GR allowed despite "Delivery Completed" indicator was checked

Hi,
We would just like to know the possible reason/s why GR was allowed for a PO eventhough the "Delivery Completed" indicator was already checked.
Thank you.

Hi
Greetings!!!
Kindly Help!!!
Recently we are using the Latest GR date (Latest Possible Goods Receipt) functionality on Purchase Order but I want to know the standard Report for the same and is it possible to delete or lock or Delivery Complete of the line item automatically after the date? If yes, then please provide me the process.
My actual requirement is after Latest Possible Goods Receipt date the line item should not be show on Pending or to be delivering Qty. But in ME2* (M, N, L etc.) report it not happen.
Note:
I have checked the t-code ME80FN, but it not fill my requirements.
Actually I want to know the report for Latest GR Date (Latest Possible Goods Receipt) on purchase order in a Report. We can see the date manually on me23n-Item Detail-Delivery-Latest GR Date
Field Name- LEWED in Table EKPO but my requirement is SAP standard Report for the same.
In which report we check the latest GR date for more then 100 Purchase Order containing more then 1000 line Item and I know the Table but I am asking about only T-codes/ Reports.
Regards,
Sumant

Similar Messages

  • GR after "Delivery Completed" Indicator was Set and Automatic PO Closing

    Hi All!
    In our system, we can still post goods receipts even if the "Delivery Completed" indicator was already set in the PO. Is there something we need to configure so as not to allow goods receiving for such POs?
    Also, can we set the PO to close automatically after reaching its "Validity End"?
    Please we would appreciate any suggestion for this issues.
    Thanks in advance!

    Hi,
    The Solution is to
    <b>Reduce the PO quantity</b> or <b>the block the item on the PO</b> to prevent any further GR's.
    Block the purchase order item.
    (ME22N: Block pushbutton; ME22 Menu -> Edit -> Block)
    Fill the date field for the 'Latest Possible Goods
    Receipt' (LEWED) in the purchase order item. If you do
    this and you enter a GR document after this date, the
    system issues message M7163, which you must set as an
    error message in Customizing.
    <b>Refer to OSS note - 856279</b>
    Here is the copy
    Number 856279
    Version 3 from 24.06.2005
    Status Released for Customer
    Set on 24.06.2005
    Language EN
    Master language DE
    Short text MIGO: Proposed qty despite 'delivery completed'
    indicator
    Responsible SAP AG
    Component MM-IM-GR-PO
    Goods Receipt from External Procurement
    Regards
    Kedar Kulkarni

  • GR possible despite Delivery completed indicator in PO

    Dear All,
    We have PO created for 100Kg, now we have received 80kg and no further deliveries are expected and we want to close this PO line item.
    We are selecting Delivery Completed Indicator after making GR for 80Kg.  But Still we can make a GR posting in MIGO for this PO line item.
    Can someone suggest me on short closing of this PO line item.
    Thanks
    Uday

    Hello.
    This is standard behavior of the system, You can refer SAP Note# 856279.
    According to this we have three possible solutions
      1.Reduce the purchase order quantity to the previous GR quantity.
      2. Block the purchase order item.
         (ME22N: Block pushbutton; ME22 Menu -> Edit -> Block)
      3. Fill the date field for the 'Latest Possible Goods Receipt' (LEWED)
         in the purchase order item. If you do this and you enter a GR
         document after this date, the system issues message M7163, which
         you must set as an error message in Customizing.
    But I would  suggest to go with 3rd option because of below issues.
    With 1st option, if we reduce the PO qty to, PR will become Open again.
    with 2nd  option,  system will not allow invoice verification for blocked line item.
    With reagrds
    VB

  • Prevent GR with the delivery complete indicator set in the purchase order

    Dear friends,
    During GR reference to PO, if goods are received partially and the delivery complete indicator is set, the PO line item is deemed to be closed.
    However, if reference is made again to the same PO line item, GR can still be done to the item that delivery complete indicator was set.(due to there is still quantity to be received)
    Is there anyway, we could prevent reference to be made to a PO line item that has delivery complete indicator set?
    Thank you.
    Regards.

    it is by design that you still can receive material.
    See SAPs explanation here:
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/a5/63343943a211d189410000e829fbbd/frameset.htm
    The delivery complete indicator only reduces the commitment values to zero.
    If you want restrict further good receipts, then you have to reduce PO quantity to equal the received quantity and must not allow overdelvivery. Further you can enter a latest GR date, which will not allow receipt beyond this date.
    Locking the item will as well prevent further actions, but this should only be a short term solution, because the PO will still be considered in MRP runs and will never treated as beeing closed. And you will not be able to archive such POs

  • How to GR for PO in which delivery completion flag is checked.

    How can I stop GR against a PO in which Delivery Completion Flag is checked for the line item.

    To stop the system from proposing a quantity in Transactions MB01 or MIGO and to prevent a GR posting, you can proceed as follows:
    Reduce the purchase order quantity to the previous GR quantity.
    Block the purchase order item.
    (ME22N: Block pushbutton; ME22 Menu -> Edit -> Block)
    Fill the date field for the 'Latest Possible Goods Receipt' (LEWED) in the purchase order item. If you do this and you enter a GR document after this date, the system issues message M7163, which you must set as an error message in Customizing.
    see OSS Note 856279 - MIGO: Proposed qty despite 'delivery completed' indicator
    By the way, setting the block is not really recommended and jsut short term solution, as it will stop you from archiving this PO

  • Delivery completed indicator not working..

    HI SAP expers,
    some purchase orders not getting chick mark of  Delivery completed indicator ater receiving goods
    i have PO with 100 qty .  then GR 100 qty  .  but its not taking in the purchas eorder
    Delivery completed indicator not check automaticalley. i did all the configuration in spro-mm-inventory-GR-indi  extt...
    most of th ePO or  getting but some POs or not getting.. is there any settings behind MATERIAL MASTER or any .?
    Regards,
    Anthyodaya.

    Try the following config..
    1. Set Delivery complete indicator at plat leve
    spro - mm --inventory mgmt -
    Goods receipt -
    Set delivery complete indicator
    2. COntrol field selection for MIGO to disable users from changing it.
    spro --> Materials Mgmt --> Inventory Mgmt --> Settings for enjoy Transaction --> Field Selection for MIGO
    set field : "Del.Completed" Ind.     GOITEM-MIGO_ELIKZ    to Display

  • Delivery Completed Indicator(ELIKZ:0COMPL_DEL) in 2LIS_02_SCL

    Hi Experts,
    I am using the datasource 2LIS_02_SCL for Purchasing reports and this extractor has the 'Delivery Completed Indicator'[ELIKZ] which is mapped to 0COMPL_DEL in BW. The ODS which in our system has the 0PROCESSKEY as one of the key fields. Hence there are multiple records for one PO item with different 0PROCESSKEY. However the 'Delivery Completed Indicator' is not correctly extracted. For example, for one of the PO items which are not marked as delivery completed in R/3, the records extracted are as follows:
    Purch.Doc. Item( Deliv.date Pur Purc D
    POD Doc             Item    Schedule Line Process Key Delivery Completed Indicator
    3000000583          00001 0001               001             
    3000000583          00001 0001               002                X
    The delivery completed indicator was set & unset in R/3. This is an issue with all the similar PO items. The indicator in not set for all the records. Is there any rule that only certain process keys should be considered to identify the indicator?.
    Kindly help.
    Regards,
    Shilpa

    Hi,
    You can have more than these 3 depending on your system setup. 
    If remember correctly, everything ending with 1 is PO related, 2 is GR related and 3 is invoice related.  So, for GR related records, look at Process Keys 1 (so you know the Line Item quantity), 2 for GR's, 12 (GR reversals or issues?), 22 (GR issues or reversals?).
    Of course, with all things SAP, every system is different and you may have other keys you need to include.  As someone else wrote, looking to the transaction key mapping for the movement types. 
    Also, you should ask the functional guys or the business (if there are no functional people) for all of the GR related scenarios for Purchasing.  They should give you a list of 5 -10 scenarios on how material can be bought and brought into the system.  With that list, run through each one and see what records are created and when.  This will display to you how the system works and you can program based on the results.  This will take a while, but will be very beneficial to you.
    Brian

  • Delivery Completion Indicator- Control?

    Hi all,
       In our organization we have defined the release strategy in such a way that, we are having 8 release codes in a release strategy,, by means of release indicator blocked and released,,,once the PO was released bythe initial hierarchy release indicator is set as blocked i.e we cant do any changes to the PO.
    Requirement is I hv created a PO for 10 quantity.
    Received only 04 quantity,,, by this time vendor told that he cant supply the balance quantity,,, so want to short close the PO. so set the delivery completion indicator during GR time,,, by which the Header status in PO was changed like this.   Ordered -10, delivered -4, still to be delivered -0.  This is what exactly we require,,, bur our end user try to do GR for the balance 6 items for the same PO,,, it has taken in even we set the delivery completion indicator,,,
    Why this indicator is not having control?system should not allow us to do further GR if this indicator is set,, even its allowing us do, how to overcome this?
    If ur suggestion is try to short close the PO by changing the ordered qty to 4,,, this is not possible in our business scenario as v r having typical release procedure as explained above. help me out
    regards,
    urendra

    Hi,
    This is a problem that is typically caused by blocking changes to an authorised PO.
    It would be better to allow certain changes and reset the release instead of completely blocking the PO for change. That way if anything that affects the release changes, it will have to be authorised again, but if something changes that is NOT part of the release check, it can be done without problem.
    That way you could set the "blocked" indicator as suggested, but if you changed the qty or price etc. the PO would have to be released again.
    One final option would be to use a user exit in MIGO that checks for the DCI  flag and prevents the GR.
    Steve B

  • "Delivery Completed" Indicator in Goods Receipt

    Hi,
    While doing GR, we want to check the "Delivery Completed" on the Goods Receipt Screen if we are expecting no future receipt against the Purchase Order.
    Currently we are not able to check the Delivery Completed Indicator as it is not in editable mode.
    Is there any issue if we enable the Check Box on Goods Receipt Screen. If no, how can we enable the Check Box.
    Please guide.
    Regards,

    Hi
    This is handled by the system automatically. you can change only in purchase order.
    Refer SAP note 1093582 for more info
    About delivery completed indicator functionality
    The purchase order item is considered closed, even though the total
    quantity may not have been delivered.
    o Although a further delivery is not expected, it is still possible.
    o At the time of the next goods receipt, the system suggests the item
    as unselected.
    o The purchase order item can be deleted, even if the total quantity
    was not delivered.
    Although the "delivery completed" indicator is not set, a purchase order
    item is still considered closed if the full quantity has been delivered. In
    this case, the "delivery completed indicator" is not required.
    In Customizing for Inventory Management/Goods Receipt/Set Delivery
    Completed Indicator, you can define at plant level that the "delivery
    completed indicator" is set automatically in the order if:
    o the total quantity was delivered
    o the underdelivery or overdelivery lies within the tolerances
    Hope it helps
    Thanks/karthik

  • Delivery completed indicator for STO cannot be set!

    Dear colleagues,
    There are number of STO’s those goods issue quantity > quantity of goods received. Because of this delivery completed indicator cannot be set due to message “06 848 - Delivery completed indicator cannot be set for item XXXXX”.
    There is an OSS note (167795) that allows to set delivery completed indicator for such purchase orders. Even though our SAP release is 6.04, report RM06EV70 does not exist (yet BADI ME_ARCHIVE_ACTIVE is active) in the system and OSS note cannot be implemented.
    Any help would be appreciated.
    Regards,
    Melih
    PS. Please do not provide answers like “the goods receipt must be first posted via the entire goods issue quantity; then you can post a scrapping via the shortfall quantity” since there are backdated STO’s.

    Hi,
    Find STO created for which plant in t.code:ME23N and check MRP parameter maintained for that plant in t.code:OPPQ( also check entry of that plant in t.code: OMCD).
    Also cross check which Field Selection Key assigned to your STO PO document type and check “Delivery completed" indicator” available as Optional entry in GR/IR control segment in your Field Selection Key.
    SPRO - > MM - > Purchasing -> Define Screen Layout at Document Level
    Regards,
    Biju K

  • Update "Delivery Completed" Indicator in PO Item via EDI

    Hello
    We have another challenging task regarding purchase order confirmations that we would like to tackle (SAP Release is ERP 6.0).
    The 2 partner in our scenario are distribution companies (= DC) which order goods and production companies (= PC) which deliver the goods:
    (1) DC sends purchase oder via EDI (ORDERS IDoc)
        -> creates sales order in ERP of PC
    (2) PC splits sales order into multiple deliveries.
       Each delivery is sent as outbound DESADV
       -> creates inbound delivery in ERP of DC.
    (3) At some point the PC has completed the sales order
       yet it is possible that less was delivered than was ordered
          (i.e. we can have under-deliveries).
    Now the question is:
    How can the PC transmit the final information "SalesOrder completed" implying that the "Delivery Completed" indicator in the PO items should be updated (= 'X')?
    My assumption is that we need to look at the sales order (ERP of PC) because this is the document which "collects" the information from all the split deliveries.
    Any help related to understanding how the (standard) business process would look like and how to translate this into a technical solution (EDI / IDoc) is more than welcome.
    Regards
      Uwe

    Hello Uwe,
    As you mentioned, I tried to check with the Workflow solution by tracking the events through Business Object BUS2032 (Order) or LIKP (Outbound Delivery) but failed to get successful results.
    Problem with BUS2032, event CHANGED is that it doesn't get triggered when the Header/Item level status changed during delivery Processing. 
    While using BO- LIKP (Outbound Delivery Processing), Events - Changed,Created, I am successful in triggering the event, but the problem with BO-LIKP is that, it does not have the item level details in the ATTRIBUTES list.  To get the balance quantity available for order line item (mentioned in my earlier reply)Item details are necessary to findout the Reference Sales Order & Line item.  With this, the Option of Triggering of Workflow using LIKP didn't give the required result.

  • Delivery completed indicator in PO

    Hi team,
    What's the significance of delvirey completed indiocator in PO. Even if i choose this, able to do GR with MIGO.
    I hope my question is clear. Kindly respond

    Hi Prasad
    When u tick delivery complete indicator system will not consider that Po as Open Qty. which u can check in MMBE stock overview
    Where open Qty is reduced..u can check this
    first try to check stock w/o delivery complete indicator
    And then after ticking Delivery complete indicator
    ( Note that here PO balance qTY SHOULD BE more than 1)
    As the PO is not closed, system allows you to do GR for the rest of the quantity.
    If u don't want system to allow pass GR once indicator is ticked u need to delete line item
    Hope this will clear ur doubt
    revert for any clarification
    Vishal...

  • "Delivery Completed" Indicator in Purchase Order

    Hi,
    While doing GR, we want to check the "Delivery Completed" on the Goods Receipt Screen if we are expecting no future receipt against the Purchase Order.
    On SDN & SAP Note, I got to know that we canu2019t tick the "Delivery Completed" Check Box while doing Goods Receipt.
    We have implemented the Release Strategy on the Purchase Order. To tick the "Delivery Completed" Check Box, we need to cancel the Release Strategy.
    Is there any other way (T Codes) to achieve the same?
    Regards,

    Even you flag Delivery Completed" Indicator in Purchase Order, system still allows GRN for open Qty.
    Use MEMASSPO trxn & Put Deletion indicator for the PO Line Item. So that you can not do GRN for the open Qty of PO line item.
    Check
    mass setting of delivery completed indicator

  • P.O. Delivery Complete Indicator

    Hi,
    We have purchase orders that are not getting the delivery complete indicator checked off when the GR comes in. 
    Does anyone know of a program that can go out and look for any PO's that should have the delivery complete indicator checked and automatically check this field.
    Regards,
    Vicki Smith

    Together with the customizing where the Delivery Complete indicator is set automatically, you should also make sure that your Over-and Under-delivery tolerences are "reasonable".  The delivery complete indicator works automatically in 2 scenarios:
    1 - You order 100, and you receive 100.  Therefor, it makes sense to the system that the order quantity was delivered in full and thus set the Delivery Complete indicator automatically when performing the Goods Receipt.
    Overdelivery Tolerance = 5%
    Underdelivery Tolerance = 10%
    2 - You order 100, and you receive 91.  This is within the acceptable Underdelivery tolerance and therefor the system sets the Delivery Complete indicator automatically upon Goods Receipt.  If the goods receipt quantity was below 90, the indicator would not have been set automatically and you should set it manually in your Goods Receipt transaction, or the system will regard this Purchase Order to still be open.
    Over- and Underdelivery tolerances can be defined in your Purchasing Value keys customizing.  It can also be changed in the Info Records.
    Hope this helps
    Regards
    Christo

  • Minimum shelf life and delivery completed indicator at GR

    Dear Gurus,
    I have two questions:
    1. As per my knowledge minimum shelf life is "minimum number of days for which the material must be keep for GR to be accepted" , (i.e. if it is 10 days the material should accepted for GR only after 10days of production ) but if I do a GR for today produced material still I m not getting any error. Why?
    2. Since we can do GR for "delivery completed" indicator set items. Canu2019t we get an error message if we try to post GR for delivery completed item (e.g. what is the use of message numbers 433 and 025)
    Thanks,
    Chameendri

    Hi,
    Answer to Question 1:
    Total Shelf life - If total shelf life is maintained then the minimum shelf life will also to be entered mandatory. While taking
    GR for such item, it actually ask the user to enter the Manufactured date so that the system automatically calculates the
    expiry date.
    Minimum shelf life ( or Minimum remaining shelf life)- While taking the GR, it asks the user to enter the date of GR date so that it checks whether the
    days entered in material master has been satisfied. If the condition is not satisfied then it will not allow to take receipt for
    that item.
    Example A material has a minimum remaining shelf life of 20 days and a total shelf life of 30 days. You enter the goods
    receipt of a new batch on 23/02/12 and enter 11/02/12 as production date. The system calculates the shelf life expiration date 15/03/12 from the production date plus total shelf life (30 days). The batch still has a remaining shelf life of 18  days. The goods
    receipt is not accepted (short fall of 2 days from minimum remaining shelf life)
    Now if the production date is 14/02/12 then batch still has a remaining shelf life of 21 days The goods receipt is accepted
    Answer to Question 2:
    Not possible to restrict by activating system messages only
    So refer this  solution
    http://www.sdn.sap.com/irj/scn/weblogs?blog=/pub/wlg/17281

Maybe you are looking for

  • Maps 2.0 - "Show on map" is not working

    Hello guys. my ovi maps is started to saying that : " this app requires Licence manager download" . and then when i click to "yes" it is trying to open web page but web page is not working. And now "Show on map" feature is not working . I cant format

  • How to give away a macbook

    So I'm thinking of passing on my MacBook White to a friend with no Apple experience. This MacBook came with Leopard and can only be upgraded to Lion, which it is at present. Question; can I nuke & pave and install my copy of Lion and pass it on that

  • MacBook Display Will Not 'Remember' Brightness

    Okay, so I finally went out and bought a black one. Since the Core2 models came out, it came to me at a great price. I'm very happy with it after a RAM upgrade to 2GB and after I turned down the screen brightness. The machine remembered my screen bri

  • InfoView Timeout Crystal Report Server 2008 Business Objects 3.1

    After two days of digging, poking, prodding and fumbling around in the dark I finally found a method (one that actually works!) to change the timeout period for InfoView.  Venkat Patnaik (second message) posted an excellent procedure in a place that

  • Why is my DQS_Projects DB so big?

    Hello everyone, My DQS_Projects DB is currently using about 12GB of disk space.  However when I run the dqsinstaller -exportkbs the exported file is not even 3MB. Can anyone explain why the DQS_Projects DB grows so big, and how/whether I can manage t