Integrated Planning data entry via Analysis Office 1.4 SP7

Hi folks
I am following your blogs on Analysis office and have a simple question
We run at customer site analysis 1.4 SP7
I try to use it with a SAP BW IP query
In Bex and web my query works fine..
Data can be entered and changed
Opening the query as datasource in Analysis excel
( planning is turned on in settings of Analysis Excel) will not allow me to interact with the ribbon button for planning
All buttons are inactive
Any idea... Am I missing a step to use IP entry ready queries in Analysis excel?
Any help is  highly appreciated
Thanks
Joerg

Hi Jorg,
Once you insert the data source and do some planning on it, say change the input enabled fields. The planning ribbon should get active then.
Did you try this already?
You could also check the thread : SAP Advanced Analysis for Excel - Writing Back & Update and make sure that this is not the case for you.
Cheers,
Kriti

Similar Messages

  • Data entrying via Web-Dynpro

    Dear All!
    Can somebody help me to relaize the following requirement:
    Through WebDynpro (Internet Browser) data entrying. Suppose there
    are couples of input fields due to these fileds the user can entry
    datas into the system.
    Regards
    Ilhan Ertas

    Hi,
    Pl go through the following liniks
    Webdynpro Links
    Programming UI and Navigation
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9214b1e5-0601-0010-fdb0-ec32d43b06e0
    Webdynpro for Java
    http://help.sap.com/saphelp_nw2004s/helpdata/en/15/0d4f21c17c8044af4868130e9fea07/frameset.htm
    Webdynpro Samples
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/webdynpro/web%20dynpro%20sample%20applications%20and%20tutorials.htm
    Web Dynpro User Interface
    https://www.sdn.sap.com/irj/sdn/developerareas/webdynpro?rid=/webcontent/uuid/ce44a14c-0a01-0010-af89-d7dbd944f176 [original link is broken]
    PDf
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/com.sap.km.cm.docs/library/nw/netweaverdevelopersguide2004s/sap%20netweaver%20developer's%20Guide%202004s/UsingJava_00_PDFsList.ca
    SAP Netweaver Application Server eLearning Catalog
    https://www.sdn.sap.com/irj/sdn/elearn?rid=/webcontent/uuid/b1203f5e-0501-0010-bb88-915402c954f2 [original link is broken]
    DTR
    http://help.sap.com/saphelp_nw04/helpdata/en/88/cb0b405bacdd5fe10000000a155106/frameset.htm
    Regards
    Ayyapparaj

  • Reg: If changes done in SAP BO Analysis office, then Changes can be done in SAP BW in respective targets. But, is it possible to do the same changes in SAP ECC? How?

    Hello Everyone,
    If any changes are done in SAP BO Analysis office, then the change can be done in the SAP BW in the respective Targets.
    But how can we do the changes in the SAP ECC ? Is it possible to do the changes in the tables ?
    Any answer is appreciable
    Regards,
    Karteek

    We are using the "Input ready Bex query", in order to modify the values in "BO Analysis office".
    ECC               BI               BO Analysis office
    1  ------------->   1   ---------->         1   ------
                                                                            |
                                                                            | (Now Data is changed in Analysis office from 1 to 2)
                                                                            |
    (?) <--------------   2 <----------         2 <-----
    (Will it be updated in ECC)
    (Diagram Explanation)
    From ECC we can load the data (Consider Value-1) to SAP BI and from SAP BI we can load the data to BO analysis office.
    So, now if we change the data in BO Analysis office (Value-1 changed to Value-2)..
    Now the data is changed in SAP BI to Value-2.
    So what about the data in ECC ? Whether it is changed or not?
    Please provide us a real time business Scenario..
    Thanks,
    Karteek

  • Select Members in Data Forms via UDA or Substitutionvariable

    Hello,
    I want to select members in row or colum dimension of a Planning data form via an UDA. But it is only possible to select members via hierarchy (member, sibling, parent,...).
    Is there a possibility to select members via UDA?
    What I tried is:
    1.) in the definition of the dimension members for the dimension "Period" in the data form I filled in: "@UDA(Period,FC01)".
    I get the error "The member @UDA(Period does not exist or you do not have access to it."
    2.) Instead of the UDA I tried to use a Substitutionvariable "&PER_LIST"
    This works if the Substitutionvariable contains only one member. It doesn't work if it contains more than one member (comma-separated list).
    I get the error: "A substitution variable required for this calculation is undefined. Variable: PER_LIST" (even though the variable exists and I selected it in the member selection dialog)
    Can anyone help? I'm using Hyp. System 9.3.1.
    Thanks in advance,
    Nicole

    I would love to see the ability to select EDA's from Planning Forms, it would definately make life a little easier.
    As CL says, attributes are great at filtering forms and BR's, their only drawback is that you can only use them on sparse dimensional members.
    To get round this problem i've relied on security to filter out the accounts i do not need to see in the forms for the specific users, and kept the form selection on @IDESCENDANTS(Account_Parent).
    If you wish to filter on the Period dimension and this is a dense dimension, can you not get round the problem with rollups and, for example, @DESCENDANTS(Q1) to only return 3 months in the form, it really depends on your outline structure.

  • Distribute new entries against existing reference data, Integrated Planning

    Dear Experts,
    Within IP, I struggle with how to distribute new entries against existing reference data.
    Example:
    Reference data:
    Product   /   Customer   /   amount
    P1               C1                  100
    P1               C2                  150
    P2               C2                  120
    P2               C3                  100
    New data:(data entered on product level, therefore not assigd to customer yet)
    P3          #                    150
    How can I distribute product P3 to Customers with reference to the data on product P1 ?
    Many thanks,
    Erik Pos
    Edited by: Erik Pos on Jan 5, 2010 3:52 PM
    Edited by: Erik Pos on Jan 5, 2010 3:54 PM

    Hi Hyma,
    This documentation indeed indicates that you can use other characteristic values in the parameter group to be used for reference, good news !, but this is based on SAP-BPS ?
    The SAP-BW IP documentationn does not include this information can you confirm this solution works for Integrated Planning using the conditions within the function distribute with reference data ?
    Many thanks,
    Erik Pos

  • Date entry error in BI Integrated planning 2004s

    Hello,
    I am trying to fill a date field in BI Integrated Planning via mannual planning. The ratio was created as Dec type. When I introduce for example the value 01.01.2006 or 01/01/2006 and save the data, the new value is not saved in the infocube, so I suppose there is some kind of format issue. The same value in the former layout in BPS Web Interface was introduced as 01.01.2006.
    Morever, if I introduce the value as 20060101 or 01012006, BEx is close immediatly with a fatal error message.
    Other ratios in the layout like %of growth are save properly in the infocube.
    I have installed SapGui NW 2004s SR1 Presentation - 6.40 Compilation 5 and SAP Netweaver 2004s BI AddOn Patch Level 801 (Bw700SP08P_801-10001615.exe).
    Thank you for your help.
    Regards.
    Message was edited by: Ignacio Arroyo
    Message was edited by: Ignacio Arroyo

    Thank you Leon,
    In fact, I had already checked that the value was represented in BEx as 01.01.2005, after introducing the value from former Web Interface layout. However if I change the value to 01.02.2005 and save data, the value return to 01.01.2005. I don't think it is a definition issue, since other ratios in the same layout are defined with the same restrictions and are saved OK.
    Moreover If I introduced 01012005 BEx is closed with "Business Explorer critical program error occurred. The program has to close.  Please refer to the trace for further information" and of course that is not a good point for our final users ......
    The following lines appear in the BEx trace log file:
    +RSR_XLS_RFCtrc: 7.1875
    RSR_XLS_RFCtrc: 1.09375
    BExApplication.GetTemplate: DecimalSep = .
    RSR_XLS_RFCtrc: 14.0625
    BExApplication.GetTemplate: Instantiating Serializer: 0
    BExApplication.GetTemplate: DecimalSep = .
    RSR_XLS_RFCtrc: 1.09375
    BExApplication.GetTemplate: Instantiating Serializer: 0
    BExGrid.CreateFromDeSer: Deserializing
    BExGrid.CreateFromDeSer: DecimalSep = .
    RenderingGridCells: 907
    RenderedCells: 907
    BExExcelApplication.BeforeRender: Trying to set Display Alerts to false
    BExExcelApplication.SetNameAddress: ComException thrown El servidor lanzó una excepción. (Exception from HRESULT: 0x80010105 (RPC_E_SERVERFAULT))
    RenderValues: 0.15625
    RenderFormats: 0.46875
    RenderIndent: 0.15616
    RenderBuildInputRectangles1: 0
    RenderBuildInputRectangles2: 0
    RenderBorders: 0.156288
    Rendering Shape: 1
    Rendering Shape: 2
    Rendering Shape: 3
    Rendering Shape: 4
    Rendering Shape: 5
    Rendering Shape: 6
    Rendering Shape: 7
    Rendering Shape: 8
    Rendering Shape: 9
    Rendering Shape: 10
    RenderHierarchyShapes: 0
    BExExcelApplication.SetNameAddress: ComException thrown El servidor lanzó una excepción. (Exception from HRESULT: 0x80010105 (RPC_E_SERVERFAULT))
    RenderData: 10.78125Count:
    BExExcelApplication.SetNameAddress: ComException thrown El servidor lanzó una excepción. (Exception from HRESULT: 0x80010105 (RPC_E_SERVERFAULT))
    BExItemGrid.ProtectSheet: Protect Sheet
    BExExcelApplication - OpenQueryThreaded -
    Windows visible is set to true
    RSR_XLS_RFCtrc: 0.15625
    BExConnect.Dispose: Disposing BExConnect+
    Thank you for your help
    Message was edited by: Ignacio Arroyo
    +<i></i>+
    Message was edited by: Ignacio Arroyo

  • Problems with HowTo "Creation of BI Master Data in Integrated Planning...)

    Hi,
    one of our customers need a planning application in which he can create master data for different attributes, insert some key figures for this attributes and changes already planned key figured.
    For the last two point I've already found a working solution, the first point (creating of masterdata in web template) is still a problem. After a little search, I found a howto-guide "Creation of BI Master Data in Integrated Planning (IP) through Web Layouts", in which the necessary steps are described, how to do this (please see following link: http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/607193d5-cdd5-2b10-c699-8ff04c3124f6)
    Does anyone of you know this guide and was able to build a working solution?
    I have different questions, maybe you could help me:
    - what kind of variable is he using?
    - do I need a DataProvider in Web Template?
    - how do I get the connection to the used variable in the button group?
    Thanks for your help.
    Regards
    Tim

    Hi Timo,
    you require two howtos to implement the solution.
    First, please take a look at the first document:
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/10d2b273-0e12-2c10-fab3-a34bde559f92?QuickLink=index&…
    In chapter 3 you see the prerequisites (note 1101726 and notes 1384495, 1387004 and 136772). By this, you change the system behaviour, not to check if the new inserted master data is valid (it can't be valid, because the entries are new!)
    And after this please implement the solution from the how to.
    Furthermore you can take a look at this how to, which might help you too:
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/607193d5-cdd5-2b10-c699-8ff04c3124f6?QuickLink=index&…
    Even if my first post is a bit old, my customer still uses this solution, at the moment we are on 7.3 sp06, so it is working in newer releases too.
    Hope this helps.
    Regards
    Tim

  • Downtime Management - planned outage entry for a past date?

    Using downtime management with success, however I forgot to enter a 'planned downtime' for some ad-hoc maintenance work a couple of weeks back. I now have a large outage spike appearing in my system availability reports (CCMSBISUITE) when I know it was a bit of planned outage work so should really be discounted. I have recurring a downtime window for our standard outage day, but this planned work happened outside of that window.
    Is it somehow possible to create a 'planned downtime' event for a past date, which will 'smooth' out the outage spike appearing in the BI reports? I'm getting 'invalid date' entries when trying to do so with Downtime Manager, but though someone might know how to do this if it's possible.
    Thanks
    Daniel

    I think you are out of luck on this one.  However it would not be too hard to develop your own report for creating a retroactive downtime.  We have done some analysis of the code for making our own enhancements to DTM and you will find CL_DSWP_DTM_MANAGER to be a good starting point if you have an ABAPer. 
    But I wouldn't invest too much in any custom solution, as DTM will be completely replaced in SolMan 7.1 (see note 1517275 and the help at http://help.sap.com/saphelp_sm71_sp01/helpdata/en/bf/5a62721652477592bf3441cc5ab6ec/frameset.htm); the new feature seems like it will be much more general (an overall IT Calendar) but will actually remove some features in a step backwards (for example you will have to find somewhere else to document system crashes and other unplanned outages...).  If we get into the ramp-up I will report back to this thread on the specifics of retroactive downtime documentation in SolMan 7.1 if I find anything interesting.

  • Reg: Provide the best possible Scenarios regarding Planning feature of Analysis office as given below

    Hello Everyone,
    I am able to save the data back to the target from analysis workbooks using the Planning feature of the tool.
    Please, can anyone Provide the best possible Scenarios regarding Planning feature of Analysis office.
    Any answer is appreciable
    Regards,
    Karteek

    Hi
    Thank you for your post.
    The reason why your contacts didn't display is currently the Tamil language is not supported by the Windows 7.5 OS and we do not have any information if this language will be supported in the future or not. The current list of supported languages are:
    Brazilian Portuguese, Chinese (simplified and traditional), Czech, Danish, Dutch, Finnish, Greek, Hungarian, Japanese, Korean, Norwegian (Bokmål), Polish, Portuguese, Russian, and Swedish.
    In regards to being a smart phone, these come from a variety of manufactures using a variety operating systems each having there own unique way of functioning and features and as such it is the responsibility of the consumers to make an informed choice on what device would suit them based on specifications of the device which includes hard ware or software. There is no unified smartphone requirements as each use's different operating systems.
    So when purchasing a new device it is advisable to do some research on what device would suit your needs and if need be to speak to your local authorised mobile phone retailers for there expert advice. If at the point of purchase you were mis-advised and told that the Windows OS did support the Tamil language then this is something you will need to go back to the point of purchase otherwise it is your responsibility to make sure you choose a device that fully suit your needs.
    Regards
    If you find this post helpful, a click upon the white star at bottom would always be appreciated.
    If it also solves your problem, clicking ACCEPT AS SOLUTION below it will benefit other users!

  • Hyperion Planning - Link a web analysis report in a data form

    Hi all,
    is actually possible to link a web analysis report in a planning data form? I tried from a custom menu but discovered that isn't possible. Any other way?
    I'm working with Planning 11.1.2.1
    Thanks

    Hi Raffounz
    Indeed, it is possible to link a web analysis report in a planning custom menu.
    Follow this procedure :
    - From the explorer :
    -> Go to the folder where your web analysis report is stored
    -> Right click on the document and left click on "properties"
    -> Copy the "smartCut" link
    - From your planning application :
    -> Edit the menu where you want to link your webanalysis report :
    -> Create a URL item and past the link in the input field
    Cheers

  • How to use the same variable value for data entry and the planning sequence

    Hi,
    the scenario is the following:
    Using the WAD template a user enters cost center plan data. The cost center is selected by the chosen value for the variable "V1".
    Afterwards he shall push a button which starts a planning sequence (including saving the data and further functions). This planning sequence uses a filter that also contains the variable "V1".
    What or where has it to be defined that the planning sequence uses automatically the same value for the variable "V1" as selected for the data entry?

    You have to define in the planning function. The planning sequence is only a sequence and it read the planning functions underneath it.
    Ravi Thothadri

  • How to get the user log from the entried planning data ???

    Dear All,
    Could you help me to give the suggestion regarding that please .. ?? :).
    I have requirement to get the last user who in charge in modifying the planning data.
    Or in the other words, i'm gonna get the log from the entried planning data.
    e.g.
    1. Phase 1 - My Friend:
    Create the planning data :
    Country           Sales
    INA                 $1000
    2. Phase 2 - I update it and create new record.
    Country           Sales
    INA                 $1500          < modified >
    USA                $400           < new >
    Could i get the log from those records ??
    The log can be contain:
    the created user       &   modified user ??
    I just read the article regarding status and tracking system in BPS, but could i cover that requirement ??
    (Because i got that the status and tracking system for creating a workflow for planning).
    Or ..
    Is there other way that can fulfill this requirement  ???
    Really need your guidance all.
    Regards,
    Niel.

    Dear Mayank,
    Tks a lot for your responses.
    I've tried it but in BPS version..
    I saw in the document there is GUID (unique ID), could you explain me what the objective is ???
    I work out to plan to store the user created, date created, and planning level information in the log data.
    What do you think ..
    Is it better to display them in the BEx Report / another manual planning layout ???
    What did you display the log data in your case ??
    Still need your guidance ..
    Really - really thanks.
    Niel.

  • View temporary data in Web layout during file upload in Integrated Planning

    Hi Experts,
    When using File Upload funcationality, in Integrated Planning,
    I have a requirment, How user can view the data in the web layout?
    After data display user can make changes in the data and on click of Save the updated data is saved in cube.
    If any one has come across this requirment can you please help me out how things can be carried out?
    If "how to implement" document is present can you please provide me the link.
    Thanks and Regards,
    Abhi

    Hi Abhi,
    I assume, you are using WAD for this..
    Please do the following: (Please note the the cube has to be in Plan mode while executing WAD)
    1. Create a input enable query (through query designer) on th eaggregate level (the one you are using for IP). You might need to create filers for the aggregate level. these filters can also be used in the query.
    2. In the WAD, pull this query.
    3. Create a button in WAD and check for the planning functionalities readily available that you can use in WAD. One of the planning functionality is SAVE Data. This will save any data which is entered by the user.
    4. In the same button integrate a Refresh Data command after the SAVE data. This will automatically refresh the query and pull the updated/changed data from the cube.
    This should work. Please write back in case of any clarification.
    Regards, Rishi

  • Planned order creation via MRP depends, If we change Delivery date in STO

    Hi,
    Planned order  creation via MRP depends, If we change Delivery date in Stock transfer Order.
    I created STO with delivery date as 31.1.2012 and when i checked MD04, i can see Planned order created on 27.2.2012 with the same above STO quantity .
    Now when i changed the delivery date as 30.1.2012 and runned MD03, and then checkd MD04, planned order disappeared.
    Why Planned order got created when STO delivery date was 31.1.2012 and when I changed the delivery date in PO, planned order disappeared.
    MRP profile details :
    Plnd delivery time   1
    GR processing time   1
    Planning time fence  38
    Tot. repl. lead time 38
    Can you please let me know why system is beaving in this manner?
    Regards
    Utsav

    Hi,
    Normally , MRP runs based upon the requirements.If your STO is created for a date , system checks through the availabiloty check wheather there exists any stock for that date to get deliverred in the supply plant .If there exists for that date the stock , planned order will not be created.If no stock available then a planned order will be created in MRP.
    cHECK the availability check parameters assigned to material master in supply plant.
    Regards,

  • BI Integrated Planning - Most Current Data in Query

    Hi Experts,
    I have a small question about Integrated Planning, for a better understanding.
    in a workbook I have a reporting query and a button. the button triggers a planning function that is executed at another query (which is not displayed in the workbook).
    Both query's are built upon the same aggregate of a real time InfoProvider.
    Now when I execute the planning function, the new data (that is in the open request in the infoProvider) made by the planning function, is immediately displayed in the reporting query.
    But I did not inserted a 'most current data' infoobject in the reporting query.
    So how come that the data in the open request is displayed in my reporting query?
    Is this a new functionality of IP?
    Gr,
    K
    Edited by: Koen V on Feb 12, 2008 8:22 AM

    Thanks for the fast reply.
    Two times yes:
    - I meant the variable 'most current data'.
    - the queries are built on the same aggregate.
    So when you built a query on an aggregate on which a function is executed, it reads automatically the most current data.
    How does this happens? Is this a filter that is automatically set on the aggregate?
    I will assign points.
    Gr,
    K

Maybe you are looking for

  • Cover flow problem

    I recently converted to Mavericks. I'm finding that when I view files in 'cover flow' and delete a file from the list the picture of the file does not simultaneously delete and so become out of sync with the list. Anyone have this problem? a solution

  • Is this good enough, or is professional hosting necessary?

    Hi, I'm going to launch a site some time in the future, and is thinking about server. My internetconnection is 1/1 mbit, with my stepfathers machine doing p2p all day all night, and my brothers all evening, don't know the exact upload for those two,

  • Customizing

    Hi Colleagues, I  have a customer requirement in ESS.  we have currently implemented who's who leave requests Employee Search and Quota Overview Now client would like to have more link in this ESS page where employee can upload their photos, upload t

  • Times to start up

    Arch takes about 1.5 minutes to start up on my laptop. The systems up to date and running KDE4, also up to date. The last five lines in dmesg are: [   17.136178] Bluetooth: RFCOMM ver 1.11 [   46.120227] EXT4-fs (sda1): re-mounted. Opts: commit=600 [

  • How to install gcc and something around compiling

    Hi all.I want compile my wine with patchs but I can´t compile it checking build system type... x86_64-unknown-linux-gnu checking host system type... x86_64-unknown-linux-gnu checking whether make sets $(MAKE)... yes checking for gcc... gcc checking w