I created Company code and gave year and posting period as 2008 and 4 but it shoild be 2008 and 2 as according to IN01 Company code(Indian standard prodecure)
         Now i am going to change to 2008 and 2 in omsy tcode but system is not allowing Please suggest me how to change to 2008 and 2.

You Cannot Roll Back the MM Period..
But, You have another option which is not advisible.
1. Go to SPRO>Enterprise Structure>Assignments-->
Logistics General -->Assign Plants to Company code.
Here, Delete all the plants of your company code and save.
2. go to OMSY, and enter the period as you want.
3. Again Reassign the plants to your company code as in step 1.
This causes serious effects in FI side of your company code.
i.e., G/L accounts will be affected.
Edited by: Anand K on May 1, 2008 12:06 PM

Similar Messages

  • Materials Management view on company code

    Hello MM Gurus,
            My requirement is as follows.
            When we go to next month (May 2007), the system should allow me to post
    for the months of March 2007(12 th period of 2006), April 2007 (I st period of 2007) and May 2007(II nd period of 2007). Is it possible? How to achieve this?
    Thanks & Regards
    Yoga

    Hi Yoga
    As i told earlier it is not possible as far as MM period is concern having 3 periods open at a single point. so if u r in May you can not post for march, only posting is allowed in april month.
    Jagadeesh: yoga is asking related to MM period, we know that In FI it is possible but not in MM.
    regards
    Yogesh

  • Excise duty: error 9914 No material data maintained for company code

    Dear all,
    when executing transaction /BEV2/EDDS I get error 9914 No material data maintained for company code in some material documents.
    However, I see material is correct.
    Can you tell me which views of material master am I missing?
    What do I need to check?
    Thanks in advance,
    F

    Settings in material master "Basic view 1"

  • Material Managent view

    Hi,
    Regarding to the first question on material management view  I would like to clarify further that while creating a material using Material master I could able to see only MRP 1 and MRP 2  view but not the MRP 3 & MRP 4 view .How can i see all four MRP views while creating,modifying as well as viewing the material master ?
    Thanks & regards
    Rabi

    Hi Rabikumar,
    You need to maintain following setting in OMT3E
    SRef: trans    *
    SRef: user     *
    SRef: matl type    *
    SRef industry       *
    SSeq                 21
    Screen Sequence description     Std ind.(short) tab pages
    Hope this solve your problem.
    Regards,
    Raja.
    Edited by: Raja on May 20, 2009 1:01 PM

  • Same material master in two company codes with batch management

    Hi,
    There are two company codes in one client. In one batch management is already active. But in another company code batch management is not required. Is it possible to have batch management active in one company code and inactive in another company code where both the co. codes are in the same client? The same material master to be used in both company codes.
    Thanks,
    Satya.

    Hi Satyabarata,
    As far as you dont want to move the same materiel i.eStock Transfer with Inter comapy billing scenario then it  will be fine.
    If you try to Transfer a Batch manged material into a non batch manged CC it will work fine. But on the other hand when do via-versa the system will ask for the Batch information where the Batch management is active.
    If you want to use same Material Master for both CC then its not advisable.
    Please let me know if you need any other information.
    Thx.
    MJ

  • Material Ledger activation at Company Code Level

    Hi All,
    I have a requirement where Material Ledger need to be activated at Company level and not at single Plant Level. We are about to implement ML and would like to have periodic unit price calculated at company code level  (e.g. 1 material, 4 plants, 1 company = 1 periodic unit price).
    I went through the customization , it only refers to Plant level (Valuation area level)
    Could anybody throw light on this.
    Regards
    Barbara

    Hi,
    What is the valuation level?
    If the valuation is at plant level you can maintain different views at different plants of these company codes.
    If only name is different i think you would do better with the same material code, and if you still want to differentiate please create two different materials
    Regards,
    Prithviraj
    Edited by: Prithviraj Talekar on Feb 11, 2009 5:25 AM

  • MIRO - deactivate direct posting to GL / material acct for selected company codes

    Hi All,
    I have a requirement to deactive direct posting to G/L and material accounts in MIRO, however, only for selected company codes (this cannot be done for all of them on client level in SPRO->Material Management->Logistic Invoice verification->Incoming Invoice -> Activate direct posting to GL/ Material accounts).
    The thing is that for those company codes, MIRO posting has to be made always with Purchase Order Reference.
    My idea is to build simple validation rule:
    if company code is equal to (SET) and Purchase Order Reference is empty then error message should appear: "Posting without PO reference not allowed"
    I was also thinking on creating own layout in MIRO and assign it to clerks which are responsible for posting in those company codes.
    Can you advise on that, please?
    Best regards,
    Lukasz

    Hi Tejas,
    Thanks for your reply.
    Answering your questions:
    1. The thing is that these GLs are being posted with other transactions.
    2. My concern is that after the document is parked and while editing user will delete PO reference, it can be any GL account picked in "GL tab" of MIRO transaction. My understanding is that I should put tick on "Post automatically only" on all the GL accounts which users are able to use (correctly or not) in that case.
    My aim in this configuration is to restrict those posting in such way that users are not allowed to use them - and this is only in regards to MIRO transaction.

  • Add material tax classification to company code

    Hi gurus,
    hope you can help me with this one.
    i need to add/extend the material tax classification to a company code... how would i do that.
    appreciate your help.
    thanks in advance

    Hello Brett,
    I am facing the same issue. Can I know how to change the country defaulted to the country where I can to create?
    Thank You.

  • Collection Management - Distrubution per company code

    Hi All,
    In Collection management configuration,i trying active distrubution per company code, i able see only one radio button(Direct Payers). If i see anothere sap system there is around four radio buttons(all items for HO,item from direct payerfor HO,all item for Branch and alternative payer).
    Please can anybody tell me, what is configauration for display this radio button in my sap system.
    Thanks & regards
    Ravi

    Ravi - When you say "other SAP systems" are these two systems owned by the same client?  The ability to produce Collection Worklist at either branch or head office comes as part of Enhancement Pack 4 for FSCM.  Is it possible the two systems you are looking at have different EHP levels or that the Business Functions from EHP4 are activated in one system and not the other?
    CK

  • To view the company code wise cost and profit centers

    hi all,
    how to know the company code wise cost centers and profit centers? and what is the transactin codes for this?
    Regards,
    Soma

    Hi Soma,
    Could you try Table-->CSKS. I believe it will give you the complete list of Cost Centers and the default Profit Centers along with Company Code info.
    Regards
    Srinivas

  • User exit for different Material Document for different company code

    Hi,
    We want to have different no. range for Material document (GR) for different compnay code. Presently we have no. range at client level. Can we do with any userexit. If so pls. give the details.
    Regards
    Sai Krishna

    [user exit for generating external serial;
    [BADI MB_DOCUMENT_BADI;
    [user exit or any other enhancements during good receipt;

  • Posting periods in material management

    hi mm gurus,
    i m fico guy, i need some help form ur side. the t.c. MMPV is closing the posting periods in MM is it right, then what is OMSY?  as per as my knowledge in MM we have a chance to open only 2 periods,  in OMSY the periods belogs open periods? or closed Perids?
    my question in OMSY the periods belongs open or closed?
    can u explain please.
    thanqu

    The T code OMSY is for Activating Material Management against a Company code.
    Maintain the Material Master company code in OMSY.
    This is done when you want :
    1.  To create a material master record, the control record must exist for the company code for which you want to create your master record.
    2.  To set up a company code, enter the current period here. 
    3.  When changing the Allow backposting or Disallow backposting indicators 
    You can also use MMRV to set the Allow/Disallowed backposting indicators.
    The current and previous period is shown on both transaction codes.
    As MMPV is only Used for Opening  / Closing MM Periods.
    There are a number of activities that are managed by period in the materials ledger including:  certain stock totals valuations, price units, goods movements, etc.
    MMPV executes program RMMMPERI to close the current period and open the new one. 
    Please Go thru the Link :
    http://www.sapcustomization.com/help/scr/OMSY-Maintaining%20Company%20Code%20for%20Materials%20Management.htm
    Regards,
    Ashok

  • Material Master : company code - BMMH1 structure ?

    Hi,
    it's possible that this question will be a bit stupid, in this case, I apologize. When I create material master using MM01, SAp never ask me for company code.
    It ask me for : material type, plant, storage location, sales organization, distribution chanel and so on depending on the view I'm creating.
    So, BUKRS doesn't exist in MARA, MARC,MARD, MLAN ...
    So, why is there a "Company Code " in the BMMH1 structure used in material master lsmw ?
    Where in material master is the company code used and if used, why SAP never ask me for ?
    As I said, it may seem stupid ...
    thanks for help,
    Regards

    Dear,
    As per my view,
    System not ask you company code at the time of material createion.
    System ask only plant, material type, storage location etc.
    But plant is map with company code so material is directly map with material code.
    Because in SPRO we assign plant to company code.
    Regards,
    Mahesh Wagh

  • Add freight cost in a cross company code scenario using a costing sheet

    Dear Forum,
    I will like to add freight cost to a material using a costing sheet. The freight percentage is very easy to add and works fine when the cost is added in the company code costing. My problems start when I want to add the freight in the cross-company code costing. I want to setup a cross-company code costing where the freight cost is added to the material in the buying company code and not on the selling company code. The cross-company code costing is setup using special procurement costing keys. 
    In below costing (CK11N) the procurement costing key is not used.
    From the itemization it is shown that purchase info.record 5300067643 is read and the price of 12,97 is determined. There is added 10% in freight coming from the costing sheet.
    The freight is shown in the cost component structure as well.
    The special procurement type is now changed from ‘20’ to ‘AT´ on the MRP2 screen in the material master. The procurement is now pointing to an internal plant called ‘DCN’.
    The costing of material 105050 is now repeated. I get the expected result from changing the procurement key, as I can now see the material is sourced from plant ‘DCN’. DCN is sourcing the material from BJ07, but that is not relevant for the example.
    If I now look at the itemization again on the costing in BGA1 I now see that the price is not coming from the info.record. It is the costing in DCN that is used.
    I will still like to add the freight cost in BGA1.
    How do I add freight cost in BGA1 when I at the same time want to have the costing to be taken from plant DCN?
    Please let me know if you need additional information on the customizing setup of the system.
    Best regards,
    Kim Hjorth Poulsen

    Hi Srinu,
    Thank You for a prompt feedback.
    I have tried to follow Your advise. The special procurement costing key is customized like below.
    I have updated the special procurement costing key on the costing 1 view of the material master. When costing the material it is using the special procurement key. This can be seen from the qty. structure tab in CK11N.
    It is also costing cross company as intended.
    The itemization looks like below.
    and the cost component structure looks like below.
    Unfortunately the freight is not added in the costing in BGA1.
    I noticed that when the costing is made without special procurement key the costing sheet used in the costing is for material components. If the costing is made with the special procurement keys the costing sheet used is for finished and semi-finished materials. The customizing in both of the costing sheets are the same, but only when costing is without the special procurement keys the freight is added.
    So unfornutely Your suggestion did not solve the problem.
    Best regards,
    Kim

  • Parallel currency valuation for material management

    Dear all,
    My comapny is maintaining parallel currency in company code in new GL, does this impact material management also.
    Should we need to activate material ledger for parallel valuation in material management, but the company is not actually into production but it still require activation of material ledger.
    Regards,

    Hi Shilpa,
    How I understand it using the U.S as my example:
    In the first transaction code, in other words, F.05 or FAGL_FC_VAL  are used if the currency in the transaction is not the same as the local currency of the company.  For instance, U.S GAAP mandates companies to report their financial statements in local or functional currency.  So let's say the transaction currency for a U.S company code is/was GBP.  However, GBP is not the local currency of the U.S company code so you would to have perform foreign currency valuation with any of the above named transaction codes using the exchange rate of the key date specified at the time of the valuation.  This valuation will then give you a gain or loss as a result of differences between the original amount and the revaluated amount.
    The second transaction code FAGL_FC_TRANS valuates the balances or additional currencies.  But to be able to run this second transaction code, you would first have to perform FAGL_FC_VAL or F.05 first (this is a prerequisite). 
    So even if you are to perform currency translation, you will still need to run FAGL_FC_VAL first.
    Regards,
    Elias

Maybe you are looking for

  • How can I call BW Report into SAP R/3

    Dear Friends, Is there any way to call a BW Report in SAP R/3. The BW Report is Customer Equipment Revenue . Please Suggest me . Thanks Regards, Ashok

  • Oracle Customer Service Incident Location Information.

    Hi, I have a question regarding the base table CS_INCIDENTS_ALL_B, the column INCIDENT_LOCATION_ID can hold two kinds of values HZ_LOCATION_ID or HZ_PARTY_SITE_ID. The column INCIDENT_LOCATION_TYPE contains the info whether the stored values is HZ_LO

  • Wireless Backup Disk

    I was wondering if you could do wireless backups with not only Apple routers, but other ones too.

  • Is it possible to record a live video feed online ?  PLEASE ... ASAP !!

    There is a Live video feed today marking Carroll Shelby's wake.  I will be away from computer but would VERY MUCH like to view it at a later time.  How can I do this ?  I have a MacBook, and a MacMini, both of which are running latest OS. Thank you !

  • Xml duration to milliseconds

    Hi I'm in a J2ME-project (i have no javax.xml.datatype.duration there) and i need now to convert a ISO 8601 duration-datatype to milliseconds. Before i begin "to invent the wheel for a second time" i ask you, if there are already some known methods o