I need to display planned quantity and actual quantity for Plant in quarter

Hi,
   I need to display planned quantity and actual quantity for Plant in quarter  AND  month wise as  below.
                                                                Q1                              Q2  .......                              M1                                       M2 .........................................
PLANT    MATERRIAL    UNIT     PLTY   ACTQTY          PLTY   ACQTY                   PLTY   ACQTY                    PLTY   ACQTY
P1            M1                      EA        20        15                      30       25                             40       35                              50       45
P1            M2                      EA        20        15                      30       25                             40       35                              50       45
P2            M2                      EA        20        15                      30       25                             40       35                              50       45
I will keep plant and material infoobject as row. Can you please suggest how i should design column section to display like above
Regards
Deep.

Hi Deep,
Assuming you have an InfoObject for Quarter (say 0CALQUARTER) & Month (say 0CALMONTH), drag the Quarter InfoObject & Month InfoObject below in the Columns. Drag your KFs i.e. Planned Qty & Actual Qty below the Month InfoObject to form a KF structure. If you don't want Qty Unit to be displayed alongside your KFs, use NODIM() function & display Unit in the Rows.
--Priya

Similar Messages

  • Planned quantity and actual quantity error

    Dear all,
    Planned quantity and actual quantity both are same,but still some variance showing in plan/actual variance column.
    Kindly find below image.Material 10000135,10000137,10000310. while confirming we dint consider these material,apart from that other values showing variance.
    Requesting you to give suggestion.
    Regards
    Rajasekaran

    Hi Deep,
    Assuming you have an InfoObject for Quarter (say 0CALQUARTER) & Month (say 0CALMONTH), drag the Quarter InfoObject & Month InfoObject below in the Columns. Drag your KFs i.e. Planned Qty & Actual Qty below the Month InfoObject to form a KF structure. If you don't want Qty Unit to be displayed alongside your KFs, use NODIM() function & display Unit in the Rows.
    --Priya

  • PS: BAPI For Planned Progress and Actual Progress

    Dear All,
                  Is there any BAPI available for Planned Progress and Actual Progress for PS Project.
    Regards,
    Sohail

    Hi,
    Try using this report s_alr_87013532.
    Also for planned and actual progress the table is rpsqt. Could not find any bapi for the progress
    Regards
    Hiren K.Chitalia

  • IW32  needed Plan Cost and Actual Cost table name

    Hello ,
    In IW32 transaction Plan Cost and Actual cost in cost tab ---Table Name.
    Req: needed  plan cost & actual cost table names  for particular order number.( For New Report )
    Can you please let me know where Plan cost & actual cost get stored in IW32 in Cost tab ( table name / function module name ) or how its get calcualted for particular order number.
    Thanks in advance !
    Regards
    Rahul

    hi ,
    i too had same issue , i wrote following FS for that :
    Actual and planned cost  from PMCO-WRT00 to WRT12(the sum of values should be considered for actual as well as planned ) for  PMCO-OBJNR taken from CAUFV -OBJNR for order number  AFIH-AUFNR  and also currency from CAUFV-WAERS .
    Actual cost will have valuation type PMCO-WRTTP = 4 and planned cost will have valuation type  PMCO-WRTTP = 1 , which will be placed in different column
    hope this helps
    regards
    satish

  • I need to know the difference between planned SKF and Actual SKF from business view and when I can use one of them ?

    I need just to know the difference between plan SKF and Actual SKF in business example and when I use one of them.
    thanks

    Hi Salaam,
    Statistical Key Figure (SKF) is a base to allocate the cost between cost centers. Usually, common cost centers cost should allocate to respective department cost centers on monthly basis.
    Some of SKFs are: Calculating floor rent on SFT, Telephone charges on No. of units, and employees head count is with "Each" in SAP.
    Apart from Ajay's reply, you can consider the Canteen exp in an organization. Assume Admin, Fin and Mfg departments are getting food services from Canteen. Here, total monthly cost of Canteen exp should be allocated to respective departments. Here, we use SKF as total head count of each department and distribute the cost.
    Planned SKF is what you planned on the beginning of a period. (Assume head count was planned as 30 in the month beginning)
    Actual SKF is what exactly you consumed over the period. (Actual employees provided canteen services during the month is 25)
    BR, Srinivas Salpala

  • In which table production order planned cost and actual cost i can see?

    Dear PP Guru,s,
    from which table i can see productuion order planned and actaul cost. i checked following tables AUFK, AFVC, AFVV, CAUFV, AFRU, AFKO, AFPO. but i did not found planned cost and actual cost field. is there any other way to get this data with respect production order?
    Regards,
    sree

    Dear,
    Planned and actual costs of prod order from COEP, COSS, COSP  S027 tables
    production order shows the planned cost based on the quantity structure.
    Please refer my reply in this thread for details,
    Re: Actual Halb Material Cost
    Regards,
    R.Brahmankar

  • Function Module to find Planned Costs and Actual Costs against WBS element

    Dear All,
    We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
    Are there any function modules to retrieve this value?
    Thanks for the help.
    Warm Regards,
    Judith

    Hi,
    The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
    Please let me know if this helps.
    jibat

  • In IW32 no Planned Cost and Actual is showing Zero

    hi,
    In IW32 no Planned Cost and Actual is showing Zero,since activity type is mentioned.
    how it could be displayed.
    Thanks

    Dear Sharma,
    1. This is regarding Maintenance order, frist you confirm by clicking on the operations tab-> double clicking on the work center->click on costing tab, check here activity type, activity unit is maintained.
    2. then in in KP26 check the activity price in the current period.if it is zero u will get zero
    3 then in the order click on components, if components are consumed  also check the component price in material master.
    this will resolve your issue
    sree

  • Tcode for planned production  and actual production

    Hello,
    I am working with a report I want to check the values with R/3 for Planned Production and Actual production. Does anybody have any idea how to check?
    Thanks in advance

    Hey Suman,
    i have the same problem, did you find a solution?
    thanks

  • Planned and actual consumption for each confirmation

    Dear All,
    There is a production order. it has two operations. i have made three confirmations of each operation for that order. now i want to see the planned and actual consumption for each confirmation. how is it possible.
    However i know that on order we can see planned and actual consumption but it is for total order but i want to see planned and actual consumption for each confirmation. Actually client wants that on 2nd confirmation what is planned consumption and what they consumed on actual. thanks

    Hi,
            In standard SAP this type of report not be there, but u can make it by using BOM,Confirmation table, & material document table.
    Use AFRU to get posted document no for confirmation & detail by joining it with MSEG by mblnr & MAZHR.
    now u get plan component qty by using mast & stpo if ur bom not changed in Production order , if in order component may be change then use afko & resb table & by comparing base qty or order qty & confirmation qty get plan component qty for confirmation.
    Thanks
    Rakesh

  • Dashboard content is not populated with Planned Cost and Actual Cost

    Hi
    We are working in cProjects 4.0 + ECC 6.0 implementation. I could not get the data for columns in Planned Cost and Actual Cost in cProjects Project Dashboard. I have properly mapped the config settings and created and assigned a Project in PS
    Has anybody got this data in the Dashboard?
    Kindly suggest the solution
    with regards,
    K Rama Krishna
    9394712743

    Hi Rama,
    It is difficult to say, where the problem is.
    but typically, the causes of the problem are
    customizing is  set incorrectly or the evaluation is not carried out.
    You can run the the evaluation DPR_EVE_BATCH_DPO additionally, please untick the flag 'check the last changed date'.
    Hope, it helps.
    Kind regards,
    Zhenbo

  • How should i get plan poc and actual poc

    hi experts,
    in cne5,the plan poc and actual poc are all null,the  bcws and bcwp already get values(the same to my plan budage),the pocs should i maintain manual and where?
    i look to help http://help.sap.com/saphelp_47x200/helpdata/en/b4/ba853488601e33e10000009b38f83b/frameset.htm,there is a step said "Determine the progress of your project",how?
    best regards
    zlf

    Hi,
    Confirm activities of your project & then execute CNE1 for that period for that project, then those values will appear on CNE5 report.
    reg,
    Sam L

  • Order Quantity and Target Quantity, both as editable in Sales Order

    Hi All,
    We have a requirement in which order quantity and target quantity, both should be allowed as editable fields in overview screen while creating a sales order or contract. Currently, only one quantity field is editable (order quantity in sales order and target quantity in contract).
    First question, is this possible?
    Second, If possible, then please tell the configurations need to maintain?
    Note: The material is relevant for delivery (so schedule lines allowed).
    Thanks & Regards,
    Vishal

    Hi Lakshmi,
    Thanks for the reply. I think I did not clarify the actual requirements. Let me explain it again:
    I understand that generally, Target qty is in contract and Order Qty is in sales order. But actually, here query is,
    When I create Sales Order (VA01), then while entering Material, user should see both quantity columns (Order Qty and Target Qty) in editable mode.
    So is this possible? If yes, then please guide.
    Please revert back if any further clarifications is required.
    Thanks & Regards,
    Vishal

  • Material Confirmed quantity and Open quantity

    Hi All,
      I am working on a report where the user wants the material confirmed quantity and open quantity at the batch level. I know for open quantity VBBE-OMENG can work. Just need confirmation that this is the correct field. However for confirmed quantity I am not able to narrow it down to one field. I have the following fields as possibilities but not sure which is the right one.
    1) VBBE-VMENG
    2) VBEP-BMENG (This is the at the sales order level though. We need it at the batch level)
    Can you please let me know if i have the right approach here? The report has Material, plant, sloc and batch along with a bunch of other fields.
    Regards.
    Sid

    Hello,
    you should extract the quantities from all the deliveries selected for material and batch, and selecting only open deliveries.
    Use a selection like this:
        SELECT lips~MATNR lips~WERKS
               lips~CHARG lips~LFIMG
          INTO TABLE lt_lips
          from lips as lips
          INNER JOIN vbup as vbup
            on lips~VBELN = vbup~VBELN AND
               lips~POSNR = vbup~POSNR
         WHERE lips~MATNR = p_matnr
           AND lips~WERKS = P_WERKS
           AND lips~CHARG = P_CHARG
           AND ( vbup~WBSTA eq 'A' or
                 vbup~WBSTA eq 'B' ).
    Best regards,
    Andrea

  • Difference between "base quantity" and "operation quantity" in an operation

    Hello
    what is the difference between "base quantity" and "operation quantity" in a production order ?
    thank you for your answers

    Base Quantity - Quantity of the material to be produced to which the standard values of the operation refer.
    Operation Quantity - Quantity planned for this operation.
    Base quantity and operation quantity may not always be the same, if we have partial lots delivered during the sequence of operations, the operation quantity will be equal to the lot delivered during the operation.
    Base quantity is dependent on the BOM, where it signifies the total quantity of output after using the components of certain quantity.
    Hope this may help you.

Maybe you are looking for

  • Can portlets access external app login info?

    I need to write a portlet that uses the login information entered by users for external applications. The portlet will access the external application, but needs the login parameters that the user has supplied. Is this possible? If so, can anyone poi

  • Question about a conditional join

    Is it possible to do a conditional join based on a field in a table? say I have the query below and the table fields ate the bottom. I am trying to get the exact syntax for doing a conditional join. Can any one help? Thanks select e.fname,e.lname,a.a

  • Itunes backup error

    whenever i try to back up my library to a disc, i receive the "iTunes has encountered an error and needs to close" message. i thought it may be due to the "!" files i had, so i deleted them. however, the problem persists. dell dimension 4600   Window

  • Problem With MRP

    Hi Friends, I am facing a problem with MRP. In my Implementation, my Client is a Automobile Gasket Manufacturer. One major product line is Gaskets which is high volume and low price We will use Make to stock  with streategy 40. Now the queries are as

  • Error Code 2907

    Dear Apple Team, Please be informed that I am currently experiencing an issue flashing after i finished my call/ receiveng a call or miscalls, Showing this phrases as "ERROR in application occured Please call support qouting error code 2907". This is