itu2019s not an option for the business to reverse the entire quantity and then perform a new goods receipt with the right quantity.

    Hi again,
    I have been trying to do the reversal with CORR but Iu2019m getting the error message u201CMixed confirmation types (time ticket/time event) are not allowedu201D, message number RU179.
    Anyone who can help me on the way?
    /WM consultant on unknown territory

  • Default GL account upon goods issue to maintenance order based on activity

    Hi all,
    There's a scenario here in Plantation Industry that we require to default GL account upon goods issue to maintenance order based on activity type assigned in the order instead of only posting to consumption account, is there anyway in OBYC or user exit able to fulfill requirement mentioned?
    Thanks as advanced.

    Hello
    With help of general Modifier in combination of valuation class you can assign GL as per your wish for offset posting incase of GI to order/anything
    Example
    Transaction key-GBB
    General modification- VBR
    Valuaction Class - checked
    Dr/CR- checked
    Assign the general modifier to T code MIGO , through OMJJ
    Regards
    Dinabandhu

  • PR Delivery Date Issue from Maintenance Order

    Hi All,
    We have a scenario -
    - Create Maintaince Order (IW31)/Assign Basic Start Date and Basic Finish Date.
    - Auto PR Generated from Maintenance Order but the delivery date in PR is Basic  Finish Date.
    My client's requirement is Auto PR will pick up the Delivery date as Basic Start Date. What settings do we need to Do for this scenario and on wht basis the delivery date is decided in PR wrt to Maintenance Order?
    Regards
    Pankaj

    Hi SAP Gurus,
    Any updates how to solve this issue?
    Regards
    Pankaj

  • Is possible create PO from maintenance order?

    From IW31 I can create a PR, and then PO in reference to PR.
    Is possible create directly PO from maintenance order? how?
    thx for attention

    Hi Paolo,
    It is not possible to create a purchase order directly from a maintenance work order. The standard SAP process is as follows:
    Create a component for external procurement on the work order - this results in the creation of a purchase requisition. The purchase requisition is then processed by the purchasing officer - the source of supply is assigned and the purchase requisition is then converted into a purchase order. If the component referenced a material master, the material may be specified on a contract/source list. In this case, the vendor and the price can be automatically deteremined during PO creation. If the material isn't on contract however, the purchasing officer may need to manually assign the correct vendor details and the price.
    The assumption is that the maintenance personnel are not purchasing experts - they just place a request for the product, and manual intervention is required from the appropriate purchasing expert within the company before this request can be sent to an external vendor.
    Regards,
    Monika

  • Material Gate Pass from Maintenance order?

    Dear SAPIENTS,
    Is there any system to issue returnable material gate pass from maintenance order in case of sending material outside for repairing. I want to keep track of material through maintenance order i.e the reason.
    Regards,

    Hi,
    There is no STD SAP Functionality Available but You can Develope the Customising Smart Form to get this fuctionality.
    Also You can get The information about the Outgoing Material in TC MB51 if your making The Reservation Of that Material agianst the Vendor,while sending that material outside.
    Regards,
    Rakesh

  • Printing Shop Papers from Maintenance Order Urgent !!!

    Hi All,
    I am in need of Printing Shop papers from Maintenance order , i know that the configuration of this thing is done through SPRO
    Plant Maintenance and customer service ->
    Maintenance and Service Processing -> Maintenance and Service Orders -> Print Control -> Define Shop Papers, Forms and Output Programs
    , but i want that when we give Print command through Maintenance order a smartfrom should trigger which i have developmed.
    My problem is that i am not able to configure the Print control for SMARTFORMS.
    What to do , Please suggest.
    Regards,
    Rachit Khanna

    Amol,
      Standard config doesnt provide the functionality to set the default selection dependant on PLANT. You will have to get the help of developer to do an implicit enhancement (Only If you are in ECC 6.0) to accomplish the same.
    Reagrds
    Narasimhan

  • Plan Component from Maintenance Order

    Hi,
    When i plan a component from maintenance order I use item category N with key MATE.
    But i woul plan component for purchase requisition on project stock( account assign Q) directly from Maintenance Order. Allow I insert item category N in the field ad near insert the value 2 for project stock.
    When i release the order the system blank the field and i don't create a Purchase requisition with project stock but i purchase requisition with account assignement F
    Because the system put away the field blank?, I must done another customizing, or i must utilize another KEY?
    Thank you

    Hi,
    When you make Item cat as N it means they are non stock .
    For non stock & with F order as account assignment system creates PR.
    if you want this componenet as Project stock them there are following  ways
    1.Make PR with item cat as Q & make PR on WBS or PS System.
      System will post direct entries.
    2.Make normal stock PR then issue against WBS by order
       Settle the maintenance order to WBS element
    3.Get material as normal stock material issue with 221 mvt against WBS or PS system.
       Systme will make enties to WBS.
    Ramesh

  • Plan material from Maintenance Order

    How i can plan from Maintenance order a material with accaunt category Q(special stock) for create a RDA
    Thank you

    Hi,
    I already have plan component from maintenance order but when i insert item category N for create a Purchase requisition and insert item category 2 for stock project Q the system blank the field and Don't create a purchase requisition with account assignment Q.
    Because the system put away the field blank?
    There are any way for create purchase requisition with account category Q?
    The BAPI that you suggest me can avoid this problem?
    Thank you.

  • Goods movement in collective order

    Hi all,
    We have ticked the indicator for 'Goods movement for collective order' in OPJH, still we are not getting required results. The goods receipt against the child order does not occur.
    Please help.
    SmanS

    Hi Dear Can u please explain..how you solved this..
    Regards
    Raghu

  • Catalog procurement from Maintenance Order

    Hi Gurus,
    My client is implementing Punchout Catalog from SAP ECC 6.0. we are not into SRM server. I made the settings in Web services ID and Description and i am able to do shopping from Vendors URl and return back to SAP ECC.
    Now 1) they want to populate the Vendor name automatically into SAP, which is not getting carried.
    2) I want to link the Punchout Catalog to Work order scenario also. For that i need to define the Order type and Catalog in the Link "Interface for Procurement Using Catalog" under the node Plant Maintenance and Customer service which i am not getting.
    Please advice me what needs to be done or what settings or any BADI needs to be activated on this issue.
    Thanks for your response in advance,
    I am not sure is this the right place to post this thread. Please advice.
    Thanks,
    Saakithyan.

    Hi,
    I already have plan component from maintenance order but when i insert item category N for create a Purchase requisition and insert item category 2 for stock project Q the system blank the field and Don't create a purchase requisition with account assignment Q.
    Because the system put away the field blank?
    There are any way for create purchase requisition with account category Q?
    The BAPI that you suggest me can avoid this problem?
    Thank you.

Maybe you are looking for