Mtl Availability Problem @ Production Order Release

Hello All,
For production order creation and order release we have different types of availability checks:
1: Order creation: check all purchase orders (ZP02)
2: Order release: do not take purchase orders into account (ZV02)
In the material master the field "availability check" is always set to 02.
The problem with this is that as soon as we want to release a production order, the future purchase orders are not taken into account, but the corresponding production orders (created ones) are. This yields missing parts at release, even though there is enough in stock.
The following options are now selected for ZV02:
[ ] incl. purchase orders
[ ] incl. purchase reqs
[V] incl. dependent reqs
[V] incl. reservations
[V] incl. sales reqmts
[V] incl. deliveries
[ ] incl. ship notific.
incl depend reservat [x] all
incl rel order reqs [ ] do not check
incl planned orders [ ] do not check
incl production orders [x] all
I tried changing OPPJ. Things that do not work or are unwanted are:
changing ZP02 identical to ZV02, since purchase orders should be included for orders in the future
changing ZV02 identical to ZP02, since purchase orders confirmed to today might be delivered tomorrow, which would yield missing parts.
changing ZV02, incl. Production orders from [x] to [F]. Still missing parts @ release.
Thanks in advance.
Regards,
Marc

Hello
I assume here that 02 is for the component in the production order, am I right ?
All components have the material availability at 02, so you are right.
Now in 02-ZV02 , the you are considering all the reqmts coming from planned or production orders, is that right ?
Yes, both planned and production orders are checked in ZV02 and ZP02.
Is ZP02 working according to what you need ?
ZP02 is used @ order creation. This works fine, because it takes purchase orders into account that are confirmed in the future. This is correct at order creation.
Cna you check the differences between both rules ?
Purchase orders are not taken into account for ZV02
Purchase orders are taken into account for ZP02.
The rest is identical to the previous list
An example:
Day 0 (current stock): 200 of material X
Day 1: Production order requires 200 material X
Day 2: Purchase order is confirmed for 200 material X
Day 3: Production order requires 200 material X
Result of ZP02: in stock: 200, required 200 + 200, confirmed @ day 2: 200 --> No missing Part
Result of ZV02: in stock: 200, required 200 + 200 --> Missing Part
The best solution would be for the system not to look at the requirements of the orders in the future which are not released yet. Therefore I changed the key ZV02: incl. Production orders from [x] to [F]. However, this did not have any effect!
Regards,
marc.

Similar Messages

  • Incorrect Result of Material Availability in production order

    Hi gurus,
    we have a problem with material availability in production order CO01. When my list of materials is checked OK with option availability material and I modify the quantity of some material. With this modification, e.g. quantity 99.999, the logical result of my material availability would be NO OK, but the system answers is OK. I think he material availability doesn't recalculate the availability.
    I will reward with a lot of points!!!
    Thank you
    Dan

    in the availability check screen of the prod order, find out the which check group is being called. and find out the scope of check,
    then in the custmisation, change the setting of the scope of check.
    Trx code OPJJ, deselect/select the indicator "check without RLT".  if there is tick in ur current system then uncheck it, it the tick is not there then tick it.
    your issue will be solved.
    Regards,
    Pravin Mukkawar

  • Preview and print a printout in production order release

    Iu2019m using CO02 to release and save the production order. Currently u201Cbatch cardu201D printout is automatically printed in production order release. I want to change this to preview the printout before printout is send to the printer. Can someone tell me the configuration for this.

    Hi
    Pls refer this link
    layout adjustement in production order- suitable to printout sheet
    Print Preview of Production Order
    layout adjustement in production order- suitable to printout sheet
    Thanks
    S.Murali

  • Unique serial number during production order release for FG materials

    Hi,
    Actually our client is asking for serial number generation for each FG material during its production order release.
    So that with this serial number he can track it in shop floor plus after dispatching to customer.
    Here the scenario is Make To Order, this serial number will also be considered by SD during dispatch.
    For serial number creation, I referred documents from SAP best practices(help.sap.com).
    After this, now I am able to create serial number for specific material automatically.
    Currently I am getting serial number with respect to material specific, i.e., serial number generating with respect to FG codes. Ex:- FG1 - 1, 2, 3, 4 and FG2 - 1, 2, 3, 4.
    But as per my client requirement, they want serial number without material specific, i.e., common serial number for all FG codes.
    Ex:- Sr No- 1-FG1, 2-FG1, 3-FG2, 4-FG1 - - - - according to production order releasing sequence.
    Plz inform if any settings are to be made.
    Thank you in advance.

    Hi Arman,
    I Had got solution for how to track which FG is linked to which SFG sr no, just go through the below link it also gives how to use COIB transaction.
    COIB transaction usage, how to track which FG is linked to which SFG sr no
    But still I had not got solution for
    how to assign common serial number for all FG codes automatically
    Ex:- Sr No- 1 -> FG1,
    2 -> FG1,
    3 -> FG2,
    4 -> FG1
    - - - - according to production order releasing sequence.
    Whether is it automatic serial number assignment is possible or not.
    Plz inform if any settings are to be made.
    Thank you in advance.

  • Serial number during production order release

    Hi,
    Currently I am getting serial number with respect to material specific, i.e., serial number generating with respect to FG codes. Ex:-  FG1 - 1, 2, 3, 4 and FG2 - 1, 2, 3, 4.
    But as per my client requirement, they want serial number without material specific, i.e., common serial number for all FG codes.
    Ex:- Sr No- 1-FG1, 2-FG1, 3-FG2, 4-FG1    - - according to production order releasing sequence.
    Plz inform if any settings are to be made.
    Thanks,
    regards,
    B C Gudageri

    Thanks Glenn Larson,
    This is the first time for me for creating serial number for FG materials.
    Actually our client is asking for serial number generation for each FG material during its production order release.
    So that with this serial number he can track it in shop floor plus after dispatching to customer.
    Here the scenario is Make To Order. So this serial number will also be considered by SD during dispatch.
    For serial number creation, I referred documents from SAP best practices(help.sap.com).
    After this, now I am able to create serial number for specific material types automatically.
    But here the condition is client wants serial number should not be specific to material codes but should be common  throughout the plant for all FG codes.
    Ex:- Sr No- 1 for FG1,
                       2 for FG2,
                       3 for FG2,
                       4 for FG3
    - according to production order releasing sequence.
    Me dont know about Presort and IMB serial numbers.
    Please tell me the appropriate approach I can make or any of links which I can refer.
    Regards,
    B C Gudageri

  • Production order release

    Dear Experts
    Good Afternoon
    I have small query regarding production order release when ever i try to release a production order system give following message
    System status WCRE is active (ACT 20030197 0010) and system status of work center is CRTD WCRE
    I can't able to find the clue how to release the sale order
    Kindy guide me
    Valuable answer will be rewarded
    Regards
    Rajeev Garg

    Hi,
    Pls. check for your Work Center Status in CR02 / CR03 -
    > Extras -
    > Administrative Data -
    > Status.
    Check whether it is locked or not. If work center is locked , unlock your work center from
    Extras Menu--->Status--> Lock / Unlock.
    Hope this may help you.
    Regards,
    Tejas

  • MRP - production order release

    Hi experts,
    I am new in SAP PP
    currently when run the MRP, it will generate planned orders and PR's. it will calculated planned order sub compoents requirement qty also.
    but i want to change settings for once convert planned order to production order once release after only need to create sub compoent PR's and planned order
    pls explain what change need to do?
    Regards,
    Elango

    Hi
    This is not possible,because planning and production order releasing is two different activity.When ur release production order thats mean ur giving green signal for manufacturing or start manufacturing and when ur release the production order ur work center or capacity is get booked against that production order. So at the time of production order release if u want to plan the child item then u have to procure ur child item then u have start manufacturing so complete time ur capacity is showing as loaded then ur not able plan for other production order.

  • Production order release Material Availability check

    Gurus,
    I have a production problem where the order can be released when the component for the order is in a restricted status.  This is not allowed by the batch search strategy.
    <u>Here's Problem Description:</u>
    When running on version 4.6C, I have a work order created. I release the work order successfully.  However there is a component that has an invalid material/batch according to the batch search strategy  The material availability check shows all components available. 
    However, I remove the batch and the batch can not be entered because it is not correct according to the batch search strategy.  I try and release and the material is added to the missing parts list.
    I change the component so that it can be used.  
    Put the batch number back in the order. 
    Save the order.  
    Change the component material/batch so that it is no longer valid.  
    The order will release and it shouldn't because the material/batch is not valid.
    <u>I've looked at the following transactions and master data:</u>
    OPL8 - Order Type - Dependent Parameters Overview for my plant and order type and the check batch box is checked.
    MM03 - Material Master MRP 2 view for the component to get the availability check
    OVZ2 - Availability check control
    OPJK - Order Control to get the checking rule for order release
    OPJJ - Availability check control details with availability check and the checking rule for order release - I did not see anything here that would influence the checking based on if the batch was entered or not.
    I did double check the batch search strategy for production order - COB3. Everything looks OK there.
    Does anyone have any other places to check? I must be missing something. I tried OSS - there weren't any notes that I could find.
    Thank you!
    Michelle

    Hi,
    Check in order control opjk for order type pp01
    Batch assignment /release material
    Release despite missing batches
    no release if batches are missing
    Regards,
    nandha

  • Error during Production Order release

    Hi Experts,
    When I am releasing one production order follwoing messege appearing.
    Error during availability check for order xxxxx (see log)
    co02>goto> logs--> release
    Date 22000504 lies after the end of the valid factory calendar (please correct).
    I have checked routing, pv, bom etc. availability check indicator 02 is alreadly maintained in mm03. Earlier we have confirmed several order of this material in the past, now suddenly this error is appearing.
    Kindly help me to solve this problem.
    Regards
    GR

    Hi,
    Chk for following :
    01. Timings in Routings/Factory calender
    02. Chk for all components in order . It may be possible that one of component is having some MRP elelment dated beyond factory calender
    03. Also chk all receipt /issue elements with dates .
    Regards,
    Milind.

  • Production order release with batch management

    Dear All
    Our company are going to use batch managment. But someone told us the production order cannot be released if the component with batch managment is missing (requirment is lower than stock). Is that true?

    Dear,
    It depend upon the setting means if you want to automatic batch determination in production order for component then system will not allow to release if no batches are available.
    This setting come from MRP 2 view batch entry if you keep it blank then system will allow you to release the order with missing batch quantity also.
    Please try and come back if any issue.
    Regards,
    R.Brahmankar

  • Stanging indicator change in control cycle after production order released

    HI
    We have MM PP interface active
    i setup staging indicator 4 for one material via control cycle
    Production order is created and released
    now we would like to change staging indicator to 1 [pick parts]
    how we reread control cycles data in production order
    Thanks

    Try: CO02 > Functions > Read PP master data

  • Disable certain changes in sales order after production order release

    We are in the MTO scenario and are also using variant configuration. The business requirement is that after a production order has been released (REL status) the preceding sales order item should be “locked” for certain changes. Such changes would include VC and some other fields (e.g. quantity and dates). Some minor changes like texts should still be allowed.
    The best idea we could come up with is to put some validation in the sales order user exits, but there are some disadvantages. It seems kind of strange though that there would be no such functionality in standard SAP (e.g. some changes in the order can’t be made after a delivery has been created). Is there by chance anything in the configuration that we missed?
    I found this old thread, but it still seems to require user exits. Unfortunately couldn't find anything specifically on the production order / SO integration.
    Thank you!

    Hi Jelena,
    Try in the userexit MV45AFZZ
      (form userexit_field_modification)
    Example:
    select * from afpo where kdauf = vbap-vbeln
    and   kdpos = vbap-posnr.        
    if sy-subrc = 0.
    select single * from aufk where aufnr = afpo-aufnr.
    if aufk-loekz = ' '.                                 
    select single * from jest where objnr = aufk-objnr
    and   stat  = 'I0002''   
    and   inact = ' '.
    if sy-subrc = 0.
    screen-input = 0'.
    endif.
    endif
    endif.
    endselect.
    .H.Terras

  • User Exit at Production Order Release

    Hello Everyone
    Could anyone tell me if there is any particular User Exit at the Release of Production Order? I have seen the list but didnt find any appropriate one.
    Reward points Guaranteed
    Regards
    Chandra

    Hello,
    Another workaround could be to create a user status 'released' (REL) that is set at 'order release' and removed at ' reread master data' is done (just like the system status REL).
    Attach the ABAP code to the activation of the user exit.
    Other advantage is that you have another field to select in COOIS(PI). We have created user statusses in order to replicate all primary system statuses (CRTD, REL, TECO, CLSD) in order to facilitate reporting. Via this way we have a column with only one status for filtering, sorting summarizing...
    Regards,
    Philip

  • IDoc Production Order Release

    Hi,
    Can somebody explain how to create an IDoc automatically whenever a Production Order is released or changes made to a released production order? Appreciate it.
    Regards,
    V M.

    Hi VM,
    It would be helpful for the forum if you can put across the method by which you resolved the issue. We all can then refer to your solution if we face a similar requirement sometime in future.
    Regards,
    Vivek

  • Production order release based on operation

    Hi friends
    How to release production order based on operations ?
    pl help me

    Hi
    The real time scenario is to select release operation wise is:
    If you are expecting any change in the subsequent operations after starting of production  say first opration, you will opt for this .
    I do not find any advantage if you release all operations at a time in mass processing. It is as goods as releasing at header level.
    Normally in such cases one can opt for  trigger points in which system will release successive oprations automatically when preceding operation is confirmed.
    If you want manually release the operations you can select the operation which you want release & press release button in operation overview screen.
    Hope it is clear now.
    Regards
    YMREDDY

Maybe you are looking for

  • Replication of   customers from R/3 to CRM

    Hi everybody, After completion of Initial Download of data from R/3 to CRM ,the customers replicate crm. But my doubt is once we do initial download then the customers which are in R/3 in bulk are replicated to R/3.But there are few customers which a

  • How to separately backup the Boot Camp drivers partition from Leopard DVD?

    I used Disk Utility and my only (and expensive) DVD+R DL disc to make a backup copy of my Leopard DVD, and it worked perfectly to install Leopard on my MacBook Pro. However, that was before I learned that the Boot Camp drivers was now on a separate,

  • Cost in invoice in the case of third party drop ship scenario

    Hello ALL We have third party drop ship scenario where vendor drop ships the goods to customer on our behalf and once we get the confirmation from vendor we bill the customer.  The sales order line has TAS item category.  When we raise the invoice th

  • Adobe Photoshop CS4 64 Bit Crashes At Start Up

    Hello. Today I installed a fresh installation of Windows 7 64 Bit. Installed Photoshop CS4. At first both 32 Bit and 64 Bit worked. After installing some Plug Ins the 64 Bit stopped working. It loads, then I get an Error Message: Runtime Error! Progr

  • How to create csv file in stored procedure

    I want the output of my stored procedure in a csv file. How can I do that?