Machine time in activity types

Hi ,
Machine time is used as an activity. How can we see the total machine time booked for the day/ month / year.
Any standard report / transaction.
Regards
ShankarR

Dear,
You will get these details in S_ALR_87013617 or GR55 reports.
Also COOIS use List as Operation or Capacity and change the layout accordingly. OR From the T code co28 choose OP/sub Operation.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Jan 14, 2011 2:14 PM

Similar Messages

  • Activity type in time sheet

    Hi all,
    In PS we donu2019t capture any cost. In such case, While entering timesheet, the system through an error message, to enter sender Activity type and it is not allowing to enter timesheet.
    Now, what should be done to skip entering activity type and enter timesheet without entering activity type?
    I guess it is controlled through work center, by not maintaining costing tab, but the system does not allow to save the work center without entering the cost center under costing tab.
    Please suggest, in entering time sheet without activity type
    Thanks,
    Chandru

    Hi,
    Go to --> SPRO --> Cross Application Components --> Time Sheet --> Settings for all User Interfaces --> Time Recording --> Choose Fields -->Data Entry section --> Activity types
    Double click and in reference to data entry profiles we can restrict the entry for the activity type whether it is required / Display / Hide / Input.
    Check and confirm whether the problem is solved
    Regards,
    Selva

  • Error In IR at the time of activating data types

    I am getting an error at teh time of activating the data type
    Namespace urn:rfctoftpserver:am is not defined in the software component version SAP_ECC_DABUR_POS , 9.5 of sap.com.
    How ever I have saved the name space in Display Software component version!!
    Pls help!

    Hello,
    This problem basically happen due to the following reasons:
    1) when you try to copy the datatype from one Object to other and the namespace is not activated in course of it.
    2) If you have deleted the datatype but it still remains in the Objects list
    Resolution:
    1) Try to change the datatype name and activate
    2) if it still doesn't work have a look at the Software component relation with the datatype namespace relation

  • In CATS,  where can I assign "Activity type to default Time sheet",

    Hi gurus,
    In CATS,  where can I assignt Activity type to Default time sheet.  Please help me asap.
    If any cats doc.  available plz share with me.
    Thanks in advance,
    Sadana.

    If you have defined activity types then you can define them with the right price in KP27 for each costcenter.
    the costcenter is connected with the personelnumber.. in infotype 315 you can define which is the default activitytype for each person.
    if you have only 1 activitytype you can also programm the user exit to fill it in by default
    see EXIT_SAPLCATS_002 to implement a fixed activitytype for whole cats
    kind regards
    arthur de smidt

  • Activity types in time confirmation (IW41)

    Hi,
    I create an activity type and assign it to cost center with price using transaction KP26. This activity type is being included in the work center. When I create a time confirmation for the specific work center which has been used in a work order I have in the selection list of activity types in IW41 several options of activity types. How can I restrict to use only the ones I require?
    What is the logic behind the selection of activity types in the time confirmation transaction?
    Thanks
    Ed

    Dear,
    It is not possible to change the activity type this with Enhancement  CONFPM04 PM/SM order conf.: Customer specific input
    or CONFPM01 fields are AFRUD-LEARR (activity type) and AFRUD-LOARR (wage type)
    Regards,
    R.Brahmankar

  • Activity types - resource related billing

    Hi,
    I am not much aware of Controlling areas. I would like to know how the rates are determined for the number of hours entered in the time sheets for time writing.iIcame to know that it's done using activity types. Could anyone explain me what are activity types and in which transaction we maintain the rates.
    Thanks and regards
    Aparna

    Hi Aparna,
    Activity types are those which we plan for Production Process. For example for manufacturing the product we need labour hours, machine hours, Setup hours etc this r the activities which we plan while running the production process.
    We plan this activities in t-code KP26, By taking cost center and actvity types.
    Regards,
    Sreekanth

  • Confirmation of activity type in Process order -Impact in FI.

    Dear All,
    On doing a confirmation of a activity type for a process/ Production order - values get posted to secondary cost element which has been assigned to a acitivity type.  This means only a impact in controlling but not in FI
    How woould the booking happens in FI ?is it not required to book in FI, if yes, why.
    Please suggest.
    Thanks.

    Hi Daya
    1. You can calculate activity price for plan in KSPI and for actual KSII for respective CCtr and activity type...but some times people manually update price at KP26 directly which in my opinion is not right way because price is either more or less than the real calculation in KSPI and KSII...
    2. However in your case price is directly updated in KP26 against activity type..when confirmation is done in order this rate * activity qty is your value posted in order level and at the same time respective CCtr is also credited by this amount which you can see in CCtr report
       Example:  CCtr  XXXX01
                       Activity type 999999
                       Sec cost Element for activity type 999999 (43 cat)
        Suppose you have booked FI entries for some expenses like Salary in F-02/FB50...against CCtr XXXX01   So your CCtr XXXX01 is debited by Salary amount and this amount will be absorbed in product through activity for which you need  activity price and confirmation.
        FI entry is booked your expense in GL a/c Salary and same time debited your CCtr through CE salary....Now when you charging this expense in product through prod order you are doing it through confirmation of activity qty which in turn calculating value by taking price from KP26 and qty from confirmation.
    Kamal

  • How to get internal order and activity type other than from BSEG

    We want the Internal order and activity type fields. From BSEG, it is taking a long time, and it hangs.
    Is there any other table we can get these values from?
    Our query is this:
    select bukrs "Company code
    gjahr "Fiscal year
    belnr "Document no.
    buzei "Document Item no.
    aufnr "Internal order
    lstar "Activity type
    from bseg
    into table gt_add_info
    for all entries in gt_gl_detail
    where bukrs = gt_gl_detail-rbukrs"Comcode from G/L acct detail
    and buzei = gt_gl_detail-buzei "Doc item no. from G/L acct detail
    and belnr = gt_gl_detail-belnr "Doc no. G/L acct detail
    and gjahr = gt_gl_detail-gjahr."Fiscal yea
    Can advise please how to make it faster. My internal table (GT_GL_DETAIL) has over 100000 records. ? thanks.

    I did a SQL trace, and saw that tables CSLA, CSSL, COKL and COKA are being hit with the values I entered inthe Activity type in transaction FB50.
    Still not clear but where it gets stored. If in any of these tables, how do I get the object key?

  • IW41: automatic update of activity type when changing the work center?

    Hello colleagues,
    when doing a time confirmation with IW41, we have following problem:
    In the PM order the operations are assigned to a neutral executing work center, as it not known which individual technician is completing the operation later on.
    Now when the individual technician is entering the time confirmation with IW41, system is proposing the work center indicated in the operation from the PM order, then technician is overwriting the work center proposal with his own individual work center ID (and pressing Enter), but the activity type is not getting updated automatically. So the technician must jump to field "activity type" and choose the correct activity type.
    Is there any solution (hopefully with user exits!) to have the field "activity type" automatically updated with the one indicated in the work center, which was entered manually?
    Thanks for your ideas!
    Regards,
    Patrick

    Hi Maheswaran,
    yes, as usual all PM work centers have only 1 activity type assigned in the costing tab.
    We also checked the settings of the activity type (KL03), but we just found one difference: the price indicator was set on 3 "Determined manually" - we've changed to 1 "Plan price, automatically based on activity" (..same setting as for the act. type of the work center with working update of act.type).
    We tested already all possible constellations and scenarios, but we have not found any good reason for the behaviour.
    Thanks for your efforts so far!
    Patrick

  • How to set activity type for a cost center

    i was practicing the split valuation topic and for the that i was making a routing for a product so that i can have that product for inhouse production.
    while using ca01(to create routing), i am facing a problem with the activity type.
    when i am setting up the operation i am getting an error " activity type # is not set up for cost center 10004220 in year 2007"
    can you please tell me how should i come out of it.
    thankyou very much

    hi Nandha, i am sorry but i could not do it. i am new in this. let me make my problem more clear to you.
    i was creating a routing using ca01
    after puttig all the details i switched to operations tab and in operation tab i put workcenter as (1111 - lathe, may be i am wrong as i told you i am just practicing).
    i did not put anything on that screen and then when i pressed enter it took me to another screen with name Operation check.
    here is the layout of the problem on that screen
                          std val      unit     activity type     efficiency
    set up                            min        1422
    machine                         min        1421
    labor                              min        1420
    and then curser being on the std value i am getting this error "activity type 1422 is not set up for cost center 1000 4220 in the year 2007.when i am ignoring it it is switching to next std val coloumn and the same error.
    thankyou for your time

  • Error Activity type 502000 not set up for cost center 1000 cc111

    hi all
    While creating a work center (CR01) I need to enter a cost center and activity type for machine hours. However, while entering the activity type the following message appears:
    Message no. CR 061
    You are attempting to assign activity type XXXX to the work center. However, this activity type has not yet been set up in controlling area 1000 for cost center xxxxx.
    while creating the activity type in KL01 i have already given * in cc category so it should go for all cc
    What could cause this problem?
    Thank you in advance,
    Kind regards

    Hi,
    Check whether the activity type is maintained at the correct controlling area via KL03. If not, then create the activity type (KL01) in the corresponding controlling area.
    Regards,
    Darrel

  • Actual activity price does not exist for cost center / activity type

    Hi,
    We are trying to upload the time sheet related data(number of hours an employee workred on a project) ect from Non SAP to SAP.
    We have used a customized program and have loaded the data from se38.
    All this HR data will be saved in CAT2
    Later we transfer the time related data into SAP FI/CO using CAT7.
    +When  tested  with a couple of employees time sheets, they got uploaded in SE38 proerly and when transfered it through CAT7 it was properly taking the hour*rate is cost and was reflecting in the respective cost element.
    For a few time sheets in SE38 we were getting an error saying that the cost center(100501)/ activity type(EAT001) does not exist for 2010.
    Hence we have taken, FY 2010, the cost centes and activity types in KP26 and have given the planned Activity as 1. No planned cost in KP06.
    We have run the price calculation forr the FY 2010.
    Then we were able to uplaod the time sheets, but when we tried to transfer the data through CAT7, it throws an error saying no activity price exist for cost center 100501/ activity type EAT001. If I ignore the warning an proceed, no amount is being calculated.
    When uploaded employee time sheets before, all the cost were getting claculated and were entering into  the respective cost elements, but now no amounts are being calculated and it is taking Zero.
    When checked the previous years data i.e, 2009 all amounts are fine, in KSII I can see the activity quantity filled with some numbers in 2009, where from are they comming? I have checked KBk6 nothing was mentioned.
    PLease assit
    Regards,
    shilpa

    Hi
    I never used CAT* though, but the error means that you need to maintain a activity price in KBK6 (Actual price)
    Regards
    Ajay M

  • Error saying "Enter the sender activity type also"

    While trying to upload the HR details from NON SAP to SAP through SE38, an error reflects asking to enter the sender activity type.
    Can any body help me.

    Hi,
    Please refer to the online documentation help whose link is listed below :
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/c3/c6c2a40f4f11d2956400a0c930669b/content.htm
    This link mentions four different data entry scenarios that can be configured for data entry profile in CATS.
    if you want to have the activity transfered to HR, you have to activate this Controlling object for pers. cost assignment in your
    customizing:
    - Personnel Time Management
      - Time Data Recording and Administration
        - Integrating Time Management with Other R/3 Applications
          - Recording Personnel Costs
            - Enter Controlling objs permitted for pers. cost assignment
    here you can find in the documentation:
    'In this step, you specify which Cost Allocation or Funds Management  objects the personnel costs can be assigned to.
      and, in addition, for account assignment to activity type:
      COBL-LSTAR Activity type
       In cac1 'cost accounting variant' is set to 'Assignment of personnel costs to master cost center'. In this case, the cost center is not transferred to HR. Activity allocation is done directly from cats through the other (non-hr) components. Check for 'activity allocation' in the online documentation.
    the cost assignment variant 'B' (Assignment of personal costs to sender) needs a receiving accounting object.
    If there is no receiving object the cost assignment variant changes to '0'.
    regards
    Waman

  • Valuation price with user Exit on activity types

    Hi All,
    Our customer could have different activity cost for different products even if they are processed on the same cost center, same activity type and same activity time. So I wonder whether SAP has valuation price with user Exit on activity types as what on material valuation, when we select "U" in the relevant valuation variant. Could anyone knows advise please?
    Regards
    Walter

    Hi Walter,
    an idea might be to include an ABC template into the costing. ABC tempaltes allow a big degree of freedom in determinin which processes to use and in which quantities. To use the product as a cost driver is certainly not an issue. I doubt that you can directly influence the process 'price' to be applied, but to change the quantity could bring the same result.
    See the docu for more info:
    [http://help.sap.com/saphelp_erp60_sp/helpdata/en/7e/cb7d1443a311d189ee0000e81ddfac/frameset.htm]
    best regards,
                        Udo

  • CATS INTEGRATION WITH PP AND PM MODULE ( TO FIND ACTUAL MANPOWER COSTING THROUGH ACTIVITY TYPE)

    Hi Experts,
    We have a scenario like, Client wants to track the actual manpower costing through activity type ( Ex: How much hours an employee worked on a particular work center to produce an “X” product, So that his actual cost should be loaded on that product.
    We have employee ( 1. Staff 2. Worker 3. Contract labor employee and apprentice from third party roll and staff and worker we plan to go with negative time management and for contract labor and apprentice will go with through cats.
    Since we are not going to run the payroll for contract labor employee and apprentice, we just maintaining the employee data as a group ( Ex: Group A,B,C etc.. Each group consists 20 or 30 employees, According to system each group as one employee and according to us each group consists as 20 or 30 employee.
    The Activity type as well cost center will be created by Co module, the same will be assigned in info type 0315, but still i want more input from experts on the same, since i am new to cross application time sheet configuration, could any one help me out to find the actual manpower costing in a better way.
    Regards,
    Prem

    Hi Experts,
    Can any one please reply on the same.
    How to arrive the exact manpower costing through activity type ?..
    Regards,
    Prem