IT IS VERY URGENT.....HELP ME OUT
Can any one detailed ON " Least cost Formula" in OPM of R12 with regard to :
1. What exactly is LCF
2. Where/when we can use, with examples.
3. Its Set ups
4. When it recommends to use this LCF
IF Any RCD (Release content docs) is there also plz sahre.
Regards
Raj

Hi Raj,
Define items,(products, ingredients,etc)
Define Ingredients item costs has been defined
(N) OPM Financials > Item Costs
Define technical Parameters(Numerical/Derived Cost, etc required for your setup)
(N) Formulator > Technical Data > Technical Paramerters
Then Assign Laboratory Technical Parameters Sequences ( for the above defined Tech parameters)
(N) Formulator > Technical Data > Technical Paramerters Sequences
Define your OPM item's Technical Data (with the above item tech parameters & sequences)
(N) Formulator > Technical Data > Item Technical Data
Create a new Formulation Specification
(N) Formulator > Formulation Specification Workbench > (M) Actions>New Specification
enter required data,
Ingredient Selection = Material Requirement
select Optimization Objective(minimise or maximise)
Create Material Requirement (Highlight your new specification, (M) Actions>New Requirement
menu.)
Create Technical Requirements((M) Actions>New Requirement object)
Approve Formulation Specification ((M) Actions>Change Status ->Approved for General Use)
Generate a least cost formula, for your Specification object ((M) Actions>Formulate, click generate button)
Click the Material View tab
Review the material View details
(Ingredient displays each ingredient with its Qty and, UOM and Description.Each technical Parameter associated with the ingredients and product are listed next to the item)
try this out,
regards
SeenuYarasi
(N) navigation, (M) menu

Similar Messages

  • Can sap ps be used for product development  for cost monitoring?

    sap-pp is configured but client insisting for product development they want sap-ps ,can sap ps be used for product development  for cost monitoring in textile industry?and how to configure with reference to sap-pp?
    venkatdas vanga

    Hi,
    SAP PS has good Integration with PP and FI CO modules. So goes well along the ETO scenario.
    The normal process is that Project is created and goes in to design phase , where we design product as per customer's requirement . Design BOM helps in this.Once you design is ready you can generate Production Orders base on MRP generated with reference to Projects.
    All the cost including overheads are charged to the Project as actual cost.
    These costs are later settled to Cost Center.
    Refer this link for detailed information http://www50.sap.com/businessmaps/76FC9D515D244754A09308BA54E97C42.htm
    Thanks,
    Nitin

  • Use of template using CPT1 for charging an additional cost to the product

    Hello,
    I'm trying to charge an additional cost burden to the cost of my product for every base unit produced. (cost estimate)
    I have created a template using transaction CPT1 with sender as Cost Center / Activity Type in environment 001
    The activity type is measured in EA (Eaches) while we make our product in boxes (Product base unit of measure is 'Boxes') with say 20 Eaches going into a Box
    I have maintained an activity price using transaction KP26 at say $0.55 per Each
    I have assigned this template to my costing sheet , valuation area and overhead key using transaction KTPF
    When I now cost the material for costing lot size of a 1000 boxes, it still charges the product with the activity price per Each ($0.55) instead of multiplying  $0.55*20*1000 = $11,000 for a 1000 boxes
    The formula I have chosen in the template against 'Plan quantity ' is in the attachment enclosed:
    I need help with doing the right thing within the template to make it give a cost burden of $11000 for every 1000 boxes costed (costing lot size)

    Didn't realize that you have to use transaction CPTD to charge template overhead to production orders. That's why it was not working. Now it is posting by reading the confirmed yield. But it is still not converting eaches to boxes using the conversion factor in the material master.
    The formula I'm currently using in the template for actual quantity is as under:
    OrderYieldConfirmed / AltQtyFactorFromMaterial( AlternativeQuantityUnit
    = 'BX', Material = OrderMaterialNumber )
    Please tell me what I need to do to the above formula to make it convert boxes to eaches using conversion factor in the material master?
    A similar formula has worked beautifully for 'cost estimate'
    OrderTotalQuantity / AltQtyFactorFromMaterial( AlternativeQuantityUnit =
    'BX', Material = OrderMaterialNumber )

  • Rough BOM at the time of product development

    dear expert:
    excuse my nascent approach. i dont know how to address this but my client is asking to fullfill the below requirement
    we are Apparel manufacturing company. as per our scenerio we pass a long development period approx 6 months before receiving confirm sales order. we need to create preliminary or rough BOM at this stage to manage the sudden load of information. as during the development time we just got little information about the product and it is subject to change is it possible to create a rough BOM and update it continuously as and when required with proper material code and finally when we are sure we need to confirm it as final BOM.
    please suggest.
    best regards
    javed iqbal

    Dear
    We are dealing this kind scinario in small project business where total product developement takes mini 4-5 motnhs and based on design BOM is not confirmed 100% .
    So we do estomation through Quotation stage -VA21 where we follow Unit costing methodology with variable and item details based on the customer requirement.Some time we also create Engineering BOM based on the design lay out and after final approval and contractual aggrement , we logg sales order for cost roll up based on the approve BOM and routing .There may be  lot consumables as well low cost material required  , which we add directly at Production order but the most crtifcal items are in Qoutation or estimation stage  /Engineering BOM.
    But if you want to create BOM at the intial stage and subsequently , want to trace the changes doen then you should adop ECM ( Engineeting Change Management ) .For engineering change management to be activated you need to define in
    modification parameters that ECM is to be active.
    Following is the link where you can get details
    http://sap-img.com/pp007.htm
    engineering change management
    Engineering change management
    Regards
    JH

  • Settlement of New Product Development Projects

    Hi Experts,
    We are working on New Product Development project. Our client involves in development of a proto-type as per their client's requirement. Receipt of Sales order, Design, Production of Prototype Sample & customer approval are the stages invloved.
    But no revenue will be generated until the delivery & approval of Sample.
    How can we settle these kind of projects? Please advise.
    Thanks & Regards,
    Kabir

    Hi Hemant & Venu,
    Thanks for the replies. Points awarded.
    @Hemant...There is no billing element used in this project. I guess i cannot consider this as an Investment project fully as it does not have an Asset. Please correct me and advise.
    @Venu...Can i settle all objects to the cost center for this kind of project? Please help me with Settlement configuration Tips.
    Thanks & Regs,
    Kabir

  • Post advertising costs as per product lines

    i need to capture cost and revenue as per the product lines(divisions in sd)  for tangilble and intangible goods, if i add more profit centers based on product lines then i need to create at least 96 more profit centers.
    is there a possibility to generate a report through sd for product line wise report where the cost of goods sold and revenues can b captured product line wise ?

    Hi,
    I don't think you can get such a report out of standard SAP SD module. What does a Product line represent in SD? A sales area? As you know, Revenue is stored PR00 (usually) conditon type and COGS is stored in VPRS condition type, you could consider creating a custom ABAP report to get margin report based on Product line using these details (table VBAP, KONP etc.,).
    Othewise, if CO-PA is an option which you could explore, then suggest CO-PA, for a more flexible/granular reporting.
    But, I did not understand the relevance of your thread subject 'post advertising costs as per product lines' with your post. So, as per you, is 'Advertising cost' and COGS are same?
    Hope this helps.

  • Short Dump while executing costing run or production orders

    Hi Guys,
    While executing the costing run or production orders saving, we are getting short dump.  it is the debugging is showing its fingers at A035 which is related to maintenance of overhead rates.
    We have maintained the overhead rates correctly. There is no issue.
    This could be some thing related to OSS notes as well.
    Just wanted to know if it has got something to do with OSS notes or something else.
    Please throw some light in this regard
    Thanks in advance

    Hi,
    In what program there is a dump? I mean, what is the log saying?
    Regards,
    Eli

  • Selection of Costing Sheet in Production Order

    Hi friends,
    I have one query, details of which are as  follows.
    Costing sheet in Requirement Class - Blank
    This requirement class assigned to Requirement type which was derived in Sales order through Material master and hence Costing sheet in Sales order is blank.
    Costing Sheet in Valuation variant (Plan) is Z0010 which is assigned to Costing Variant (Plan). It was assigned to Order type.
    Costing sheet in Valuation variant (Actual) is Z0020 which is assigned to Costing variant (Actual). It was assigned to Order type.
    I have created a new Valuation variant T01 in which Costing sheet is blank. It was assigned to a Particular Plant.
    When i am creating the Production order with reference to the Sales order in that Particular plant, system is deriving the Costing sheet as per Valuation variant (Plan) which is common instead of picking from the plant specific valuation variant.
    So, its calculating overheads and is impacting our Goods receipt valuation (In this plant, GR Valuation is as per Plan cost of the Production order).
    I tried different combinations, and finally observed that it is picking the Costing sheet from the valuation variant (Plan) which is common and not Plant specific.
    Is this system behavior correct as per SAP Standard?
    Kindly advise on the same
    Regards
    Madhusekhar Gupta G

    Hi Madhu
    1. Production order gets coating sheet from the valuation variant assigned to order type
    2. The valuation variant that you assign to Plant is for standard cost estimate only
    3. For your case, create a new costing variant without costing sheet and assign the same to the order type for this plant
    You can assign different costing variant to the same order type per plant
    Br. Ajay M

  • Cost  of finished product repetitive manufacturing

    Hi,
    My clients produces 5 different finshed products always. I want to map the scenario in Repetitive manufacturing.
    Is it possible in REM to get the actual cost of production of 5 products separately?? fir example can i get cost of finished product 1 as Rs200, in the month of Jan2009 for 10 quantity, cost of finished product 2 in the month of Jan2009 for 5 quantity etc etc .
    Regards.

    Thanks to all for their valuable inputs.
    Dear Mangalraj: Its really a challenge for me to decide whether to go for REM or not. The reason why I am not going for discrete is :
    1. Client doesnt know how much of ( for example) fertilizers it issues for finished 1 or finished 2 . client says he  knows that in a month how much he has used  for example 100 kg of fertilizers in total, not on basis of finished goods. So, i think i will have problem during BOM creation and goods issue in particular.
    2. Since finished products are rose plants, jasmine plants etc, client says i dont how much to do Goods reciept. few plants may still be not ready to be able to do goods reciept.Client says its very difficult for me to count flower plants everyday and then say out of 1000, 10 are ready to be done Goods reciept and 15 are dead so these should be scrapped etc.
    These are the resons why i thought it to map to REM. But client also wants to know price of each plant , means whats the price of rose plant(per plant), price of jasmine plant( per plant).
    Request you all to throw some light on this..
    Regards.

  • Percentage based overhead based on target cost of actual production

    Hello,
    I'm trying to calculate percentage overhead (overhead as a % of total cost of production) using the usual overhead group, overhead key ,costing sheet, etc.
    Also put the overhead group in the material master.
    Although I am getting it correctly as part of product cost planning, when it comes to calculating this overhead on a production order, it does it based on 'total actual costs' posted to the order. I want it to calculate the % overhead based on the standard cost of actual production (the target cost).
    I would really appreciate some help on this.

    Hi
    If that's the requirement, you can achieve through template allocation. Refer the doc contributed by arturo senosain
    I use a workaround for such cases. Add an activity type in routing with activity quantity same as base qty of routing.. Say, 1 PC
    Maintain the activity price as .15. And you are done
    Br. Ajay M

  • Cost center to production order

    hi friends
    i have material cost on a cost centere A, i want to allocate thru assessment cycle from cost center to production orders. when i enter production order nummbers in ksu1 in allocation cycle as receiver, system give an error that it is "No valid receiver enteries exist".
    sapians

    Hi,
    You have to check two things before executing this assessment cycle.
    1. Check the allocation structure whether you have assigned the assessment cost element and
       settlement of cost element to ORD (ticked in by cost element box).
    2. In KSU7 you have filled the allocation structure field and received field and tracing factors.
       Have a check of the cycle before saving.
    Regards,
    Sadashivan

  • Cost center for Production Order

    Hi all,
         We are now not able to get a report of Material consumption cost, Cost center wise. It is Because cost center is not linked to Production order or not linked to material issued to production order. Can we get the cost of material cosumption for  production order cost center wise. Please give us a solution.
    With Regards,
    R.Mahendiran.

    Hi,
         Prod order is linked with controlling, for the direct costs like material cost linked with accounting view, costing view and secondary costs are linked with costing tab in work center and inturn workcenter is assigned to cost center, and for the prod order controlling part you will be assigned to the costing variant in transaction OPL8, if you remove this you can't get any reports.
    To understand the difference
    201 - Goods issue against cost center. Means you create reservation through MB21 and do posting of cost directly at cost center.
    261 - Goods issue to Production order. Means you create a reservation through Production order  and do posting of cost to Production order. When cost settlement of production order is done cost from production order will get transfered to cost center mentioned in settlement rule of production order.
    Hope this clarifies your doubt.

  • REM Product cost collectors and Production version

    Hi All,
    Can some one pls let me know
    What are the product cost collectors in REM and how to create the product cost collectors ?
    What is the production version and the difference between production version and controlling version?
    Thanks & Regards,
    Bujji

    Dear Bujji,
    A product cost collector is a cost object in Product Cost by Period that collects the periodic actual costs incurred in the production of a material. It can be created in txn KKF6N.
    [Product Cosr Collector|http://help.sap.com/saphelp_47x200/helpdata/EN/08/77ba810a1611d3a6b900104b55d538/frameset.htm]
    [Product Cost Collectors: Collective Entry for Repetitive Manufacturing |http://help.sap.com/saphelp_47x200/helpdata/EN/08/77ba810a1611d3a6b900104b55d538/frameset.htm]
    A production version determines the various production techniques that can be used to produce a material. It defines the following information:
    Alternative BOM for a BOM explosion
    Task list type, task list group, and group counter for assignment to task lists
    Lot-size restrictions and period of validity
    A material can have one or more production versions.
    It can be defined in the Material Master (txn MM02) in one of the following views:
    MRP 4
    Work Scheduling
    Costing 1
    The costing version is a different issue. It is a costing parameter and is used to save several cost estimates for the same material, with the same costing variant and the same costing date (e.g. in oder to cost the material several times with minor changes without creating new costing variants).
    BR,
    Antje

  • Primavera webcast: Strategies for New Product Development and Innovation

    [Strategies for New Product Development and Innovation Success: Project Portfolio Management for the Industrial Manufacturing Recovery|http://www.bulldogsolutions.net/OracleManufacturing/ORM02252010/frmRegistration.aspx?bdls=23246]
    Jim Brown, manufacturing industry expert and President of Tech-Clarity, will discuss how leading manufacturers are shifting their product portfolios for the economic recovery, emerging from survival mode and resuming growth strategies.
    * Webcast: Strategies for New Product Development and Innovation Success: Project Portfolio Management for the Industrial Manufacturing Recovery.
    * Date: Thursday, February 25, 2010
    * Time: 11 a.m. EDT
    * Registration: http://www.bulldogsolutions.net/OracleManufacturing/ORM02252010/frmRegistration.aspx?bdls=23246
    For questions about this event, please contact Julie Castro at +1 415 608 4677.

    [Strategies for New Product Development and Innovation Success: Project Portfolio Management for the Industrial Manufacturing Recovery|http://www.bulldogsolutions.net/OracleManufacturing/ORM02252010/frmRegistration.aspx?bdls=23246]
    Jim Brown, manufacturing industry expert and President of Tech-Clarity, will discuss how leading manufacturers are shifting their product portfolios for the economic recovery, emerging from survival mode and resuming growth strategies.
    * Webcast: Strategies for New Product Development and Innovation Success: Project Portfolio Management for the Industrial Manufacturing Recovery.
    * Date: Thursday, February 25, 2010
    * Time: 11 a.m. EDT
    * Registration: http://www.bulldogsolutions.net/OracleManufacturing/ORM02252010/frmRegistration.aspx?bdls=23246
    For questions about this event, please contact Julie Castro at +1 415 608 4677.

  • Target cost for a Production order

    Hi
       How to get Target Cost for a production order?
    Thanks
    Naga

    Well Naga, Right now I’m on HR implementation , but I programmed same kind of requirement two years before , but I got planned cost and actual cost .
    I also notice “cost analysis" the cost is not exact , it wont read the value from KP26 of that particular month .
    Here I am talking about 4.5b system.
    You can find the sales order ref on production order, and your production order is made up of your different kind of material like scarp, raw, semi-finished etc
    Here are the steps I followed .
    1- I read the material which you can see in material component on production order in Co03.
    After that I take the qty and also multiply by the cost at which machine is posted .
    I have that programs, as I need to find out . I’ll post you later .
    But you have to read the tables afko,afpo,afru,caufv,cost ..etc
    Do you see information structure I refer you , If i am not wrong this CO3 ( cost analysis ) report use report painter ( Tr.Gr51,Gr52 ) . you can also see by going in to said transaction which information structure its populating . This’ll also help you.
    Hope this’ll give you idea!!
    <b>P.S award the points.!!! DOn`t forget :)!!!!</b>
    Good luck
    Thanks
    Saquib Khan
    "Knowledge comes but wisdom lingers!!"
    "Some are wise and some are otherwise"

Maybe you are looking for

  • Store downloading to wrong drive

    Back in the day, I used to use an external hard-drive for all of my media because it took up so much space. My Mac mini simply didn't have enough room for my gargantuan collection of music. Then I bought my MacBook Pro and decided that the external h

  • FTP Publishing

    I have a site that I built using a PC application that has a ton of reference files in .pdf on it already. I want to use iWeb to maintain the site as part of my divorce from Mr. Gates. I do not want to have to reload the referenced files. If I publis

  • Upgrading student edition for commercial use?

    hello i have called up the Adobe customer service line twice now and been given two different answers to my questions, so i have decided i would give the adobe forum a go as you guys seem on the ball, and most likely don't work in an Indian call cent

  • 2 New Free Elearning Courses – vSphere Data Protection Advanced and IT Business Management

    We've added two more elearning courses to the extensive libraryof free VMware training classes. vSphere Data Protection Advanced [V5.8] Fundamentals - provides information about the vSphere Data Protection Advanced backup and recovery solution for vi

  • Macbook pro keeps slowing down

    My Macbook pro had been playing up lately.  Looking at the activity monitor the Memory Pressure keeps going to red and slowing the computer down. A Safari Web Content process keeps opening up and causes it to use up all the RAM, slow down and a few t