Hello,
We understand that R/3 is able to do more complex currency calculations than BW. For example is it ok for R/3 to calculate from USD to NOK if only the NOK to USD rate exist in the system. It's even possible to calculate via another currency. This is not easily possible in BW. To be able to do the same in a BW-report we would like to have the NOK to USD rate in the currency tables in BW. The rates are loaded from R/3 and of course we don't want to add exchange rates manually in BW.
I suppose it's possible to write a program which loops through the currency table and generates the missing rates. Are there any simpler solutions?
Anyone who has had the same problem?
Best regards,
Christoffer Owe

Hi,
In transaction RSCUR you can use a number of conversion rules. 
If you want to have something more complex, just use an ABAP-routine to do the conversion.
The exchange-rate tables in BW and R/3 are exactly the same, so you can use the same function
modules as the ones used in R/3.
regards,
M.

Similar Messages

  • How to change exchange rate during billing (VF02)

    Respected Members,
    i already created the Billing documents from sales order and it took the exchange rate wat i mentioned in the sales document.
    but still it is not release to accounting .
    So i want to change the exchange rate in change of billing document.
    The pop up box for that field is coming in the display mode and it is not coming in the change mode.
    How to do it.
    Please tell me .
    Thanks a lot.

    Thanks for your replies.
    But i have one querry that is when you go to billing document header there you will see exchange-rate accntg flied and above that there will be one checkbox set exchng rt and by going F1 on it is mentioned that you can give the exchange rate during billing and it can redertmine the value at billing level and also the exchange rate acctng field gives one pop up box same as it gives in sales order ,but here that box is in grey mode and in sales order it is in grey mode and how to bring this box in change mode during billing.
    Please clarify my doubt.
    THanks

  • How to check Exchange rates are daily updating in BW

    Hi All,
    How can we check whether currency exchange rates are updating from R/3 to BW.
    If not how can we update daily from r/3  to bw in Background Job?
    How can we do manully in BW?
    Thanks in Advance,
    C.V.

    Hi,
    First of all check what time and how frequently the R3 system gets updated with the new/changed exchange rates. Depending on that you'll need to fix up the timings after the R3 system has been updated.
    If you use PCs or any scheduling tool you can easily schedule them in the background using the background jobs.
    Cheers,
    Kedar

  • How system calculate Exchange Rate for material?

    I have some doubt how system calculate exchange rate for material when doing GR.
    For example, standard price of material is 0.01 USD per ea. PO is created in foreign currency (THB) with qty: 40,000 ea (THB 2,852.00)
    Actually when I do GR ea then accounting doc is:
    Dr. Inventory 400 USD (12,800 THB)
       Cr. GR/IR    88.64- USD (2,852.00- THB)
       Cr. Variant 311.36- USD (9,948.00- THB)
    for 2nd and 3rd line item, exchange rate M (THB -> USD) is 0.03108 which is correct.
    Could anyone advise where system get exchange rate for 1st line item?

    Hi
    First of all, as mentioned by you, the exchange rate for Item 2 and 3 is not 0.03108.. It is as below, based on the figures given by you...
    Dr. Inventory 400 USD (12,800 THB)........ Exch rate is 0.03125
    Cr. GR/IR 88.64- USD (2,852.00- THB)....... Exch rate is 0.03108
    Cr. Variant 311.36- USD (9,948.00- THB).... Exch rate is 0.0313
    I guess the item 3 is just a derivation from Items 1 and 2.. The Price diff results as a difference between std cost and purchase price...
    I believe, the exchange rate would have been 0.03125 at the time of GR... You need to check this in your system... For sure, it uses  exch rate type M in the standard... Check if 0.03125 (USD -> THB) or 32 THB -> USD exists in your system at all
    Item 2 is based on your PO negotiated rate...
    Regards
    Ajay M

  • How to shynchronizes exchange rate

    hi gurus,
    we need to shynchronizes exchange rate between Central System and Sub System.
    how to transfer exchange rate from Central System to Sub System using IDOC / ALE
    thanks for help
    rgds
    echo

    Hi Prashanthi,
                 I just came across the same problem that you happend to cross thru, If u can please share your tots on how u distributed Exchange rate it wlll be very helpuful, I have done the following configurations;
    1. Partner profile configs, Outbound message type give as CURR_A ( Created this message type in WE81? ), and basic type as T_CURR01, correct if my configurations for partner profile are wrong,In the parnter profile i have give message type as CURR_A .
    2. In BD64 i distributed the logical system, added the method exchangerate.getdetail
    3. Then i used RFALEX00 report to distribute it.
    But cudnt get the idocs in WE05...
    Please let me know the reason for not posting the idoc..all your help will be highly appreciated..Hoping you wud reply.

  • Redetermine the exchange rates during the billing.

    Hi
    I would like to redetermine the exchange rates during the billing.
    When we are creating a sales order we are maintaining exchange rate in sales order header, but in case of any change in rates
    I have to change it in sales orders first and then i have to create an invoice. Instead of doing this i would like the exchange rates
    to be redetermined during billing automatically.
    Please help
    Suresh

    Hi,
          Firstly let us know If you want to redetermine the pricing exchange rate or the exchange rate to accounting? I imagine that the pricing exchange rate you are talking about ,the pricing exchange rate type should definetely work no matter  what the  pricing source is . Normal sales cycle always has the price source as order, which controls from where and in what sequence the conditions from the reference documents are copied to the billing document. It does not control the exchange rate. Check the billing date in your sales order(its always advisable to take the service rendered date as the base to calculate the exhcange rate which is PGI date when a delivery is involved) , not the actual billed date. If you want the system to determine the exhcange rate on the date when the Invoice has been raised(Different from the billing date in the sales order) then go for the option of "E" which will take the service rendered date.
    But If you want the exchange rate for accounting then you have to append a routine at the item level in "VTFL" .The Logic would be to read the exchange rate from TCURR table using the function module "READ_EXCHANGE_RATE. If you have specified the exchage rate in the header(Accouting tab) of the sales order this gets copied to the billing document This is SAP standard behaviour. To over write this you have to go for the routine ammendment as suggested above.(In case of billing dates and the exchange rates differ). Kindly please let me know If you need any more help on this.
    Regards
    Ram Pedarla

  • POSSIBLE TO SPECIFY EXCHANGE RATE DURING GOODS RECEIPT

    Dear All,
    Anybody can throw light, whether we can able to specify the Exchange Rate Manually while doing Imports GRN.
    Tks
    Mani

    Dear Deepak,
    Yes, Of course i understood, But scenario is we have cleared the stock from customs and kept in duty paid bonded warehouse couple of months back and we have not done GRN for the PO in SAP. Once the Material is moved to the factory from warehouse after two months, While doing GRN the Material cost is getting calculated based on the current exchange rate and its giving impact in the stock value also. So, to avoid ther is any manual intervention is there to change the exchange rate during GR for such scenarios's alone.
    If not, pls suggest your view to overcome on the above scenario.
    Tks
    Mani

  • How to change exchange rate type for specific pricing condition type

    Hello every one,
    I have a requirement for billing ie VF01.
    currently  all the exchange rate are being calculated with exchange rate type 'M' by default.
    but now client want it should calculate exchange rate with type 'E' for two pricing condition type for all others it should calculate with type 'M'
    Please any body can help me with the exit and code which i can use.
    I have checked exits SDVFX008.
    but how to change exchange rate with type 'E' only for two conditions.
    as changing exchange rate at document header will change exchange rate for all condition type.

    You need to assign KOMK-KURST = 'E', for those two condition types. If it had been item number specific, you could have used USEREXIT_PRICING_PREPARE_TKOMK(RV60AFZZ).
    Do one thing, put a breakpoint on FM 'PRICING' and then do selective runtime analysis.
    Check whether any user exit/BADI/ explicit enhancement are available when condition types are processed in a loop. If nothing is available, try implicit enhancement.
    Link to refer for selective runtime analysis - Runtime Analysis for VOFM
    Also try with VOFM requirements ( not sure whether changing KOMK-KURST is permissable in requirement as normally  we only set sy-subrc values to suppress/allow condition types ). Don't forget to assign requirements against condition types in pricing procedure.

  • To use GR Exchange rate during IV

    Dear ALL:
    my customer has such request that they want the GR's exchange rate during IV automatically.
    Exchange Rate for invoice matching IR ( at Feb at 2.10 ) should be similar to GRN ( Jan at 2.00 exchange rate ). Customer does not want to fix the exchange rate during the PO .
    They want to pick up the exchange rate when the GR is being executed .Is there any automatic setting to enable this, they want to avoid manually changing the exchange rate during IR.
    Can anyone assist please ? Thanks.
    by the way, do you know which date determine the exchange rate in IV , the posting  date or the document date?

    Think about it once...
    You can do one thing, don't make the PO first...Directly go for the GR and while making the GR make the PO, so that the same exchange rate will be treated at the PO and GR ....now for the IR, GO for the ERS functionality, so that as soon as you make the GR, system will take those GR and PO into consideration for the ERS settlement and IR ie. vendor will be payed with the same exchange rate...
    If you don't want this functionality and then take the help of ABAP consultant to develope a new enhancement for your functionality...
    Hope it helps..
    Regards
    Priyanka.P

  • Exchange rate should pick from TCURR based on custom date field added in MIGO

    Hi,
    In MIGO, FI document get posted by picking exchange rate based on the posting date. Through BADI(MB_DOCUMENT_BADI) we have added a field called translation date in MIGO screen, while doing GRN exchange rate should pick from TCURR based on translation date instead of posting date. We have tried this logic using substitution (GGB1) in FI accounting it is working fine in FB60 & F-02 transaction but it is not working with MIGO transaction. Please suggest some solution for this.
    Thanks & Regards
    Vinoth Kumar.M

    Hi Maniraj,
    This will a modification to existing system and it is not supported directly.
    There are 2 notes of SAP for modification of translation date of BKPF.
    SAP Note 574583 will activate a BADI kindly refer to it for details.
    http://www.stechno.net/sap-notes.html?view=sapnote&id=574583
    There is another one but is appilcable if material ledger is active in the system
    Regards

  • How we can automate the data loading from BI-BPC

    Dear  Guru's
    Thanks for watching this thread,my question is
                  How we can load the data from BI7.0 to BPC.My environment is SAP-BI 7.0 and BPC is 7.5 MS version and 2008SQL.
    How we can automate the data loading from  BI- BPC Ms version.Is manual flat file load is mandatory in ms version.
    Thanks in Advance,
    Srinivasan.

    Here are some options
    1) Use standars packages and schedule them :
        A) Openhub masterdata file into a flat file/ BPC App server  and Schedule the package - Import Master Data from a Data File and  other relevent packages.
    2 ) Using Custom Tasks in Custom Packages ( SSIS)
    Procedure
    From the Microsoft SQL Server Business Intelligence Developer Studio, open the Microsoft SSIS folder.
    Create a new package, or select an existing package to modify.
    Choose  Task  Register Custom Task .
    In the Task Location field, browse for the target .dll file.
    Note
    By default, the .dll files are stored in BPC/Websrvr/bin.
    End of the note.
    Enter a task description, select an appropriate icon, then click OK.
    Drag the icon to the designer window. Enter data as required.
    Save the package.

  • How do I get LR2 to "load from device" via command line?

    Hi,
    how do I get LR2 to "load from device" via command line?
    I've got XP to load LR2 when a "camera" (and only a camera) is connected but really cool would be if LR2 would also import the pictures.
    cu,
    Michael

    1. Make sure you are using IOS 7.
    2. Make sure your iPad is register in My Support Profile.
    https://supportprofile.apple.com/
    3. Try downloading again; it should be free.

  • How to get Exchange rate from SO to specific Document type in PO

    Dear Experts,
    I have an Intercompany scenario in which I need to have Exchange rate used in Sales Order into a specific document type in a PO. Is it possible to achieve this?
    Thanks
    Manish

    Hi ;
    To my knowladge , you have two options.
    1- Fix exchange rate in PO
    2- You can get exchange rate in Miro based on invoiced date.
    Another ways will be development ...
    Regards.
    M.Ozgur Unal

  • Exchange Rate difference recovory from vendor

    Hi Expers,
    We have an issue with our client over the below issue .
    A Canadaina Plant created a PO with Hungary vendor with HUF as currency in the PO , During PO creation there an exchange rate say X1 ( Exchange Rate not fixed ) . Due to some reasons the GR is done lately after four months from the PO date creation and after the invoice is done .Invoice is done after the three months of PO creation date  .and during the GR/Invoice creation the exchange rate is X2 .
    Sytem posted with X2 exchange rate by not considering the X1 rate . Thease delay in making the GR/MIKRO errors causing the client to pay excess amounts to the vendor and he want to get them back now .
    Requested to advice in which process he can get from the vendor and how to see that the GR to get posted with the old x1 rate for all those posted POs .
    Regards,
    Message was edited by, removed the unwanted terms: Jürgen L

    I hope you misunderstood the facts.
    if the exchange rate is not fixed, then it is not taken into account when invoice or GR is posted.
    If the GR was posted after the invoice, then the goods receipt is valuated by the invoice value.
    You did not overpay the vendor, because you  pay the vendor in the currency of the invoice, and this amount is just equal to the amount you ordered, the difference is just somewhere in your own books

  • CRM exchange rate delta download from ECC

    Hi experts,
    We are trying to download the exchange rate from ECC for the delta scenario. I've tried to schedule a job to run the program SMOF_DOWNLOAD with Object DNL_CUST_BASIS3, but it comes up with an err, which says "Error     004     DNL_CUST_BASIS3: No Initial Load if data distribution is active. Use Synchron. Load". Will anyone advice how to achieve the delta download for exch rate from ECC to CRM or what i did wrong in the program execution?
    Rgs, Michelle

    Hi,
    you can check the object DNL_CUST_BASIS3 by t-code:R3AC3,
    Delete Function COMPARE, Then can load again and check
    Regards...
    Arup

Maybe you are looking for

  • Cover flow window size keeps changing

    As you can see to the images below, iTunes suddenly started to changing my cover flow size every time I restart it. !http://img11.imageshack.us/img11/2162/30848223.jpg! !http://img13.imageshack.us/img13/695/39067239.jpg! Before 2-3 days I never had t

  • Getting started with JCOP Tools

    I have a working Eclipse + JCOP Tools installation, activated. I now also have a Cardman reader (drivers loaded) and some blank JCOP30 cards. I read through the Eclipse embedded JCOP help page, but couldn't find the answers to some simple questions:

  • Getting a ref cursor out of a procedure

    Hello, I am having some issues getting the ref cursor out of this procedure that returns a ref cursor when given inputs. I have included the code below and made bold the call to the package and procedure where the requested function lies. I put c2 in

  • How to reset mac admin password for os x 10.8.5

    cannot update software because i cannot remeber my computer password (admin) and i need to reset it. Please help.

  • Opening project CS6 crash problem

    Opening an older project that I was working on collegues machine. Its an older version of premiere pro i think 4. I have Cs6 and am trying to open the same project. It says this which is fine; Then I say ok, it goes on to locate media which again is