Hi
We started at a new client and have difficulty maintaining the Org Structure A 011 relationships to child Org Units. The system undoes our implicit links. We want the implicit links to be there and not inherited. Is it possible to switch off the inheritance in config?
Please assist/advise.
Thank you, Adrian

what do you mean when you say the system 'undoes' your implicit links? Did you mean the system undoes the inherited cc value by using the explicit cc-assignment done at an org unit level? if yes that is how sap works,...  the options are
a. do not do explicit creation of cost center to org unit . that way assigning a cost center at the top org unit will suffice as that will be inherited to all org units down the structure. But this is not a workable business scenario at all.
b. determine the explicit cost center assignments at each org unit level and do the assignment accordingly.
lastly : I dont think inheritence of cost center is something you can deactivate in img.
cheers

Similar Messages

  • How to hide parent cost center code in the costing LOV

    Dear Gurus,
    I have a very peculiar issue. I want to hide parent cost center code that appears in the costing LOV of employee in the others tab. Can any body help me out on this one?
    Regards,
    Muhammad Noman Shafique

    Hi,
    I do not have the exact steps for form personalization as I am not good in this :-(
    But regarding the costing segment (removal from all pages) you can follow below steps:-
    1. Navigate to Sysadmin --> Application --> Flexfield --> Segments
    2. Search for title "Cost Allocation Flexfield"
    3. Now click on teh code that is attahed with your business group and then click in segments.
    4. You will see all the segments defiened for the costing.
    NOTE: If you want to disable one of them uncheck the "Freeze Flexfield Definition" in the "Key Flexfield Segments" window. But do remember that it will affect all your costing and you wont be able to select the disabled costing segments in any other window (Element Entries, Assignemnt, Organization, Element link and Payroll)
    Thanks,
    Avinash

  • Org Unit and linked people

    Hello everybody,
    I have a requirement to show the Org Units available in the system, I found a table (HRP1000 or HRP1001) where I can get it, but I nedd also to show the personnel linked to each Org Unit, does anybody know how can I do it?
    Is it posible??
    Thanks
    Gabriel P.

    You can create a range for this value...
    SOBID LIKE HRP1001-SOBID,
    And linked them with PA0001 table -;)
    HRP1001-SOBID ==> P0001-ORGEH.
    Greetings,
    Blag.

  • Link between Material, Cost center to Work Center.

    Hi Experts,
    Can you provide me the following.
    Link between the material and work center.
    Link between Cost center and Work Center.
    Thanks in advance.
    Jyoshna.

    Extend the cost center validity from 01.01.2008, there won't be any harm. It may take from the beginning of the calendar year.

  • Linking documents to cost center?

    hi all
    is it possible to linked finance documents to cost centers?
    if yes how to do that because i don't find any SAP object for that.
    for usefull answers pts will be awarded,be sure
    thx in advance...

    Dear friend,
    service for object for attachment is available with every tr. code and for that DMS is not required.
    what i required is SAP object link in tr. code CV02N for attaching documents with cost center.
    thx..

  • Link b/w cost center and activity of a WBS

    Hi,,
    Can anyone let me know how work center and activities of a WBS are linked?
    Please let me know ASAP...
    Regards,
    Balu

    I got to know...
    Take object id from AFVC for the activities and give it to CRHD to get the cost center

  • Cost center and org unit missing in payroll report

    Hi Gurus,
    Our HR administrator has moved a position from one org. unit to another via PP01 - she has done this via a change action and not copy thus the record went missing and caused staff for that position with no Cost Center & Org Unit.
    Although the position has been reinstated back to the old org. unit, and relationship shows correct cost center and org. unit - still the payroll report does not pick up the same attributes.
    Please help.
    Thanks,
    MVM

    hi ,
    is the cost center data correctlly stays in 0001 infotype  ?
    if your connections are normal in pp01 1001 infotype , you can run rhintexx programs.

  • ISH Cost center allocation NCOP

    Hi there,
    Using transaction NCOP I have set up cost centers linked to organizational units.  I have a requirement to assign organizational units to different cost centres based on validity dates.  For example, org unit C5 is assigned to cost center C5 from 19990101 to 20100811.  As of 20100812, org unit C5 is assigned to cost center C5SG.  When billing using transaction NA30N when the patient has been discharged, I would expect that the revenue up to 20100811 would be assigned to cost center C5 and after that, it would be assigned to C5SG.  However, when I bill using a date of 20100830, I see that all revenue is going to C5SG instead of being split based on validity dates.  When interim bill using a date of August 11, the revenue up to that date is allocated to C5 correctly.  The entries in table NO2K have the correct validity date.  Any idea why revenue postings do not consider the validity date on the cost center config and why they seem to be dependant on billing date?
    Thanks,
    Shelley Braida

    Hi Shelley
    I'm sorry, but the system takes the billing date for cost center determination ...
    See include LN090F01 - form FILL_FKOMP_GENERAL.
        PERFORM fill_costcenter USING p_fkomp-anfoe p_fkomp-anpoe
                                      p_fkomk-abdat  s_tn25a
                                CHANGING p_fkomp-kostl p_fkomp-kokrs
                                         p_fkomp-prctr p_fkomp-aufnr p_rc.
    the p_fkomk-abdat is the Billing date and is the date used for cost center determination.
    IF you need to do another determination, from service date for example, I recommed to do so in the SD exit USEREXIT_FILL_VBRK_VBRP from the include RV60AFZC.
    With best regards
    Matías

  • I want to find the cost center manager's PERNR

    Hi,
    I have list of cost centers which are not the home cost centers. For this cost centers i need to find the person responsible. For this requirement BAPI_COSTCENTER_GETDETAIL1 function module returns the cost center details where VERAK field is the PERSON Responsible name. But I want the owners PERNR, USRID, AND POSITION.
    I dont know how to find the pernr from PERSON responsible name. So Please anyone help on it.
    Thanks & Regards,
    vignesh

    Hi,
    Your answer was helpful.
    Org.unit manager might be different. I can pick the org unit attached to the cost center and find the manager of the org unit. How are you saying org unit manager is same for cost center also.
    If org unit manager is responsible for cost center attached to it then i got my solution for my requirement. Please confirm this.
    If you know the bapi_get_costcenter_details1, then please confirm me that person_in_charge_user parameter is the user id of the pernr. This will also help me in resolving this issue because using user id i can get pernr.
    Thanks in Advance,
    Vignesh

  • Assigning cost center

    Hi Gurus,
    My scenario is like this.
    i have one org unit and five positions assigned to that org unit.
    Here client wants cost center assign it to org unit wise and also position wise.
    So my question is can we create different cost centers to positions and also org unit and assign them respectively.
    can i get the report position wise and org unit wise separately.What is the t code used for that.
    Regards
    Ananya

    Hi,
      I have below query requested your help and appriciated .
           I have done the automation of salary updating basic Pay based on the appriasal points . We have scenerio that an if employee gets 5% hike and from his salary of 4800 he should not get more than 200 as his grade is 5000 Max for this grade .But his actual eligibility would be 240 per month .
    I have to define the Maximum amount of 5000 for a specific grade
    I have tried using the Job Pricing --> Pay Grades and Levels(But i am not able to see the effect in this system , What would be missing )Please suggest .
    Thanks
    Sameer

  • Cost center behind an org. unit

    Hi,
    how can I get the cost center assigned to an org. unit ??  I am not talking about relationship A011; this works only if the relationship is available in the object´s master data. The problem is when the cost center is inherited from the org. unit above or from the one above this one or from .....
    Another problem is when the position is vacant; I cannot read IT 0001 for the employee.
    Is there any function or BAPI for that ??
    Thanks a lot.

    Hi,
    thanks both but it does not help. I´ll try to explain it other way. You create in CO a cost center and you create an org. unit in HR. You can then assign 1 or more org. units to the cost center. I am looking for that union. Relationship A011 is not much of a help.
    In the org. structure, a lower-level org. unit inherits the cost center from the father or grandfather org. unit, if we did not assign it to a cost center.
    I don´t want to read the higher-level org. unit for finding A011 or one level higher if A011 is not available or another higher level.

  • OM - Multiple Cost Centres link with Org Unit/Position not to employee

    Hello gurus,
    In OM there can only be one relationship at a time between an organizational unit and cost centre (A011). For those areas where there is a requirement for the position to have control over more than one cost centre, there are multiple options.
    Option 1 - If only one of the cost centres is used for employee cost incurrence, this should be the main cost centre, and the others controlled through authorizations.
    Option 2 - If more than one cost centre is used for employee cost incurrence, a subordinate organizational unit is created into which those positions are placed.  In this scenario, the  subordinate  organizational units would not have a chief, and the reporting structure would go up to the more senior organizational units.
    Option 3 - Use Cost centre distribution infotype 1018 (A014)
    My question: is there a standard way through which we can show multiple cost centres attached to a position/org unit such that cost incurred by employees goes to master cost centre attached to org unit or positon and other cost centres are just attached to position/orgunit (just to show the org unit/position is managing these other cost centres as well).
    Any thoughts? Anybody has used Enterprise Organization in CO to achieve this?
    Regards,
    Ahmad

    To capture more than 1 cost center, you have to specify them in IT-1018  but employee's cost will be split based on this.
    For data maintanance alone cost distribution is not possible (based on my knowledge).
    May be equivalent custom infotype similar to 1018  @ Postiion / Org Unit level may work.
    along with Master Cost center.

  • Change of Cost Center Assignment for Organization Unit in HR

    Hi,
    Recently my client is changing their cost center number from 6char to 5 char format. I have created customized mapping table to link between old cost center number and new ones.
    Create new cost center referencing to old cost center is done too.
    However, for each Personnel Number, i need to change the cost center assignment which link to org unit. I have done this too manually at t-code PPOM. How can I do this for mass change? I have a list of org unit number with me. Is there any standard program to do this or i should use LSMW ?
    How do I make sure for each Personnel number, their cost center assignment will change to new 5 char format in the end as required?
    I am new to HR module.
    Thank you for your help.

    Hi,
    As Sikandar said, you will have to write an LSMW or BDC ( where in you can check and validate the input Cost centers) using PP01 or Po10.
    Also I think if you use BDC or LSMW you will have to run the RHINTE30 report. Check the documentation on RHINTEXX reports to get better idea.
    Cheers..
    Ajay

  • Cost center and Org. Plan

    Dear All,
    When  i am  assign to cost center   using polgi orga " " use blank its come. But after move to production  org plan part are disable and no data  is there. How i  assign both . i want cost center ans org. plan in pa30. Pls help.
    Thanks $ Regards,
    SRoy.

    Your question is not clear. Please check in T77S0 the value for PLOGI-ORGA is X and cost center is maintained for that org unit in 1001 infotype. To ckeck that goto PP01 and give your org unit and check the relationship infotye. If cost center is maintained and some person is hired to that org unit then in pa30 the cost should appear automatically.
    Thanks & Regards,
    Sandip

  • Link between customer and cost center

    Hello,
    How can we link customer with cost center?
    Thanks.

    Hi Pari,
    If you want to required cost center field in customer transaction.change the field status in G067
    or if want to assign the cost center for customer go for substitution rule.
    Regards
    Surya