Loading data from Cube to Planning area

Hi,
         If I am loading data from a cube to a planning area using transaction TSCUBE,
does the system load data into planning area for the combinations that exist in the cube or does it load for all CVCs?
For example,
I have my CVC as Plant, Material, Customer
If there are 4 CVCs in the POS that were previously generated as
Plant--Material--Customer
01--M1--
C1
01--M2--
C3
01--M2--
C2
01--M4--
C5
If the cube has data like this:
Plant--MaterialCustomer----Qty.
01--M1C1--
10
01--M2C3--
20
01--M2C2--
5
(doesnot have the last combination), then if I use TSCUBE transaction to load data to Planning area from this cube,
is the data loaded as
Plant--MaterialCustomer----Qty.
01--M1C1--
10
01--M2C3--
20
01--M2C2--
5
Only for the 3 combinations that exist in the cube and not load anything for the last one
OR
is the data loaded as
Plant--MaterialCustomer----Qty.
01--M1C1--
10
01--M2C3--
20
01--M2C2--
5
01--M4C5--
0
Load all 4 combinations and send 0 as the cube doesnot have this combination?
Hope I am clear on this question.
Thanks.

Thanks a lot Vinod, Srinivas and Harish. The reason why I am asking you is that we have a scenario where we get this situation.
We initially get data from R/3 to BW to APO like the below:
Plant--MaterialCustomer----Qty.
01--M1C1--
10
Later when the customer is changed or bought out by somebody C1 is changed to C2. Some times when the business doesnot know who the customer is initially they just put C1 as dummy and then after sometime replace it by C2. Then the new record coming in is as follows:
Plant--MaterialCustomer----Qty.
01--M1C2--
10
BW can identify changes in transaction data  but not in Master data. What I mean by this is when Qty. 10 changes from 10 to 20, the system can identify it in deltas.
If the customer (master data) changes to C2 from C1, the system thinks it's a new record all together then if I use delta loads, it gets me the following:
Plant--MaterialCustomer----Qty.
01--M1C1--
10
01--M1C2--
10
If I am looking at Plant and Material Level, my data is doubled.
So we are planning to do a full load that works like this:
1. Initial data like the below:
Plant--MaterialCustomer----Qty.
01--M1C1--
10
The CVC is created and the planning area has Qty.10
Then we delete the contents of cube and do a full load into the cube with changed customer
Plant--MaterialCustomer----Qty.
01--M1C2--
10
This time a new CVC is created. Then we have another 10 loaded into Planning area.
If the system loads all CVCs, then the it would send
Plant--MaterialCustomer----Qty.
01--M1C1--
0
01--M1C1--
10
If the system loads only combinations in cube,
then it loads
Plant--MaterialCustomer----Qty.
01--M1C2--
10
But the system already has another 10 for Customer C1 duplicating the values.
We are trouble in the second case.
We had to go fr this solution instead of realignment as our business has no way pf knowing that C1 was replaced by C2.
Hope I am clear.

Similar Messages

  • Loading data from cube to Planning Area - Error

    I have two cubes. one has history data and other ratios.
    the forecast is dis aggregated based on that ratios.
    first the ratio data is getting loaded and gets populated.
    when i try to load the history data, a error says, CVC not maintained.
    there are totally 6 Char used in this Config.
    MPOS is created using the ratio cube and has the same char as in history cube, additionally one more sub family.
    Can some one help me in this.??
    Thanks !!!

    hi
    char in hist cube           
    mkt fam                           
    mkt seg                           
    regn                                
    gobl                                
    cntry 
    Char in the MPOS(from Ratio cube)
    mkt fam                           
    mkt seg                           
    regn                                
    gobl                                
    cntry 
    sub family                           
    the main obj of not including it in hist cube, i forecast @ mktfam level n dis aggre to sub family.
    if i include the sub family also in hist cube, then i can forecast @ sub family itself..
    the whole dis agg. logic does not serve the purpose.
    On the Adjustment of Time series, will try it n revert n back.
    like can you please tell me how it affects the process???? or the logic behind doing this????
    Thanks!!!
    Edited by: Aswath ram on Sep 10, 2008 6:33 PM

  • Load from cube to planning area

    Hi,
    We are facing a problem in loading data from Cube to planning area, we need to distinguish between the Zero and the blank values in planning area when loading data from cube to planning area.
    Scenario is like this.
    For a CVC u2013A on day D I am having key figure value as blank and on D1 is Zero and on D2 is 2, I want the same to appear as my planning area data If I load this data to cube my day D value will appear as Zero  (but it was blank) and on D1 Zero and on D2 as 2 in cube.
    I am using Std T-code /SAPAPAO/TSCUBE to load data from cube to planning area, in std T-code we are having option of ignore Zero, if I use this it will also stops the actual zero value(which I need) on day D+1 to come in to planning area which I donu2019t want.
    I want my planning area data to be as blank on day D and Zero on D1 and 2 on D2 after loading data from cube to planning area..
    Can any one put some light and help me out from this issue.
    With regards,
    Sreerama

    Hi Seerama,
    I am not sure to understand completely the issue: do you have an issue in the cube or in the planning area?
    In order to differentiate a blank for a zero in the planning area, you need to set the flag "zero allowed" in the planning area settings. (in the tab keyfigure, click details, then for each key figure you can select or not the flag "zero allowed")
    When you load the data, you should indeed not flag "ignore zero value"
    If the issue you have is in your cube (between the file and the cube) then it is another matter...
    Kind Regards,
    Julien

  • I need format for data in excel file load into info cube to planning area.

    Hi gurus,
    I need format for data in excel file load into info cube to planning area.
    can you send me what should i maintain header
    i have knowledge on like
    plant,location,customer,product,history qty,calander
    100,delhi,suresh,nokia,250,2011211
    if it is  right or wrong can u explain  and send me about excel file format.
    babu

    Hi Babu,
    The file format should be same as you want to upload. The sequence of File format should be same communication structure.
    Like,
    Initial columns with Characteristics (ex: plant,location,customer,product)
    date column (check for data format) (ex: calander)
    Last columsn with Key figures (history qty)
    Hope this helps.
    Regards,
    Nawanit

  • Error while copying data from infoprovider to planning area

    Hi,
    Error for COM routine using application program (return code 40,075)
    Message no. /SAPAPO/OM102
    Diagnosis
    An application program has called a COM routine. During the process, an error occurred.
    I got the above error while copying data from infoprovider to planning area using t code TSCUBE.
    How to resolve this?

    Hi,
    Is your issue resolved, If not please run MPOS consistency checks, Planning area consistency check and livecache consistency check.
    Below are the programs for the same.
    /SAPAPO/TS_lcm_cons_check
    /SAPAPO/TS_PSTRU_TOOL
    /SAPAPO/TS_PSTRU_CONS_CHECK
    Regards
    Kishore

  • Copy Data from Non CBF Planning Area to CBF Planning Area in APO DP

    Hi Experts,
    I am working in APO implementation in an automative client, here we have material type Vehi and configurable material.
    I have done my forecasting in Non CBF planning area . Now I want to copy Key figure of final conenses forecast which is in non - CBF planning area to a CBF planning area .
    Can anybody has worked on similar scenario or worked in copying data from a non - CBF planning area to CBF planning area.
    Looking for your valuable inputs
    Thanks and regards
    Kapil

    Hi Kapil!
    We have the same need mentioned by you "Copy Data from Non CBF Planning Area to CBF Planning Areau201C.
    We obtained the source data, but can not do to write the same in CBF area.
    You managed to make the recording of such data in CBF area? How did they do it?
    Thanks and regards.
    Clelidon

  • RE : BI APO Question Reg Data feeding from cube to Planning area.

    Hi BW Experts,
    iam working in an Implementation project for SCM in BW prcisely working with APO Bw..
    For that I have taken historical data as a flat file and loaded it in to the external BW Infocube and its fine...
    Second step I have created generate export datasource on topr of BW infocube and replicated in to Bw and used this export datasource as datasource for APO BW Infocube which is inbulit BW System from External Bw..
    also I have created tranformations and data is loaded in the BW cube in APO system.Also Included Version charecterstics..
    When I try to fed the APO Cube data to planning area Iam gettinga the following  warning itsnot an error:
    1.Key figure copy: InfoCube - planning area (DP) 01.01.2010 to 31.12.2010-- Successful
    *2.No data exists for the selection made (see long text*
      Diagnosis:Data could not be loaded from the Cube for the selection you made. Check whether the Cube actually contains data that is relevant for your selection.
    For the second point I have time charecterstics filled in the infocube which Iam feding to a Planning area like 0CALMONTH,0CALWEEK,FiscVarnt,0CALMONTH
    3.Characteristic assignment: No data copied --- Message
    Can you please help me with your thoughts so that i wll try to corner the issue I will be highly obliged

    Hi,
    As I understood, you have loaded data from external BW cube to APO BW cube and now loading planning area from APO BW cube.
    I hope your settings in /SAPAPO/TSCUBE transaction code would be correct and you have selected the correct planning version with correct cube.
    Check if Data in APO BW cube is available for reporting or not and data is avilable for given selction (if any but I guess you are not giving any).
    Thanks,
    S

  • Loading data from Cube to ODS

    Hi All,
    I have a cube which contains projects data. I want to load the data from cube to a write optimized ODS. In the cube for a project i have multiple records. But while loading the data to ODS, I have to summarise the data in such a way that i should have one record for a project i.e if the cube has data as follows:
    Project Cost
    abc      100
    abc       200
    abc       300
    Then in the ODS the record should be
    Project    Cost
    abc        600
    How do i achieve this ?
    Thanks,
    Satya

    Hi Satya,
    Generate export datasource from Cube ( Right click on cube ->generate export datasource).
    Create update rules for the ODS and in the update rule of Cost , you will find two options
    1. overwrite
    2. addition.
    Choose addition and activate update rules. ..This will work exactly same way you wanted.
    One more thing to mention ,Put project info object in to key fields of ODS and rest all info objects in to data fields.
    Hope that helps.
    Regards
    Mr Kapadia
    Assigning points is the way to say thanks in SDN.
    Message was edited by:
            Mr Kapadia

  • Error while loading data from cube

    while ia m trying to load into the infocube i am unable to load data into the infocube. it is getting an error as raise_exception in the short dump analysis.  how to solve the problem if u know give me clear clarification.

    Hi,
    Can you check what is the difference in the PSA Data in the previous load and the latest load.
    May be by that way you can find what is wrong in any fields if any chance. It may be the case that it would be giving you that error because of some data mismatch in the fields. And in the Short Dump analyse it completely there would be definitely something which will be evident of the error.
    It may also very well be a data base table space issue as well.
    Hope this helps,
    Pradip Parmar

  • Loading data from Info cube to PA

    Hi All,
    I am trying to load the CVC from Infocube to Planning Area in Development environment.
    I am getting error message for mismatch of periodicity of infocube and Planning Area.
    how to resolve this. Where do we define the periodicty of infocube ? I don't think so ?
    Please help me
    Thanks a lot
    Prabhat Sahay

    Prabhat,
    I understand that you already have the data in the infocube and want to load it into the planning area.
    However it is important to ensure that the data in the cube and the planning area have the same periodicity failing which we will run into such issues.
    So pls go back to the step of defining the infocube.
    In RSA1 if you double click on the infocube name which you are using as source, you can see the details in the right. In that, look for the dimensions section, under that look for the time section. If that contains a calweek or a calmonth and you are using a fiscal variant, this issue occurs.
    You have to drop your infocube data, redefine the cube to use FISCAL PERIOD and FISCAL VARNT instead of calweek or calmonth and then load the data back again. You need to ensure you populate the fields FISCAL PERIOD and FISCAL VARNT. You might want to do that with routines in your update rules or your infosource communication structure. REmember to activate the entire structure from cube to data source.
    Once you load the data into the cube with the new setting, and then try to copy the data into planning area, it will be successful.
    To answer your other question. Yes Time Characteristics is necessary for loading data between cube and planning area.
    Hope this helps.
    Thanks
    Mani Suresh

  • How is data loaded from Infocube to Planning area - need technical info

    I would like to find out how data is loaded from cube to planning area ,
    I know that CUBE has tables, but how does that get loaded to planning area , where is the mapping from which I can compare
    data in CUBE and the same data that reaches planning area.
    Say for example I have below values in the infocube
    Prod1 --> Loc1 -
    > available provisioning qty
    AAA        AB90             100
    Then where do i check in the planning area tables ( are there any tables mapped) after running the TSINPUT program, i know it can be checked in the planning book , but i want to check in planning area tables if they exi

    Hi ,
    The data is loaded from infocube to planning area using update rules. The issue you have mentioned seems to be two requests are having data for the same CVCs in the cube.
    Example: For the same CVC, two requests avilable in the infocube. When you copy the data using TSCUBE transaction, whatever data avilable in the cube for the CVC gets copied into Planning Area.
    CVC1 - cube - Old Request - 100
    CVC1 - cube - Actual Request - 200
    CVC1 - Planning Area = 300 ( The value is supposed to be 200, but since the old request also contains data in the cube for the cvc, it gets copied as 300)
    Issue : There might two request contains data for the same code
    Solution : 1. Check the data in the cube using transaction LISTCUBE  2.  Delete old request and check the data agian. 3. If it matches with your requirement, run the TSCUBE again.
    Please let me know if you need additional information.
    Thanks,
    Jeysraj

  • Loading data from APO-BW cube into DP planning area

    Hello,
    Please explain to me how to load data from an infocube within APO into the DP planning area.  So far, I generated the data mart, created the update rules for the DP planning area (cube) and replicated data sources.  The problem that I am having is that when I create the infopackage, there is no data targets on the data target tab.  How can I get the data targets to display?  All the other actions appear to be set up correctly (confirmed by BW experts).  Can data be loaded from an APO-BW cube directly to the DP planning area cube?
    Thanks

    Hi James,
    Loading of data from an InfoCube to a Planning Area is done using transaction /SAPAPO/TSCUBE (program /SAPAPO/RTSINPUT_CUBE). You just specify the InfoCube, target Planning Area, Selection condition, Infocube Key Figure to PA KF mapping, etc).
    Have you tried this transaction already?
    Hope this helps.

  • Load data from infocube to DP planning area

    Hi All,
    I have loaded the data from info cube to DP planning area keyfigures with the transaction /SAPAPO/TSCUBE.
    the data copy was successful and there were no error messages. However, the keyfigure values in planning book are shown exactly as double the values of infocube key figures for all the periods.
    I repeatedly loaded data several times and the behaviour was same.
    We didn't implement any BADI in standrad /SAPAPO/TSCUBE program.
    Could any one please give some hints what would be the reasons for this problem.
    Thanks
    Krish

    I am not sure on how you check the Live Cache data for DP but based on your testing I can say that the old data is not overwritten by the new data in the Live cache. I cannot say the root cause for this however I can suggest you the remedy. To avoid this issue, you zero out the values of the key figure before loading from the Cube.
    For this you have to run a macro which copies zero for the entire horizon and then load the cube. First test this in test system, if it works (it should work), then to make it simple create a batch job with two steps, first step would run this macro and the second step will load the data from cube. you can run this job whenever you want to load the data

  • Automatically trigger the event to load data from Planning cube to Standard Cube

    Hello,
    We have a below set up in our system..
    1. A Planning BEx query using which user makes certain entries and writes back data to the planning cube.
    2. An actual reporting cube which gets data from the planning cube above.
    Now, what we want to do is to automate the data load from Planning cube to Reporting cube.
    This involves 2 things..
    1. Change the setting " Change real time load behaviour " of the planing cube to Planning.
    2. Trigger the DTP which loads data from Planning cube to reporting cube.
    We want to automate the above two steps...
    I have tried few things to achieve the same..
    1. Created an event in SM64,
    2. In the Planning cube "Manage" Screen,  clicked on "Subsequent Processing" and provided the event details. ( Not sure if its the correct place to provide the event detail ).
    3. Wrote a ABAP program which changes the setting of the planning cube (  " Change real time load behaviour " to Loading )
    4. Created a process chain, where we have used the event as a start variant, used the ABAP program as a next step, DTP run as the last step..
    This i hoped, would trigger the event as soon as a new request comes and sits in planning cube, which in turn would trigger the process chain which would load the data from Planning cube to reporting cube..
    This is not working. I dont think the event is triggering, and even if does i am not sure whether it will start the process chain automatically. Any ideas please ?

    hi,
    try to do the transformation directly in the input cube by using CR of type exit, more details :
    http://help.sap.com/saphelp_nw70ehp2/helpdata/en/43/1c3d0f31b70701e10000000a422035/content.htm
    hope it helps.

  • To load data from a cube in SCM(APO) system to a cube in BI system.

    Experts,
         Please let me know whether it is possible to load data from a cube in SCM(APO) system to a cube in BI system.If so explain the steps to perform.
    Thanks,
    Meera

    Hi,
    Think in this way,
    To load the data fro any source we need datasource Ok. You can genare Export data source for Cube in APO,  then use that datasource for BW extraction, try like this. I think it will work, in my case I'm directly loading data from APO to BW using the DataSource sthat are genaraed on Planning Area.
    Why you need to take data from APO cube?. Is there any condition for that?. If it is not mandatory, you can use the dame datasource and load the data to BW, if they have any conditions while loading the data from APO to APO cube, they you try check wherther it is possible in BW or not. If possible then you use DataSource and do the same calculation in BW directly.
    Thanks
    Reddy

Maybe you are looking for