In Requestor POWL, Shopping cart Related/Follow on documents should display as columns in POWL Table

Hello Experts,
Currently we are in SRM 7.02 implementation, for this we got requirement like below.
In Requestor POWL, Shopping cart related/follow on documents should display as columns in POWL. Please suggest me on this, how can i achieve this requirement. Thanks in advance.
1. we have Related/Follow on documents as shown in below screenshot.
2. As shown in above screenshot, these related/follow-on documents should show as columns in requestor POWL, as shown in below screenshot.
Thanks & Regards
Sivaram.

Hi Siva,
Take a look at the last part of the following document.
http://scn.sap.com/docs/DOC-25692
Regards,
Lisandro

Similar Messages

  • Sales order number in Shopping cart related documents tab.

    We are using SRM7.0 with classic scenario. Client wants to see the Sales order number (Created in Backend) for the backend PO in shopping cart Related documents tab same as other history like Confirmation and Invoice.
    How to update the sales order number to shopping cart? is there any BADI ? Please help me..
    Thanks Lot
    Srini.

    Thanks for Reply
    I have already tried validation and sub situation but that is not working and second is it is related to FI GL line item so SD consultant cant help i  that.
    Regards
    Shayam

  • Follow on document details not updating in shopping cart

    Hi Experts,
    I created a shopping cart  and created PO as a follow on document  from sourcing cockpit after assigning vendor.
    but Shopping cart is not updating with follow on document (PO)details even after running BBP_GET_STATUS_2 report also.
    Is there any other settings required to do for updating shopping cart with follow on document details.
    Thanks,
    Bhaskar.

    Hi ,
    Please check the repots ( jobs )  CLEAN_REQREQ_UP And BBP_GET_STATUS _2 are running..
    Check in RZ20 is there any error message for the follow on document.
    Thanks
    prasad.s

  • I1112 status of Shopping cart- Need to create a follow on document

    Hello Experts,
    I have one issue in which enduser had created a shopping cart and header status is approved but no follow on document is generated. at line item level the status is Error in Process.
    When i ran the report BBP_ALERT_SB_NOTTRANSFERED. then my Shopping cart status changed from I1111(item in transfer)  to I1112"error in transmission'..
    In Applicaiton monitor : the message is Not transferred to backend and Shopping cart 3100001911: Follow-on document(s)  not transferred. we are using Extended Classic Scenario and i dont know why we are getting this issue, we are getting this same issue only for 2 Shopping carts.
    Please guide me how i can repost the document so that follow on document will get generated.
    I am in ECS scenario with SRM 7.0
    Help will be appriciated.
    smriti

    Hi,
    If it is only the problem with only few carts, Check if any Short dumps are occuring in SRM as Well as in R/3.
    We faced a simialr situation and observed that it was resulting in a short dump due to bad coding in one BADI.
    regards,
    MRao

  • What is the difference between 'Shopping cart' and 'Team cart'

    Hi,
       There a knowledge about 'Team Cart' in SRM 7.0 .I want to know what is the difference between 'Shopping cart' and 'Team cart'?
       Thank you !
       best Regards

    Hi,
    SRM self-service procurement and requisitioning process was generally focused on the requestor and goods recipient. SAP SRM 7.0 introduces the new 'team' approach.
    Team purchasing enables users to:
    Define their own procurement substitutes
    Make shopping carts accessible to substitutes
    Substitutes (team members) are able to:
    Search for and take over team shopping carts
    Create follow-on documents (such as confirmations) for team carts they have taken over
    Regards,
    Jason

  • Shopping cart selection faded in sourcing

    Hello
    Sometimes the shopping carts created are not able push to  the work area as the check box of the cart is faded in the worklist .When we check the status through Monitor shopping cart ,In Follow On Documents it is showing as status "Approved".How to process the shopping cart in this case ,Is there any chance of making the cart check box to enable condition.
    Thanks & Regards
    Rajan.S

    If the SC is sourcing relevant it appears in sourcing cockpit of purchaser.
    It is open for work area (check box editable) till the  follow-on creation has not taken place.
    For self service SC (by employee) normally the follow-on is PR or PO.
    After approval SRM transfers this SC to table BP_DOCUMENT_TAB with follow-on no booked.
    and in BBP_PD you can see the status "item in transfer process".
    clean_reqreq... programme cleans this entry and creates follow-on.
    For sourcing SC (auto created by transfer of ext requirement ) sourcing follow-on like bid invitation or auction is created.
    BR
    Dinesh

  • Backend PO not getting created inspite of Complete shopping cart

    Dear All,
    We are having Classic Scenario with SRM 5.0 in integration with ECC 6.0 with support pack SAPKIBKT09.
    After Shopping cart creation with all details (fixed vendor, material, price etc) still backend system doesn't create PO. It always creates PR. Wht settings are missing plz suggest.....
    I understand that I have maintained under "Define objects in Backend system" as Purchase order if item data complete otherwise PR. Product categories has been transfered from backend.Document type has been created as ECPO in backend for PR and PO both.
    Kindly suggest any solution or pointers....
    Thanks
    Regards
    Dinesh Singh

    have you specified the backend po no range under
    SRM IMG ->Supplier Relationship Management->SRM Server->Cross-Application Basic Settings->Number Ranges->SRM Server Number Ranges->Define Number Ranges per Backend System for Follow-on Documents
    no range of POs (preferably as PO)
    this interval should be defined in above step
    Define Number Ranges for Shopping Carts and Follow-on Documents
    this no range should match to the external no range in ECC under
    IMG->Materials Management->Purchasing->Purchase Order->Define Document Types-> the desired PO doc type in ECC
    Aslo for attribute BSA yr ECC PO doc type should be available.
    If you are using ECC contract as a SOS for SC item
    For that coontract type in ECC the PR type should be liked in contract doc type config.
    Also check the logic in BADI BBP_CREATE_BE_PO_NEW
    BR
    Dinesh

  • Unable to create a PO from a shopping cart in classic scenerio

    Hi Experts,
    I tried creating a PO from the Shopping cart, but i am getting an error Number range 70 doesnt exist. Whereas
    when i tried creating a PO from Rfx, PO is getting created. Can somebody suggest what would have went wrong.
    Regards,
    Santhosh

    Hi Santosh,
    It could be possible that the number ranges are not defined or altered. Please check the path in SPRO(in SRM) for the number range of backend follow-on-documents.
    IMG : Supplier Relationship Management -> SRM server-> Cross Application Basic Settings->Number Ranges-> SRM server number ranges->Define Number ranges for shopping carts and follow on documents.
    Please check if number ranges are maintained properly for PO. After maintaining the details, try to push the shopping cart again. Check in RZ20 for the error details further(if it occurs again).
    Hope it helps.
    Regards
    Bash

  • My shopping cart number increasing everytime 2.

    Dear All,
    My shopping cart number range is increasing everytime 2.
    Per example as of now my shopping cart number 0000001 if i create next shopping cart nmber is coming 3.
    Can you please suggest me where we have control on this
    Thanks
    Ravi

    Ravi,
    I looked at Define Number Ranges for Shopping Carts and Follow-on Documents in the IMG and didn't see anything about an increment factor.  There are some BADIs, BBP_BS_GROUP_BE, is one of them, that be implemented to customize number assignments.  See if that is causing your issue.
    Otherwise, unless no one else replies, it could be a bug and you might need to open an OSS message to SAP.
    Regards, Dean.

  • Error:movement type for follow-on document missing

    Hello,
    Can anyone help me that i got the error message while creating the shopping cart from INTERNAL GOODS/SERVIES after adding the product id in the second step.
    Error :"movement type for follow-on document missing"

    i define BSA in ppoma_bbp as
    BSA: oneclnterp\nb
    and i define this number range Supplier Relationship Management ® SRM Server ® Cross-Application Basic Settings ® Number Ranges ® SRM Server Number Ranges ® Define Number Ranges for Shopping Carts and Follow-on Documents
    NO
    From Number
    To Number
    Current Number
    Ext
    Description
    (not in the table)
    01
    0010000000
    0019999999
    Shopping cart
    LO
    0020000000
    0029999999
    Faulty local PO
    PO
    4100000000
    4199999999
    Backend PO
    RQ
    0090000000
    0099999999
    Backend Purchase requisition
    RS
    9600000000
    9999999999
    Backend Reservation
    SE
    0200000000
    0209999999
    Backend Service PO

  • Need to delete PO value for a deleted shopping cart item.

    Hi SRM experts
    Please help me on below mentioned issue.
    I have a shopping cart with one deleted item, That deleted item shows a PO number under table BP_PDBEI field BE_OBJECT_ID in production server.
    User want that PO number to be delete or clear from that shopping cart deleted item.
    We are not authorize to delete or clear a entry from the SAP standard table itself.
    Is there any function module, I can use directly in production server which can delete / clear this PO number from table BP_PDBEI field BE_OBJECT_ID from shopping cart deleted item
    Please help urgently.

    Hi Sharma,
    normally if this PO doesn't have further follow-on documents, should be able to be deleted. Once the PO is deleted, the SC will be updated and in the follow-on document history of the SC you will see an additional remark "follow-on document deleted".
    But I guess, this is not what you would like to do.
    Without manual database changes you won't be able to delete the connection between the SC and PO.
    If you somehow will get authority to the database changes, please don't forget to delete also the relations between PO and SC. You will find it in the tables SRRELROLES and BBP_PDBINREL.
    Regards,
    Peter

  • Shopping cart line items are missing while transfering from ITS to EBP

    Hi everyone
    I am Raghu, working on EBP (version 2.0)
    Some shopping cart line items are missing while transferring the shopping cart data from ITS to EBP.
    For example in my shooping cart 4 items are there,during transferring shopping cart data from ITS to EBP all 4 items are getting updated for all the shopping cart related tables except account assignment table.
    In account assignment table for this particular shopping cart only 3 items are updated and usually the first line item gets missed out.Hence the the system fails to create the follow on documents in R/3. 
    This is happening randomly for few of the shopping carts that too most of the cases first item of the shopping cart was not updating reqacct table(this is account assignment table for shooping cart items).
    I have debugged entire scenario,but  couldn't find the cause for this..
    Can any one  please advise me....why this is happening?
    Your immidiate ersponse will surely help me a lot.
    Thanks,
    Raghu

    Hi Yann
    Thanks for your support.
    Yes, we are using EBP2.0/CRM 2.0C & the support pack level is SAPKU20C23.
    Please advice
    Thanks
    Raghu

  • Shopping Cart change by approver is not updating in approval preview screen

    We are using SRM 4.0 in ECS and have been noticing a problem with the approval preview on the shopping cart when the shopping cart is changed or rejected by one of the added approvers.
    The shopping cart was created with multiple line items for materials and when the shopping cart was ordered it workflowed to the 1st approver that was added.  He noticed that a price was wrong on one of the line items of the shopping and proceeded to change it and then approved the SC.  The approval preview screen in the SC shows that it was approved but the preview does not show that it was forwarded to the next approver listed on the preview screen.  However checking in the backend I'm showing the SC sitting in the inbox of the next approver stating: Your shopping cart 'MD D&C LL1 dvf Vetco-Subsea Wellhead Eq' was changed/rejected in part. Please check.
    Why isn't the approval preview updating when the SC is rejected or changed?

    hi,
    This  behaviour of the system is as follows , when the first approvers makes the changes and then approves the cart , it will go to the requestor of the shopping cart , and wether the workflow should restart --->
    depends on the security level of the approver who is changing the cart -->
    you can find the security level of the approver --> in the transaction SU01 ---> persononalization tab ---> key bbp_wfl_security
    and the text you have mentioned --->
    Your shopping cart 'MD D&C LL1 dvf Vetco-Subsea Wellhead Eq' was changed/rejected in part
    this is for the requestor of the cart ---> this is mail which specifies that the first approver has partially approved the cart.

  • Error in shopping cart creation

    Hello,
    We are creating a shopping cart and following error message has been displayed on the portal.
    The url was not called due to an error.
    Following notes were describing the error:
    Inetrnal error cannot sync.
    The error was occured on application server eccps_srq_50 and work process 4
    termination type TH_RES_FREE.
    ABAP Call stack was
    system-exit of program SAPLBBP_SC_UI_ITS
    Regards,
    Ashish

    Hi
    On what event, this short dump is happening. Please elaboarte.
    Can you please paste the details dump here. ?
    Hope this will help.
    Regards
    - Atul

  • Object: Error on Shopping Cart creation (BBPSC02)

    Hi all,
    While adding an item to a Shopping Cart, the following error is occurring:
    Error when processing your request
    What has happened?
    The URL https://srm.test.corp:8005/sap/bc/gui/sap/its/bbpsc02/~flNUQVRFPTIwMzA1LjAwNC4wMy4wMQ== was not called due to an error.
    Note
    <b>The following error text was processed in the system EST : Template interpretation failed. Template does not exist.
    The error occurred on the application server sapsrmt_EST_00 and in the work process 1 .
    The termination type was: RABAX_STATE
    The ABAP call stack was:
    Function: B40B_ACCSERV_CHECKACCASSIGNMT of program SAPLBBP_BD_DRIVER_40B
    Function: META_ACCSERV_CHECKACCASSIG_BUF of program SAPLBBP_BD_META_BAPIS
    Function: META_ACCSERV_CHECKACCASSIGNMT of program SAPLBBP_BD_META_BAPIS
    Form: COBL_CHECK of program SAPLBBP_PDACC
    Form: ACCOUNT_CHECK_SINGLE of program SAPLBBP_PDACC
    Form: ACCOUNT_MAINTAIN_SINGLE of program SAPLBBP_PDACC
    Form: ACCOUNT_F_CREATE of program SAPLBBP_PDACC
    Function: BBP_ACCOUNT_CREATE of program SAPLBBP_PDACC
    Form: ITEM_F_CREATE_FROM_WTAB of program SAPLBBP_PDIAD
    Form: ITEMLIST_F_UPDATE of program SAPLBBP_PDIAD</b>
    Going into the ST22, as Error Analysis it is suggested:
    “As a test, you can set the service parameter ~generateDynpro = 1. The system then generates the HTML page for this service without a template. You can then at least see which screen was sent by the WebAs. Make sure to reset the parameter to its original value.”
    Adding this parameter, the transaction is working properly, but is asking User ID and password to connect to the back-end (that seems strange to me!).
    A similar error (with different functions involved) is occurring while clicking on “Settings”: user settings are not visualized, but also changing the service parameter ~generateDynpro = 1, the transaction is working.
    Any idea on where is the problem?
    Thanks in Advance,
    #Bill J.

    Hi Luciano,
    these are the information coming from ST22 about the dump:
    <b>Information on where terminated</b>
    <i>Termination occurred in the ABAP program "SAPLBBP_BD_DRIVER_40B" - in "B40B_ACCSERV_CHECKACCASSIGNMT".
    The main program was "SAPLBBP_SC_UI_ITS ".
    In the source code you have the termination point in line 181 of the (Include) program "LBBP_BD_DRIVER_40BU34".</i>
    <b>Source code extract</b>
    164             IMPORTING
    165               expcobl        = e_backend_cobl[]
    166               messages       = return40b[].
    167           IF e_backend_cobl[] IS NOT INITIAL.
    168             REFRESH lt_backend_cobl.
    169             lt_backend_cobl[] = e_backend_cobl[].
    170             lv_change_in_badi = gc_yes.
    171           ELSE.
    172             IF lv_change_in_badi = gc_yes.
    173               e_backend_cobl[] = lt_backend_cobl[].
    174             ENDIF.
    175           ENDIF.
    176         ENDIF.
    177       ENDDO.
    178     ENDIF.
    179     IF lv_change_in_badi = gc_no.
    180
    >>>>       CALL FUNCTION 'BBP4X_CODINGBLOCK_CHECK'
    182         DESTINATION destination
    183         TABLES
    184           bbpcobl               = i_backend_cobl
    185           expcobl               = e_backend_cobl          "note 202684
    186           return                = return40b
    187         EXCEPTIONS
    188           communication_failure = 1  MESSAGE msg_text
    189           system_failure        = 2  MESSAGE msg_text
    190           OTHERS                = 3.
    191
    192       IF NOT sy-subrc IS INITIAL.
    193         CALL FUNCTION 'CONTROL_RECORD_ADD_VALUE'
    Any suggestion on how to debug are welcome.
    Thanks
    #Bill J.