Order operations in sequence
Hi,
As per strategy, tasks are getting copied from Tasklist to Maintenance order. In this case operations in Maintenance order
are not in sequence . For eg. 0010, 0020, 0050, 0090 etc., How to get the order operations in sequence like 0010,0020,0030,
0040 etc.,
In config for TL profile, renumber & remaining check boxes are ticked .
Eventhough it's not coming in sequence.
Kindly advise me where i'm going wrong
Thanks
Prasad
Pete,
Thanks for your reply.
For eg., Task list has 15 operations.(0010,0020.....0150) as per strategy based plan only monthly taks have to come in preventive
maintenance order.
After scheduling system creates preventive maintenance order.
In operation screen Client requires operation number in sequence like 0010,0020,0030,0040 etc.,
but in system it's 0030,0040,0050,0070,0090. Since it's monthly strategy system picks only those operations.
In SPRO i ticked Renumber for Tasklist profile & in order also default settings renumber chk box is ticked.
But still operation numbers are not in sequence.
Kindly help me to come out of this issue.
Prasad
Similar Messages
-
Process order operation information
Dear Experts,
I want to know the name of table from where I can get information of process order no., process order status and the operations which are still to be confirmed for the order. I think I will have to create a view by using two tables but let me know which tables should I refer.
Thanks in advance.
PrashantDear
Find below the SAP tabel for your report requirement :
Order tables :
AUFK Process order headers
AFKO Order header data PP orders
AFPO Order item
AFVC Order operations
AFVV Quantities/dates/values in the operation
AFVU User fields of the operation
AFFL Work order sequence
AFFH PRT assignment data for the work order(routing)
JSTO Status profile
JEST Object status
AFRU Order completion confirmations
Process Order operation tabel :
PLAS Task list - selection of operations/activities
PLFH Task list - production resources/tools
PLFL Task list - sequences
Order and Operaton syetm Status : SAP Table and field : JEST-OBJNR
1.Orders/Operation with status CRTD : JEST-STAT = I0001 .
2.Orders/operation with status REL/PREL : JEST-STAT = I0002 /I0042
3. Orders with status MSPT : JEST-STAT = I0004
4. Orders with status PRC : JEST-STAT = I0016
5. Orders with status DLV/PDLV : JEST-STAT = I0012
6. Orders/operation with status CNF/PCNF : JEST-STAT = I0009/I0010
7. Orders with status GMPS : JEST-STAT = I0026
8. Orders with status TECO : JEST-STAT = I0045
9. . Orders with status DLFL : JEST-STAT = I0076
Hope this will help you to include required table in your BI report
Regards
JH
Edited by: Jiaul Haque on Jun 3, 2010 9:12 AM -
Work order operation number in Production Scheduling
Hi,
We are using production scheduling for scheduling the discrete jobs. In production pegging view, the work order operation is shown in number "xx:xx:xx:xx:xx" not the name of the operation. Is there any setup required to display operation name? Any patch required?
Thanks,
Anitha.Hi,
I have face similar issue in deleting PO line items.
Even though I delete items, system check budget for deleted qty with the currency conversion + value & gives budget exceed error.
In some cases we have asked user to deactivated AVAC asked to do the transaction, which is not recommended.
You can try running CJBN & CJBV in sequence for affected WBS.
Thanks & reg,
Sam -
Error message if invalid characters entered in PM order oper.short text fld
Hi ALL,
I need to display a error message, when user enters the invalid characters in work order operation short text field. The error message should be displayed during work order u201CSaveu201D (during creation and change mode).
Kindly let me know is there is any user exit / BADI can be used for this.
Note: I have checked some user exit, such as IWO10009 but I am not getting the value of Operation short text (AFVGD-LTXA1) to compare and throw the error message
Regards
Ramuhi
the exit is correct but don't use structure field,
follow this to get text
get AUFPL(Routing number of operations in the order)from CAUFV and paa it in AFVC -AUFPLyou get the short text
it can be usefull
-ashok -
Standard Report for missing parts at production order operation level?
Hi PP Gurus,
We have standard report for missing parts at production orders level.
For our client, they need a report for missing parts analysis at production order operation level. Do we have any such standard report in the SAP?
Please help.
Thanks,
Reddy.Hi Arvind,
Thanks for for your response.
1. List: Components, Layout: Standard layout set the Missing part
It shows the component requirement/withdrawn quantity for each operation of production order. It is not showing the commit quantity.
2. List: Components, Layout: Pick list set the Missing part
It shows the component requirement/withdrawn quantity for each production order.
3. List: Components, Layout: Missing Parts List-Material View set the Missing part
It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
4. List: Components, Layout: Missing Parts List-Order View set the Missing part
It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
We are unable to get the solution from all these 1 to 4 reports from COOIS.
Do we have any option to change the existing layout (ex: 3 ) to get the commit quantity for operation with missing parts indicator?
If avilable, what is the procedure to be followed?
Thanks,
Reddy. -
PM Order Operations Default Unit of Measurement
Halo Experts,
We have a problem in UOM for PM/CS order operations. We have defined HR as default value of UOM for operations in IMG.
Business wants to change at the order level to H as UOM and it is manually keyed in and saved. But when we check with the F4 option for Unit of Measure " H" doesnt appear where as HR appears.
Any restrictions in displaying all the unit of measures. Can anybody clarify why "H" is not appearing on F4 option in the work order operation line items.
Regards,
SelvaHi Rajesh,
We are getting the default unit in operation tab and all the config of default values is available but when we execute the F4 option the unit "H" is not appearing where as if we change from HR which is a default unit to H it is getting saved at the operation Tab.
Hope it is clear now.
Regards,
Selva -
Changing Work Center in PM Order Operations
Hi PM Experts,
We got two companies operating in the same SAP client. But user are properly restricted with Authorizations in terms of company codes, maintenance panning plant, maintenance plants etc, etc,
But I noticed that in IW32, in work order operations users belonging on to one company can select(F4) work centers/maintenance plant from the other company and save orders.
I was under the impression that org level authorizations block this. Is there a way to stop this? provision of the the relevant authorization object in this regard will be a great help.
thanks in advance,
Cheers
DeepalHi
Please check the below link. may useful
[http://help.sap.com/saphelp_470/helpdata/fr/a5/3eca044ac011d1894e0000e829fbbd/content.htm|http://help.sap.com/saphelp_470/helpdata/fr/a5/3eca044ac011d1894e0000e829fbbd/content.htm]
Regards
Seenu -
Status not updated in JCDS Order Operations
Hello Experts,
I have a requirement in which if status changes (either system or user status ) for any operation of an order, I need a table which shows object number , the date of status change .
In JCDS , when i change some Order Operations status they are reflected into JCDS with their change dates and when i change some Order Operations status they are not reflected into JCDS.
In JEST we have only status values but not the change date , i need the status change date.
I checked so many tables but they don't Order operation status change date.
Can any share some light , are they are restrictions that certain order types operations only get reflected into JCDS.
Thanks
VamsiHello All,
I have spoken to my functional team.
There is setting in SPRO or you can directly go to Tcde 'OIOE' and you have differnt plants and order types and you can set different flags accordingly the change pointers will be updated to JCDS.
From the next doument created after enabling this setting, the change documents are reflected in JCDS in our case.
Appreciate your help.
Thanks
vamsi -
Process Order operation scheduling duration calculation
Hi
We have following formula has been maintained for processing time calculation in resource.
Machine * ( Operation quantity / Base quantity / Operation splits ) + Setup + Change-over
As per above formula for following procee order qty and time, SAP caulates time.
Opeartion qty - 100,
Base qty - 100,
Op split - 1
Machine - 0.5 hrs (30 Mins)
Processing time calculated as 30 mins (.5hrs)
When I schedule the process order with same resource for same qty and machine time, processing time is calculated as 33 mins. We dont have maintained any floats in scheduling margin key in material master. We dont have any wait times also.
Can you please let us know why process order operation is having 3 mins tolerance? Any idea where such settings has been maintained?
Any pointers will be helpful.
Edited by: nilesh sankpal on Dec 8, 2011 5:47 AMHi Mangalraj,
Thanks for your reply.
We have not maintained ay reduction levels in OPUZ for plant and order type combination.
In resource, we have 2 hrs break time and total operating time is 18.50 hrs.
I got following SAP help link for calculation of duration for processing time.
http://help.sap.com/saphelp_46c/helpdata/en/b1/c04387439a11d189410000e829fbbd/content.htm
Is processing time is calculated based on following formula.
Processing time u2013 Calculated Processing time * (1+ (Length of break / Operating time)
Can you please correct my understanding here?
Thanks in advance.
Nilesh -
Use of field 'StartPoint' in work order operation's 'Dates' tab
Hi,
Can someone please explain me on the uase of field 'StartPoint' on work order operation's Dates tab.
Regards.Start point will be used in case of scheduling for the operation.
By mentioning the condition & date, while doing automatic scheduling, system will change the start date of the operation & correspondingly finish date.
Note: This will work only when Automatic scheduling is ticked for the control key.
Regards, -
Query of catalog in order operation tab
Hi experts
I have a question of catalog in order operation tab.when pressing the 'catalog' button,
system prompts "No catalog could be determined",
could you explain how to do it's configuration and the business scenario when we need
to use such catalog.
thank you!Mark,
You can create internal or external catalogues similar any any internet based shopping site. The catalogue can have stock and/or non-stock components which you add to your shopping trolley.
PeteA -
Standard report for User defined feild in order operation
Hi all,
do we have any standard report? for User defined field in order operation. actually we have User defined field in task list and same could be reflected in order operation. so i am using those user defied field to record extra info in maintenance order. i am wondering how to get the reports . do we have any standard reports?
thanks
Amit kushwahaDear Amit
I have utilised 3 user fields & activated order enhancement tab. I could find these three fields in report IW37N & IW49N. I m using ECC 6.0 EHP4. Try to set the layout & look for fields - user field for quantity in the layout. For this please maintain some data in these user fields of some orders and then check for those orders in t code- IW37N & IW49n.
Shakti -
Prevent assignment of personnel in maintenance order operation
Dear Gurus,
Is it possible to block or give a error message when I try to assign in a maint order operation a person assigned in the workcenter who has been marked absent through SAP HR module. Suppose in HR module the person (personnel no.) has been marked absent for the day 19.07.2008. Now when I create a maint order with operation and assign try to assign the same person ( linked through workcenter) for 19.07.2008, the system should give a error message saying that the person is marked absent for that day.(something similar to availability check).
thanks and best regds
Arunhi arun,
have you got the answer of your question b/c i also have the same question.
Regards,
E-Jad -
Mass change of Production orders operations in ECC 6.0 using COOIS
Dear experts,
Kindly Suggest a way to mass change of direct operations and components overview screen of production orders in ECC6.0
using COOIS transaction code which was available in SAP 4.7 using environment >change order> operations or components once we execute the COOIS with certain input parameters in the out put screen,this function seems to be not available in ECC 6.0 , if available kindly guide me or any alternative way to perform the same.
Thanks in advance for your inputs and help..
Best regards,
Nitish jainYou have that button "Change Order" you can just click on it and once you're in the change mode of the order click "Component Overview" button , it's the same number of clicks...
Anyway, SAP has changed the entire ALV for all the transaction codes using PPIO_ENTRY (COOIS, CO26, CO27, CO28 et al)
look at question 12
https://service.sap.com/sap/support/notes/540779
if you really want your old GUI status. there is a way to get it back. In SE38 enter the program name PPIO_ENTRY and select variants and click display. Once you're in variants screen enter variant name and click create and select all "screens" check box and then it will take you the selection screen in there check the box "Old ALV Display" in the Technical settings sub screen. (If you want you can choose other functions also like "Selection List" as PPIOM000 Always display components directly etc. if you want ) Click on "Next Screen" button and it will show "Attributes" button then click on the attributes button and save it.
Now go to SE93, make a copy of transaction COOIS to ZOOIS and in the variant field enter the variant you just created. The new transaction will always start with the variant you just created and it will look like your old COOIS with Environment > Change Order > Components will be visible.
Edited by: Jeevan Sagar on Oct 20, 2011 9:50 AM -
Maintenance order Operation mass change with Ehp5
Hi Experts,
We are currently working in ECC 6.0 Ehp3 and we are exploring the additional features with Ehp5.
To explore the Ehp5 functionalities (Maintenance order Operation Account Assignment and Operation mass change) we did the foloowing:
1. LOG_EAM_CI_2 to LOG_EAM_CI_5 and LOG_EAM_LINEAR_1 business function is activated
2. LOG_EAM_OLC: Operation Account Assignment business function is activated
3. Under Define Cost settings configuration, the relevant Plant and Order type checkbox is activated
4. The user role is adjusted to enable the Maintenance order Operation mass change functionality
Suppose the LOG_EAM_OLC business function is activated on 01.02.2012
The Maintenance orders created before 01.02.2012 is allowed to do the Maintenance order Operation mass change.
But the Maintenance orders created after 01.02.2012 is not allowing to do the Operation mass change and throwing the error message.
Error message: Operation Account Assignment orders (order type XX) are not supported
Program name: SAPLIBAPI_ALM_ORDER_PROCESSING
Message Class: ERP_CO_OLC_E (Messages for Operative Level Costing)
Message number: 066
I have reffered the supporting documents, but it didn't helped.
Please help me.
Thanks,
RajHi,
I expect the issue is with BAPI_ALM_ORDER_MAINTAIN. The mass change functionality usues this BAPI but the BAPI does not currently support OLC orders. When you try to change OLC orders via the BAPI (or the mass change functionality tries to do it) this is prevented and the error message is issued.
At the moment, you will not be able to use mass change for OLC orders.
-Paul
Maybe you are looking for
-
The DigitalPersona Personal icon does not come up now that I've installed Firefox 4.0 beta.
-
New MacBook Air: Video clips I've shot don't show up from my external hard drive
Bought the smaller Mac Air for international travel, intending to use the an external for all the video I edit. Brought an older external drive (last used last year on an overseas trip) with back-ups of lots of video clips there. I want to mix my o
-
Any suggestions on how to take the text from a PDF and use in Word doc
-
Cant transmitt and Recieve data when USER INTERFACE Execution Mode selected
Hi.. I am working on a project in which I have to continuously send and recieve serial data.. Again, in my application, I want to use AciveX control to open PDF (Theory related to the project). PDF can be opened only in USER INTERFACE Execution Mode.
-
How to exclude top-level keywords from export?
Hi, I have keywords organised into a hierarchical structure; I never want the top-level keywords to appear in the exported image but can't find a quick way to do it. I can make it work by going to one of it's children and editing that keyword tag, un