Internal Order restriction with Plant during PR & PO
Hi All,
Generally we create budget based PO for each plant.
So we have defined internal order for each plant and we assigned those order during PR and PO creation
But my requirement is i want to restrict the Order with respective Plant
e.g If Order VX123 is created for plant A then Plant B can not use this order during PR and PO.
So can it be possible in std SAP or i will go for Enhancement?
Regards
PR
Dear Priyaranjan,
You can achieve above requirement by using the Badi, at the time of creation/change of PR and PO.
For PO use ME_PROCESS_PO_CUST
For PR use ME_PROCESS_REQ_CUST
R,
Amala
Similar Messages
-
Issue services with different Internal Orders within a Plant from one PO?
Hiii... Please advice me of issuing services through one purchase order (one vendor comes and do the service to different machines of different internal orders in a plant) to different internal orders within a plant.
Thanks
Manojwhat is the problem? you can have Multiple Line Items in a PO (one for each internal Order).
And within one Line item you can add multiple service lines. -
IW32 - restriction or validation to accept only internal order from a plant
HI team!!
I´m needing your help
Im working with Tcode IW32 when creating a maintenance order and we got through Goto / Settlement rule we can assign any internal order number.
there is no restriction or validation to accept only internal order numbers from the corresponding plant, this condition may affect other entities
How can I limit it?
Thks & regards "In configuration, in settlement rule, restrict receiver other than internal order. In case if you want to have internal order as a receiver but restrict only some orders, you can do that using a user exit/badi at save.
example user exit -IWO10009 -
Internal order restriction for a particular GL posting
Hi SAP Experts,
I have created an internal order(statistical). I want to restrict the internal order postings for a particular GL accounts.
For example: Internal order 10001 can post only with GL 500003 and 500004 for Budget and Forecast (KPF6).
How is it possible.
Thanks,
SimarHi
I do not think that KA02 assignment alone would be a good option. You need to create a validation rule in GGB0 and assign the same in OB28 for your company codes. Also, you can look at the option of Substitution to populate the Internal Order field, when you use these GLs.
Regards
Sanil Bhandari -
Internal Order Budgeting with Purchase Order
Hi,
I am creating a purchase order for a material with account assigned as Order.
I have maintained a substitution wherein from a cost center Internal Order is derived.
I have created an Internal Order with Category - Overhead and activated the availability control for the Order. Also maintained the Budget for the Internal Order.
Now when I am creating the Purchase Order and giving the Cost center, it is deriving the Internal order but not doing the availability check.
What can be the issue in terms of Configuration or Am I missing any steps.
Please help
Regards
KamiThanks Eli,
If I activate the committment Management at Controlling Area level and the order type, the budget will be consumed at the Purchase Order level itself. I hope I am right ?
But I want , at PO level only the control and check (in terms of error message and the system should not allow me to save the PO) and not the consumption of budget. I want to utilise the budget only at the time of issuance of the materials.
Can we achieve this without Committment management active or is it mandatory?
Any help on this.
Thanks and regards
Kami -
Internal order - restrict charges
How do I restrict the charges to an internal order ? I want to use a new order type but restrict its use by Responsible cost centers and or cost type ( ie only Investment management cost centers and non labor only ) Do not want the order open for any group to charge
Hi,
I cannot understand completely your requirement, but in order to restrict the usage of I/O, you can use validation via OKC7 transaction. If you are talking about restricting changes to the I/O itslef (master data), you can use user exit COOPA002.
Regards,
Eli -
Internal Order settlment with Fixed amount
Hi. I'm having hard time. Please help me out.
Requirement:
I need to create settlement rule for Internal order.
When I do so, I need to define Fixed amount in OBJECT CURRENCY.
Given Condition:
Object Currency and Contorolling Area Currency is DIFFERENT.
(Controlling area currency is EURO, while Object currency is country local currency.)
Problem that I'm facing now:
When I try to create a settlement rule, it allows only Controlling area currency
for fixed amount, even though I need to create it with Object currency.
(Directly, the Field name is indicated as "Amount in EUR".
You know, usually we have 2 fields; 1 for value, 1 for currency. But in this case,
it seems that we have only 1 field for 1 fixed currency, which is Controlling area currency)
Is there any way to solve this issue?
I've looked into Settlement profile and Investment profile (for AuC order),
but both of configuration just had an indicator to enable fixed amount settlement,
but nothing about currency.There is not a perfect solution, however you can check OSS note 769818 for some helpful hints. It sounds like you want to use this for settlment of investment measures. If that's the case, you may want to consider using line item settlment intead of summary settlement. You have a little more flexible with that type of settlement and it may get you closer to what you want.
thanks, -
Internal order restriction for a particular GL
Friends,
I have created an internal order(statistical). I want to restrict the internal order postings for a particular GL account. How is it possible.Hi,
In OKB9, you can assign a particular GL against that internal order. Otherwise write substitution for that.
Regards,
Kalpik Shah -
Internal order created with incorrect auc number
Hi, An internal order was created but the asset number entered was incorrect. The internal order has now been settled but i need to change the asset number. Any help on how to do this and if i can what will happen to the settled amounts. Thanks
hi
reverse the settlement and assign the right asset number and again run the settlement. -
Error message display for PO creation with reference to internal orders
Sir,
While creating PO with Tcode ME21N (item category I) with reference to ' Internal Order with Funds provided (Tcode KO12), system displaying error message when Budget is exceeded.
But when Funds provision is not mentioned (Funds value is initial in KO12) , error message is not being given by the system during Po creation with ME21N.
Where should I configure in img(Tcode SPRO) , so that system will throw error mesage while creating PO without Budget Provision (Funds not mentioned ) in Internal Orders.
Regards,
Srinivasa MurthyHi Anupam,
The error message display as follows. (when the PO Price exceeds the Planned Funds kept for internal order)
This error comes during PO creation Process and PO can not be saved. This error message display is correct.
Item 001 Order 600643 budget exceeded
Message no. BP604
Diagnosis
In document item 001 Order 600643, budget for fiscal year 2009 was exceeded by 99,960,000.00 INR.
But my question is 'when funds have not at all been mentioned for the internal order' then system has to throw the same error as mentioned above. But it is not happening. System is allowing the PO to save which is not correct.
Regards,
Srinivasa Murthy -
Hi all,
my client has one requirement on Internal order report.
He wants report like internal order plan with actual value with cost centers. is any standard report available for the same or we have to develop any specific report.
if i want to write a Query through SQVI what are all table i need to joint. kindly suggest me on this.
thanks & regards
sudhaHi
thanks for your responses,
Here my requirement is i want to build report through SQVI only, my requirement will be.
inputs will be order number or order group from period to to period and fiscal year.
report fields should show order number, cost element, Budget amount, actual amount, variance, cost center plant.
so kindly suggest me how to build report for the above requirement and what are all the table i need to join in sap SQVI qiery.
Thanks
Sudha -
Internal order settlement rule
Hi Friends,
We have a internal order type with investment measure for AUC. When I create a internal order it is creating a AUC in the background but no settlement rule is updated. I released the order, posted some values and ran KO88 ( with and without TECO status) but still settlement rule is not updated with AUC. It is not even allowing me to update settlement rule manually with the AUC. Also in the settlement rule, I don't see AUC in the object type, but I see a FXA, not sure if it is an issue. Thanks in advance
Edited by: nspv81 on Dec 7, 2010 10:05 PMHi,
The system design does not offer the settlement type "AuC" for manually created settlement rules. This is correct.
AuC-settlement rules can only be created by the system automatically if the order/WBS-element has an investment profile with the flag "Manage AuC" set. The investment profile can be reviewed in transaction OITA.
If this is the case then the system will create the AuC rule during the FIRST run of a periodic settlement (update run) by automatically taking the AuC as a settlement receiver.
If you do however not use the investment profile you need to maintain a fixed asset settlement rule and enter the asset number manually.
regards Bernhard -
Inaccurate JE hitting wrong Internal Order
Hi
We got a journal entry posted during the month of February through FI (FB50). The JE got one P&L a/c (debit) and balance sheet a/c (credit). The P&L entry consist of a real internal order..That particular internal order consist of a budget (KO22) as well JE was posted for February without any errors. Budget also consumed accurately. The internal order was settled (KO8G) during the month end for the month of February and it had hit the respective cost center without errors.
This month we realized that the JE should not have been used an internal order. It should hit only a cost center. Not an internal order.
How to correct this entry? Please let me know the steps.. Budget also need to be revised to the original figure
ThanksHi Srikanth
Thanks for the reply
The orginal JV was posted by,
Debit - Expense (with internal order)
Credit - Bank
Internal order was settled during the month end and it has hit the cost center.
If I do the JV you mentioned, dont you think the cost center value will be double coz the settlement of the internal order has hit the cost center as well?
What will happen if I reverse the JV through FB08 and put a new JV with correctly..and suppliment the budget through KO24?? I guess the internal order problem will not get sorted if I do that right??
Thanks -
Hi Guru
I have come across Master program which required to create internal order.
Any BAPI for Internal Order creation (with example) ???.
Thanks
YogeshHi Mustafa,
Sorry for my late reply.I've just seen your message.
I have to use a BAPI since we are using a programm in MM module which creates Internal Orders automatically. With the help of this programm during creation of purchasing documents Internal Orders will be created simultaneously. We are now in the testing phase of the project and incase I need to delete Internal Orders which BAPI should I use?
Regards,
Fatma -
Any standard report on INTERNAL ORDERS:Overview
Hi Experts,
Report I need to develop INTERNAL ORDERS:Overview with Following requirement: R u talking about this, Can u help me out with this? Do u know <b>if there is any standard report</b> as well..Many thanks1
Report Layout
Sample Layout 1
Rows
Total Direct Expenses\Total Labor Expenses
Internal Order Number
G\L Account (Cost Element)
Columns
Month (1 through 12 months)
Actual Posting
Sample Layout 2
Rows
Total Direct Expenses\Total Labor Expenses
Internal Order Number
G\L Account (Cost Element)
Columns
Projected
Annual Total
Month (1 through 12 months)
Commitments
Sample Layout 3
Rows
Cost Center Expense
Cost Centers
Internal Order Expense
Internal Orders
Columns
Month (1 though 12 months)
Actual Postings
Note
Division between Direct and Labor expenses is defined by cost element range. The definition is query based rather than InfoCube or ODS object based.
Report Fields
[Please provide the fields and their descriptions in the report layout]
Field Name--Description-Data Element-- Info Source
Company-- Code Company Code --SAP ECC
Cost Element (G\L Account)--- Cost Element SAP ECC
Cost Center --Cost Center Number SAP ECC
Internal Order --Internal Order Number SAP ECC
Order Group --Internal Order Group SAP ECC
Cost Center Group --Cost Center Group SAP ECC
Cost Element Group--- Cost Element Group SAP ECC
Fiscal Year --Fiscal Year (same as calendar year) SAP ECC
Month ---Month (same as fiscal period) SAP ECC
Version (plan\actual\commitment) --Internal Order version SAP ECC
Plan Version SAP ECC
Amount Total Postings SAP ECC
<b>How to do 3 different Layouts, is it 3 different reports or the user needs drag&drop watever is required for him... </b>You can have 3 queries embedded into a single workbook.
May be you can also provide with all the query elements needed ( Structures, RKF, CKF )...so users can create on their own ( Query Writers ).
You can searh Help.SAP for Buss Content queries, change em accordingly...
First search if the datatargets provide you all information...
Maybe you are looking for
-
Hello I need some help. I would like to know how one changes the orientation of a page ex. in a 6 page documents. Let me explain. The first page is vertical but I have a chart to insert on the second and I would like that page only to be horizontal.
-
Interview question at progress soft
Hi, Please don't think this question as school home work.I had attended an interview at progress soft.This question I couldn't understand so help me. Sports Associations The Sports Associations (SA) wants to choose 2 teams of 4 people each to send to
-
Once I purchase a new application from Apple store by using credit card, I used to get the billing information in my mail the next day. But now a days it is not happening why?
-
HI all, Can anyone explain the logic in the code ? This is to display the pages numbers in page 1 of 4 page 2 of 4 format. i got this code in one of the forum. if the lineno is less then 64, th
-
When to restore controlfile, rman is complaining database not mounted?
to restore controlfile, shouldn`t the database be in NOMOUNT status? if yes, then why rman is complaining ORA-01507? where I went wrong? Please advise. C:\Documents and Settings\PhoenixBai>rman target / nocatalog Recovery Manager: Release 10.2.0.1.0