KSP4, KSVB, KSUB

Gurus,
Now that I have populated values through KP06, KP26, KP46.
I'm trying to go ahead with KSP4, KSVB, KSUB
The case with KSP4 is that I try to run all of the cost centers and the result the system gives is 'NO ERRORS' but also not relevant.
What does not relevant mean here?
And what is the purpose of this TCode KSP4
Kindly also give a detailed procedure for the other two TCodes as well.
Thanks, points available..

Hi:
Fot T.code KSP4 - Overhead ,Refer to sap.help
http://help.sap.com/erp2005_ehp_02/helpdata/EN/a9/ab75da414111d182b10000e829fbfe/frameset.htm
For T.code KSVB - Distribution ,Refer to this documentation
http://help.sap.com/erp2005_ehp_02/helpdata/EN/08/514e2e43b511d182b30000e829fbfe/frameset.htm
For T.code KSUB,Refer to this documentation
http://help.sap.com/erp2005_ehp_02/helpdata/EN/08/514e3b43b511d182b30000e829fbfe/frameset.htm
Please let me know  if you need more information.
Assign points if useful.
Regards
Sridhar M

Similar Messages

  • Clean the KSUB history in the S_ALR_87011763 reports

    Hello,
    Is there any chance to clean/erase all the previous inputs made in the KSUB so that won't pollute the S_ALR_8701173 report view?
    When I try to see this report, (after each time that I run the KSUB job), the reports take more and more time to be displayed.
    Anyone knows?

    hi ,
    Please check the business transaction of  posting made by KSUb and opy the transaction and exculde that business transaction .

  • What's the report to see the result after we run KSUB ?

    Dear All,
    Could you kindly help me ?
    I'm new for FI-CO .
    If i'd like to run assessment, and in the cycle I use Receiver Rule: Variable portion and type is Plan SKF . The sender will be cost center and receiver is WBS Group.
    Afterward, I run KSUB to run cycle.
    And I'm keen to see the result after doing the assessment, what's the report for it ?
    Could somebody tell me ??
    I wanna see the result from allocation ( type assessment). What's the report for it ?
    Thanks a lot.
    Have a good day,
    Best regards,
    Daniel N.

    Hi,
    the sender / receiver relation and the values are reported after executing KSUB.
    Another possibility is to execute KSB1 report for the sender cost centers and the assessmnet cost elements for the assessment period. Create a layout where the receiver (=partner object) is displayed.
    Best regards, Christian

  • Exchange rate type P not getting picked up while executing KSUB-Plan Assess

    Hi,
    We have Exchange rate type "P" maintained in SPRO in Maintain versions for the Fiscal Year 2010, but even then when I execute KSUB, it posts with Exchange rate type M.
    Has anyone faced this issue? We want it to pick up P and not M.
    Regards,
    SAPFICO

    Hi, set it here IMG-Controlling-Cost Center Accounting-Planning-Basic Settings for Planning-Define versions-Maintain Settings of Version in Controlling Area    then Setting for each f. year , double click on current f.year

  • KSUB - Cost Center Plan Assessment

    Hi All,
    I am doing a Plan Assessment for Cost Center in Trans KSUB and i need a Sender & Receiver Line items by Plant... I tried to use Filter but Plant is not present.
    I will be glad if anyone can help me out..
    Thanks & Regards
    Ajoy

    Hi,
    You can use only CO entities as senders/receivers, e.g. cost centres, internal orders, WBS, etc.
    Plant is not a CO entity and therefore cannot be used as an object in assessment cycle.
    Regards,
    Eli

  • Error in plan distribution (KSVB)

    Hi,
    When i run run plan distribution (KSVB), I am facing a error
    saying ' the document xyz does not exist'.
    I checked dat document in FB03 also, it doesnot there.
    How to resolve this??
    Regards,
    Swetha

    Hi,
    Have you done archiving of your documents? The error implies that one of CO documents that was created by previous run of allocation cycle (you cannot see it through FB03, but through KABP) is deleted, and therefore cannot be reversed. If you did not archive your documents, you can look at the following notes:
    186352
    192120
    ... and eventually execute RKCORR99_EASY report.
    Regards,
    Eli

  • KSUB - Plan assessment report currency

    Hi,
    I'm executing plan assessment cycle and i found the report showing (sender, receiver listing) currency in USD. Can help me to advice on how I can change the report to local curency/company code currency?
    Best regards,
    Shanti

    Hi
    After executing KSUB - Using the Menu options - choose LAYOUT - Object Currency / Comp Code Currency
    br, Ajay M

  • KSUB - Plan Assessment

    Hi Guys!
    When I execute cycle in plan assessment [ T-Code KSUB], I received a SAP office express info [ Business Workplace] " Express document " Update was terminated" received from author "  ". I view the report but there's no changes in data. Is the system terminate update?

    HI,
    Termination with an erroe "Express Document" in most of teh cases is due to the overlap of number ranges.
    Check the number ranges in KANK and set the current status to a higher level and run the assessment cyclenow.
    It should solve your problem.
    Reward if useful.
    sarma

  • Exchange Rate Type not working during plan assessment in T Code KSUB

    Hello Experts
    We had different exchange rate types created for different plan versions. We had Exchange Rate Type Z1 for Plan Version 01.
    We had maintained the same in Planning settings for the fiscal year 2011.
    We had created a new plan assessment cycle with version 1.
    Now when we execute assessment cycle it is not using the exchange rate from 01/01/2011. Instead it is selecting the rate from 01/01/2010.
    Is there something wrong when we copied fiscal year 2011 from 2010 for version 01.
    Request your inputs and help on this.
    Thanks
    Satya Alapati

    Hi Ajay
    Thanks for the information.
    We had not maintained the value date for any of our versions since we keep changing the rates for every period and wish to have the system pick the latest rate for the period.
    It has been the case in earlier years also.
    Thanks
    Satya

  • Allocation of cost from service cost center  to production cost center

    Dear sir ,
    Will I use to distribute the cost from service department to production department  and that cost centers also using for activity planing will get currect result in product costing ?

    Hello,
    Can you clarify what you want to do ?
    Allocation of cost from service cost centers to production cost centers can be done with the help of Assessment / Distribution cycles and you can do a activity planning using the same costs as well. The steps for activity planning would be as under:
    1. Create primary cost planning in the service and production cost centers (KP06)
    2. Create activity planning in the production cost centers (KP26) without any rate
    3. Run assessment / distribution cycles to transfer cost from the service cost centers to production cost centers (KSUB / KSVB), in case you are not transferring based on activity quantity then also do SKF planning in KP46
    4. Run plan cost splitting in case you have more then one activity type (do config for splitting structure beforehand) (KSS4)
    5.  Calculate Plan price for the production cost center activity types (KSPI)
    BR // SG

  • Standard Overhead distribution process in SAP

    Hi...!
    I need to work on Standard Overhead distribution process in SAP. As per my understanding Overhead Distribution process means - Assessment & Distribution.
    If my understanding is wrong, Please help me by providing some inputs to proceed further.
    Thanks,
    Anil

    hi  Anil
      You bare right. To allocate overhead expenses from OH Cost Centre to Other Cost objects ( CCtr,WBS Element,Orders etc) you can se Assessment cycle or Distribution cycle.
    For Plan
       1. Creat assessment cycle T.code KSU7 and execute T.code KSUB
        2. Creat Distri Cycle T.code KSV7 and execute T.code KSVB
    for further details write back
    kkumar

  • Allocation of Costs

    Hello,
    Can somebody please tell me how you can allocate the costs in a particular GL Account (and Cost Centre / Company Code), to various other Company Codes/GL Accounts/Cost Centres?
    Baiscally, we want the functionality of the Assessment process in SAP - however the Assessment in SAP does not allow for intercompany transactions.
    Is there any other alternative besides doing an Intercompany journal entry (which we want to avoid)?
    Any help would be greatly appreciated.
    Thanks!
    Rob

    Hi,
    For this you create an assessment cycle, where you define the percentage to the receivers, sending cost elements etc.
    IMG->Controlling->Cost center accounting->planning->allocations->assessment->define assessment.
    run KSUB to execute the plan cost assessment
    Hope it helps
    Regards,
    GK

  • What are the year end and month end activities carried in FI?

    Hi all,
    I am new to FI, what is the steps or the activites/process to be carried out during the month end as well as the year end activities for FI.
    Can anyone explain me about it and does sap provide any standard documentation on year end / month end activities.
    Thanks
    Pooja

    Hi Pooja,
    Please find the details below
    Month end closing Activities
    1. All the expenses including amortization, prepaid expenses, Preliminary expenses and accruals have been booked.
    2. Complete Bank Reconciliation (T. Code: FF67)
    3. Make sure that Sum of Inter Company balances is Zero
    4. Suspense Accounts should be cleared regularly.
    5. Ensure that all documents related to MM & SD have been entered in system. (T.Code:F-22 & F-43) 6. Ensure that all billing documents are released to accounting.
    7. Calculate Overheads on all process Orders (CO43)
    8. Technically complete all process orders which are fully processed (CORM).
    9. Calculate Variance (KKS1)à (Relevant only if Standard cost is calculated).
    10. Settle all process orders which are technically complete (CO88).
    11. Close All settled Process Orders
    12. Close MM period (Transaction Code: MMPV).
    13. Carry out GR/IR clearing (F.13) transaction
    14. Depreciation Run (AFAB) has been carried out for the month
    15. Close FI Posting period after the month end closing activity is over (T.Code:OB52) Year end
    Closing Activities:
    1. Calculate production work in progress on process orders which are not technically complete. (CO88).
    2. Carry out Assessment cycle for Cost Centers (T. Code: KSUB)
    3. All month end closing Activities should be carried out.
    4. Carry Forward Balances to next year With TC: F.16 we can carry forward the balance to next year. With TC: OBH2 copy the number ranges to next year Open next year periods by selecting the Posting Period Variant. then test by posting the transaction in F-02)
    SAP FI Month End and Year End Activities
    1 - Maintain Activity prices - KP26
    2 - Release of Standard Cost Estimate - CK40N
    3 - MM period close and open - MMPV
    4 - FI period open
    5 - Parked documents to be posted - FBV0, MIRO
    6 - Reposting of Inter Office CC - KB61
    7 - Bank Reconciliation
    8 - Update Section Code where missing - J1INPP
    9 - Maintain GRIR clearing - F.13
    10 - Provision for current month - FB50
    11 - Depreciation entry - FB50
    12 - Exchange rate - To be Updated
    13 - Revaluation of foreign currency open items - F.05
    14 - Recognition of Inventory at Bonded warehouse - FB50
    15 - Maintain Statistical Key Figures - KB31N/KP46
    16 - Variance Calculation of Process Orders - KKS1
    17 - Settlement of variances - CO88
    18 - Assessment cycles - Aux/WH CC to Main CC - KSU5
    19 - Assessment cycles - Functional CC to SBU CC - KSU5
    20 - Assessment cycles - SBU CC to COPA - KEU5
    21 - Profit Center Reposting - 9KE0
    22 - Balance Sheet Adjustment calculation - F.5D
    23 - Transfer Profit Center to AR & AP - 1KEK
    24 - Transfer Inventory to PCA - 1KEH
    25 - Assessment Cycle - Dummy PC to SBU PC - 3KE5
    26 - Check for u201CDelivery made, not Invoicedu201D - VF03
    27 - Match GL and PCA - KE5T
    28 - Match PCA and PA
    29 - Top Down Distribution in COPA - KE28
    30 - Reclassification of GL balances
    31 - Balance Carry forward (Year End Only) - F.16
    32 - PCA Balance Carry forward (Year End Only) - 2KES
    33 - Transfer to FI - 1KE8
    Regards,
    JA

  • Cost alocation and or distribution

    Hello Gurus,
    ive got a requirement to settle the spcific % of costs from one cost center and cost element into another cost element.
    These steps are done to calculate the primal cost of the workers months load. i.e. if we planned 1000 working hours, but the fact was 500 working hours then we should take 50 % from the posted amount and send it to a specific cost element and cost center.
    What is the best way to do that?
    Today ive created distribution cycle which collects the specific % of amount and sends it from Cost center and Cost element into Internal order (using TC: KSV5) then i close the IO with KO8G which puts the collected amount into a General ledger account (WITHOUT cost element) then those amounts must be manualy removed from the GL and sent to cost element with cost center.
    best regards
    Laurynas Prikockis

    Hi..
      You should allocate through assessment cycle to be created KSU7(for Plan) KSU1(for Act) and to be executed through KSUB (For Plan KSU5 (for Act).
    You also creat one secodary cost element in KA06 with Cat 42.
    Proceed. if any further help required pl revart back.
    kkumar

  • Plan Assessment and Allocation for Service Orders (CS)

    Hello,
    I'm trying to run plan assessment (KSUB) and plan allocation (KO9E) for a service order (created via IW31), but I'm not able to do it.
    I can do assessments (KSU5) and allocations (KO8G) with real values, but since I'm not able to do it in plan mode, I can't have comparative values between real and planned values (no value is flowing to allocation secondary cost elements).
    Can anyone let me know if this is some sort of limitation for Service Orders? Because I checked SPRO in transaction code KOAI and for this type of orders there is no Indicator for Integrated Planning, nor it's possible to assign a planning profile.
    Many thanks for any help you can provide!
    Regards,
    Cátia

    I created a SAP message and they confirmed that this is not possible.

Maybe you are looking for

  • Parameters to pl/sql pages

    Hi all, I installed the pdk examples showing how to pass parameters betweens pl/sql portlets. I saw it but not understand very weel. This is the same way to pass parameters between pl/sql pages? Is there any step-by-step that explain how to make the

  • Schema Validation Error details

    Hi, I am trying to get hold of the error message thrown when validating the schema. Somehow I am not able to get the details using - getfaultasstring() function but I can see the exact error message in the EM console when I open up the instance. Is t

  • Dvd drives not reading

    Our dvd drive on our Power Mac 2x2.66 GHz Dual Core intel.The drive is an Optiarc dvd rw ad-717a: sometimes will not read inserted discs. These discs work ok when tried on our I mac. Other discs work fine. This has occurred with discs that have bee w

  • Won't boot up, Won't boot up?

    Gray screen, spinning gear but will not start. Have restarted several times, same thing happens. I can hear running sound

  • How to create PDF form files

    Hi, how to do this: I have two PDF forms,  form "A" and form "B", both files are located in the same folder. Form B has an array of fields, like this: Name1, Address1 Name2, Address2 ...etc Form A only has one set of fields: Name , Address. How do I