Material Procurement from many vendors

Hi friends,
I am working in a process industry where raw material is supplied from nearly two thousand vendors.I put all vendors in a source list. I want to create purchase requisitions at a time for all vendors for same material. How can I create it?
Please guide me.

Hi,
For this you need to follow the "Quota Arrangement" Process.
Go to MM02 - In "Purchasing" view, enter "Quota arr. usage" as '4" and save.
Also maintain MRP views of the material master.
Now go to OMI4 - here for MRP Lot Size (For e.g. EX), activate "Splitting Quota" for Short-term as well as Long-term planning both and save.
Now go to MEQ1 - here for material master and plant and press enter, here maintain valid to date and pres enter and double click on this
Here enter Procurement as "F" (External Procurement), also enter all the vendors and enter Quota as "1" for all the vendors.
Prerequisite for Quota Arrangement is Purchase Info Record and Source List must exist for the material.
Now maintain Planned independent requirement for material in MD61 and then run MRP for the material in MD02 and check system will generate the PRs for the material for all the vendors maintained in MEQ1.

Similar Messages

  • Impor material procuring from local vendor with all import conditions

    Dear Experts,
    Our client requirementis that, we are getting import materials from local vendor.
    The vendor ischarging all the import charges like cutoms duty and etc., apart from that,
    He is charging 4% additional TAX on total amount .
    After that vendor is charging 2% CST on total amount
    Please help me out to do this configuration in SAP.
    Regards,
    Sathya
    Edited by: RRB Energy on Feb 2, 2011 9:41 AM

    Hi,
    This is a standard scenrio.Where the local trader will be supplying the imported material.SAP has provided a standard notes for this.Pl check in the forum.You have to use sub transaction type for this 4%

  • In subcontracting procure from second vendor

    Hello,
    If i wanna procure from second vendor and wanna get delivered material to the subcontractor directly.
    Then what is process to follow??
    Thanks & Regards
    P.S.P

    See this help link:
    [Subcontracting/Third-Party Order Processing|http://help.sap.com/erp2005_ehp_04/helpdata/EN/55/eb4c27e00b11d1a6aa0000e83235d4/frameset.htm]
    The GR of a 101 will place the stocks at the vendor's location (seen in ME2O - SC Stocks per Vendor).  This should take the place of the 541.
    Regards

  • Pricing Procedure for Imported Material purchased from local vendor

    Dear SAP Experts,
    I have a scenario, where the Imported material is purchased from a local vendor.
    The local vendor passes on all the customs duty, CVD and all the related duties to the customer (us).
    All the duties including CVD in the form of Excise duty etc. have to be inventorized.
    How to map this in SAP?
    Thanks In Advance.
    Regards,
    Muthuraman.K

    HI,
    I have given the pricing procedure for TAXINN
    100     0     BASB     Base Amount                                         362
    110     0          Calculated Call     100       
    120     0          Sub total               
    250     0     JSRT     Service tax set off     100                                      VS7
    251     0     JEC3     A/P Ecs for Serv tax     250                                      VS8
    253     0     JES3     A/P SE cess serv tax     250                                      VSE
    258     0          Total Sevice Tax     250     253
    260     0     JSVD     IN:Service tax debit     250                                      ESE
    560     0     JMOP     IN: BED setoff %     120             X                         VS1
    561     0     JMOQ     IN: BED setoff Qty     120                                      JI2
    564     0     JSOP     IN: SED setoff %     120                                      VS1
    565     0     JSOQ     IN: SED setoff Qty     120                                      JI2
    570     0     JMIP     IN: BED inventory %     120             X
    571     0     JMIQ     IN: BED inventory Qt     120                                      NVV
    574     0     JSIP     IN SED inventory %     120                                      NVV
    575     0     JSIQ     IN SED inventory Qty     120
    578     0     JMX1     IN: A/P BED setoff     560     561
    580     0     JSX1     IN: A/P SED setoff     564     565
    581     0     JMX2     IN: A/P BED inventor     570     571
    583     0     JSX2     IN: A/P SED inventor     574     575
    584     0          Total excise duty setoff     578     580
    585     0          Total excise duty Inventory     581     583
    586     0          Total Excise Duty W/O ECess     584     585
    587     0     JECP     A/P Ecess set off %     584                                      VS2
    588     0     JECI     ECS inventory %     585                                      NVV
    589     0     JSEP     IN:A/P SEcess setoff     584                                      JI6
    590     0     JSEI     IN:A/P SEcess inv     585       
    591     0          Price     120     120
    600     0     JAOQ     IN: AED setoff Qty     120                                      VS2
    601     0     JAOP     IN: AED setoff %     120                                      VS2
    605     0     JAIQ     IN AED inventory Qty     120                                      NVV
    606     0     JAIP     IN AED inventory %     120                                      NVV
    U have to setup ur taxprocedure like this.In this the acct key is the main.IN OBCN ucreate the acct key & give them as non cenvatable.Then assign this acct key against the condition type in the TAXIIN.
    Then in FV11 create the condition records for the cond type.For the cond type the access sequence should be JTAX

  • Procurement from one vendor

    Hi expert,
    is there any chance of procuring material form one vendor while using particular document type.because that material can use in other document type also.
    But in me01 we can fix that vendor r leave blank.
    my client required when he use that material for particular document type in ME57 it need to assign to that vendor
    pls advice
    regards
    arun

    solved

  • Return Material back from Vendor without PO

    We are having problems returning material back from a Vendor without a PO. We had sent some of our product to a Vendor to have them restack the pallets. Now we cannot bring the material back in without referecning the PO. (RGA) (VA01). We are allowed to do this on the sales side of our business when we are dealing with customers but not with a regular Vendor. Is there some flag on the Vendor that I need to check? Please let me k now.

    Hi
    You could do a goods receipt with movement type 501 whish is Goods receipt without a Purchase Order but be careful has this has the effect of making stock appear from nowhere.
    This can be done with transaction MB1C
    I hope that this helps

  • MRP consider other plant inventory before procuring from vendor

    Hello All,
         Is it possible to have standard R/3 (5.0) consider inventory of other plants before creating a schedule line to procure from a vendor?
    Example:  We have inventory in two plants. 
    <b>In plant 1000</b>,
    requirements of 500 pieces
    inventory of 100 pieces
    <b>In plant 2000</b>,
    requirements of 50
    inventory of 200 pieces
    In plant 1000, I would like the MRP result to create a stock transfer requirement of 150 from plant 2000 and then a schedule line from a vendor of 250 pieces.
    Is this possible?  If so any suggestions on how to setup my plants/materials?
    Thank you,
    Jerry

    Hi,
    If Plant 1000 regularly receives supplies from Plant 2000 apart from the Vendor, I think it would better if you can maintain Special Procurement Type (Ref SPT 40) for transfer from 2000 to 1000. Then maintain Quota between Plant and Vendor (MEQ1).
    However if your scenario is such that stock transfer reqmt should get generated only if when there is surplus inventory at Plant 2000, I am not sure if this can be achieved in Std R/3.
    Raj

  • Q. M PROCUREMENT-PAYMENT TO VENDOR  BASED ON INPSPECTION RESULTS

    Hi GURUS,
    My Client requirement is that payment for material procured from vendor should be based on quality of material.
    For example: My client procure Ferro Alloy from a vendor,quality specs for this material is  60%.if after inspection quality of material is e.g 58%.then according to this diiference in quality the vendor should be paid less.After we do RR and UD.based on the quality of product the Accounts Department should automatically know that there was change in the required quality and the vendor should be paid less.Is it possible to calculate the value to paid to the vendor by the system automatically by maintaining certain formulas.
    Thanks and Regards
    Ramkumar

    Hi Ramkumar,
                            You can generate a Z Report with the help of your ABAPers and there you can define the formula what you are asking to calculate on the basis of Quality. The logic of formula may be like if Purity is 60% then it will be 100% money & if it is less then the formula will calculate the value accordingly on the basis of Quantity & purity results.
    Please revert me the findings after consulting to your ABAP Team.
    Regards.
    Edited by: ATUL MITTAL on Oct 20, 2008 7:54 AM
    Further this report will be run by your account personnel and they will know the price deductions on the basis of Quality along with all other related informations.
    Thanks

  • Report on inventory purchased for a period from a vendor

    I am looking for a report which shows the inventory of a raw material purchased from a vendor for a particular period. Is there any standard report ?

    Hi!
    Case 01: If you are interested in just knowing the qty of Material received from a Particular Vendor, you can use MB51 by defining the Vendor and Movement Type (101,102).
    Case 02: If you are interested in the existing Stock in the Stor.Loc / Plant segregated by Vendor, probably you need to have Batch Management activated - with Vendor as the criteria for batch. This will allow to you to see Stock per Vendor in any Standard report like MB52. In this case the System will require you to enter the batch (Vendor in this case), every time you do a GR, GI or Transfer Transaction.
    Hope this helps.
    Regards,
    Riju.

  • Inspection Lot control GR from external Vendor and Vendor Consignment

    Hi Everybody,
    We have a material which is received in the plant from external vendor as well as from vendor consignments. The requirement is that when the material comes from external vendor and Inspectin Lots should be created and when it comes from vendor consignment(PO is created with item category K and GR will be done with mvt type 101 K) a lot should not be created.
    Can we achieve this ? if yes, please tell me how ?
    Regards,
    Manish.

    Hi,
    Deactivate Quality Inspection for 101 K in SPRO.
    Quality Inspection-----> Inspection for Goods Movement
    Regards
    Nitin

  • Project material Procurement

    Hi,
    Ours is a construction company.
    We have different sites were actual activies are taking place.
    since Sites keep varying once project is completed, we can not create plants site wise in SAP.
    so all requirements comes from Projcet systems Module against which we procure material ( procurment against WBS)
    sometimes we ask vendors to directly send materials to Sites or we may ask him to send material first to our central Store and then we transfer it to project sites as per requirement.
    1) when we have to receive material at our store , we use plant AB01 in PO which is our physical plant  and we receive material against Project WBS.
    2) When vendor has to supply directly to site, we use plant  AA01 in PO ( this is a virtual Plant not mapped to any project location) .we receive material in this plant and then issue to project from this plant.
    This allows us to segregate us whether material is lying in our store or at project site. ( is material is shown in AB01 against WBS, then it is in our store and if shown in plant AA01 then its actual project site).
    but this is causing us duplication of activities since if we have to trandsfer material from store to project site then we have to do plant to plant transfer first(AB01--> AA01) and then issue to  actual project from AA01.
    Is there any way we can remove this virtual plant and we can still have visibility of stock at project sites.
    Thanks
    Manoj

    If you manage stock for WBS, you always receive it in a storage location.
    Is it possible that when you receive it the projects plant WBS it is not manged in stock, but rather consumed immediately? If so, the you can get rid of the projects plant, and instead use only your "real" plant, with "real' storage location.
    Then have another permanent storage location for all projects (instead of the virtual plant), and use it in combination with WBS stock to have visibility on which site the stock is. Only limitation is that you have only one site related to one WBS.

  • Payment from one vendor to another vendor against PO

    Hi experts,
    Hi experts,
    I have a scenario,
    1. Vendor-A   ( material supplier)
    2. Vendor -B    (Term loan vendor )
    Raised Purchase order for procure vehicles (10 lac) from vendor-A
    suppose PO no: 4500000000
    payment will be made to  Vendor-A by Vendor-B
    Accounting entry will be
    Vendor-A   Dr  10 lac   PK 25
    To Vendor-B     10lac   PK 31
    Internal clearing a/c DR  Rs 10  PK 40  Prof center -11xxx
    To Internal clearing a/c    Rs10   PK 50 Prof. center- 11xxx
    above entry posted by JV entry(F-04) but  my requirement is  if payment is made against PO-4500000000 by vendor-B
    how it will be reflected in Purchase order history?
    how we can know how much amount is paid particular purchase order?
    after payment by vendor-B we have to pay amount to vendor-B.
    vendor-B a/c Dr 10 lac PK 25
    to bank(Check issue)  10 lac PK 50

    Hi
    Payments are not updated in PO History anyways. However, you can still get the Invoice details of Vendor A, if you process this entry through FB05, using the option Transfer Posting with Clearing. This will ensure that when the Vendor B pays to A, this document will show up as a clearing documnent for Invoice of Vendor A.
    Thanks & Regards
    Sanil Bhandari

  • Kanban - External procurement with multiple vendor

    Hi Gurus,
    We are working on implementation of Kanban for external procurement (Scheduling agreement) in my organisation. As per the business requirement, some of the components are supplied by more than one vendor. As per the standard process, Kanban supports automated processfor single vendor only & not multiple vendors
    Has anybody come across this issue? Could you plese share your experiene & any possible workaround or solution to this isuue
    Thanks
    Kariya

    Hi,
    This is how KANBAN works. Since sourcing is automatic.
    You could do a couple of things; first, have more than one control cycle, one for each vendor. Drawback is that you also need to have separate kanban containers for each cycle/vendor. But in the case where you have more that one supply area for a material this is not so bad.
    Another way could be working with internal demand area, in such a way that Kanban creates a stock transfer reservation. Then you need to process the requirements with MRP, and issue orders to multiple vendors (maybe using quota arrangement).
    To ilustrate the solution: your supply area is geting replenishment from the main warehouse, not directly from the vendor. These are two different storage location or plants...
    Regards,
    Mario

  • Subcontracting material directly to subcontracting vendor

    hi all
    i created BOM in cs01 for material suppose m for three child materials .these components i procure from a regular vendorA. and give it for subcontracting to vendor C. i am creating a PO  in this at item tab delivery address is of subcontracting vendorC ,SC vend field is ticked and PO is given to vendor A. now when i want to do GR for this material i am getting error that "MATERIAL DATA AND PO DATA DO NOT MATCH"
    any help

    thanks i got the answer it can be planned via mrp

  • Customer sales return and same material return to respective vendor

    Hi Experts
    would like to get your valuable inputs in the below mention scenario
    I procured material ABC qty 10 from vendor and same has been sale to customer
    now Customer is returned the material ABC qty 5 to my client
    now client want to return the goods for the respective vendor from whom it was procured.
    The requirement is the system should able to predict automatically  from whom the goods has been procured? 
    note:- client can procure the same material ABC from 10 different vendor
    Is there any  common link can be maintained  between purchase material from vendor to my client  and from my client to customer ?

    Hi,
    Lets Try to do in this way,
    1.Create a sales order
    2. Create a PO for that material, Now at GR in delivery filed give the sales order number. so in PO histry tab of PO we can c the sales order number. and sales return can link with PO.
    Now in case Sales order is latter the Purchase then
    in Sales order PO filed we can give the PO number on which we have procurred the material. so when u go to sales order display system will give PO ref.
    3. Now while sales return you will get the ref. of sales order
    4. Lastly it is time to send the material to the vendor 4m whom it is been purchased, here u can get the link :- 4m sales order, PO field u'll get or 4m PO history you can get the sales order number.
    try this mix, it may work without any further efforts
    Rgds
    S