Hi,
My client has procured the 7 machines from china.but he wants to take cenvat only for two machines and want that duty of another five machine will be loaded on asset cost.
Kindly suggest, how i will do it.
Regards,
Dinesh
9953460025

Hi,
You can try to create two line items in the PO with Qty 2 & 5 each.
Your Import pricing procedure should contain two sets of CVD condition types: one set is cenvatable and the other non-cenvatable. Eg: JCV1> CVD Condition type (Cenvatable), ZCV1>CVD Condition type (Non-Cenvatable).                            
Assign cenvatable CVD condition type in your "Maintain Excise Defaults" IMG node.
For the first line item in PO with 2 Qty use the CVD condition types(CVD, Edu.cess on CVD, SeCess on CVD & ADC) which are cenvatable in nature and for the second line item use CVD condition types which non-cenvatable. Post the GR's separately so that you can separately capture the excise invoice for first line item with Sub-transaction type IP.
Alternative solution:
If a separate set on non-cenvatable conditions are to be avoided, create the PO single line item with 7 Qty. Capture the entire duty as cenvatable. In case of Capital item procurement, the company is eligible to avail only 50% of the total excise duty credit i.e., 50% of the credit is posted to RG23C Part II G/L account and the rest 50% will be posted to Cenvat onhold account.
In your case, this 50% which is posted to Cenvat onhold account has to be immediately transferred to RG23C Part II account using T.Code J2I8 and then an excise JV can be posted to reverse the excise duty from RG23C Part II account using T.Code J1IH.
Try and let me know if it works.
Regards
Guru
9620944466

Similar Messages

  • AED for import purchase of  capital goods.

    Hi guys,
    We are executing the import flow for capital goods.In this case we also have the AED for customs(4%) applicable.In case of AED for customs we can take credit of 100% in the 1st year itself even for capital goods.But the problem is that after GR takes place the GL for carry forward gets updated for the AED even though we are taking complete credit in the 1st year.Hence the creadit is being taken twice for the same amount.
    PLease suggest any solutions for the above problem.
    Thanks in advance,
    Akshay

    Hi
    Please go through the SAP note on the same
    Regards,
    abhay

  • CENVAT CREDIT 100% TAKEN IN CASE AED ON CAPITAL GOODS INSTEAD OF 50%

    Hi Experts,
    This is with reference to the Cenvat Credit taken on Additional Excise Duty Payable on Capital Goods.
    Presently in SAP 100% Cenvat Credit has been taken into 26010713 CENVT CAP GOOD (CAD)  but as per law 50% Credit should be taken in the same year in which
    Duty has been paid and balance 50% should be taken in next year.
    The same treatment has been taken correctly in excise records.
    And i want to know only for imported there has been any law change regarding 100% credit should be paid in same year.
    Regards,
    Manjax

    Yes, this is std behaviour of the system,as per the law the AED will be allowed to take 100% credit in first finanacial year only.
    For more information refer the below link.
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/808c60ca-013b-2c10-34a2-94d1eb442e6f?quicklink=index&overridelayout=true

  • Cenvat clearing for IMPORT

    Hi
    i had selcted the accurals in condn type and assingned a key of fr3 . here my cenvat condition values shud not add to material . but still i see the values are cumulated at GR .
    Please help how to avoid
    chris

    Hai,
    1.Maintain excise defaults for CVD related condiitons in SPRO - IMG - Logisitcs general - Tax on goods & movements - India - Basic settings - Determination of excise duty - Maintain excise defaults.
    2.If CVD values are added to the material cost, then check the material type in J1ID.
    Maintain this input material as a raw material or capital goods like assets, tools or consumables as per ur requirement in Material & chapter id combination in J1ID.

  • 4 Entries for 1 purchase of capital goods

    Dear Gurus,
    I am Purchasing excisable Capital Goods ( Either from local or Import Vendor). In both cases in RG 23 c Part 1, register shows 4 entries for only one capital purchase. BUt in RG23part2, system is considering first entry out of 4 entries from RG23CPart 1.WHy it is like that ?.
    What is the CIN Rule for AED. is is 50 % this year  and 50% next year or full 100 % in current year in case of capital goods AED.
    Please Help.
    Thanx in advance.

    As per Std. rule u can take the ADC credit 100% in the Current year for Capital Goods.
    Biswajit

  • Setting in Tax code for VATABLE VAT on Capital Goods

    Can anybody tell me setting of Vatable VAT in Tax code on Capital Goods in Calculation Procedure Taxinn

    Hi
    first check the all conditions assign with pricing procedure.
    check tax code assign with co code and for vat condition type created the condition records or not ?
    check the validity periods of condition records.
    laxman

  • Help in CENVAT Posting for Import Asset Purchases

    Dear All,
    I have a Import Asset Purchase order that has excise posting.
    Excise duty rates are:
    HCESS 200
    BASIC 200
    CESS 200
    SED 200
    In Part 2 of Excising postings, I have the following entries:
    HCESS 100
    BASIC 100
    CESS 100
    SED 100
    Current system will have the following accounting postings:
    CENVAT Hold 400
    HCESS 100
    BASIC 100
    CESS 100
    CENVAT Clearing 400
    I would like to know why the SED Posting was combined in the CENVAT HOLD.
    Upon investigastion, the ETT for the PO is GRPO and subtransaction type of XX.
    In configuration for specify GL Account for Excise transaction, the Account is also different to the one actually posted in accounting.
    Customer also wants that for SED the Part 2 Posting should be 100 percent, so in the case above the Part 2 Posting should be 200 instead of 100.
    So I have a bunch of errors, the accounting document posting is not posting in the correct GL account as configured. The SED Posting is being bundled with the CENVAT Hold and customer wants 100% Part 2 Posting of the SED Excise rate.
    Appreciate if you could help.
    Thank you!

    hi
    please check that u have main tained the gl accounts for subtransaction IP for ETT CAPE
    check ur entry here
    spro>Logistics - General>Tax on Goods Movements>India>Account Determination>Specify Excise Accounts per Excise Transaction check combination of CAPE and IP is maintained here
    CAPE IP Credit CENVAT clearing account
    CAPE IP Debit CENVAT on hold account
    CAPE IP Debit RG 23 AED account
    CAPE IP Debit RG 23 AT1 Account
    CAPE IP Debit RG 23 BED account
    CAPE IP Debit RG 23 ECS Account
    and then for Specify G/L Accounts per Excise Transaction u have to maintain the GLs
    also check that u have maintained the material type as A asset for the material in J1id
    regards
    kunal

  • 100% cenvat on capital goods

    Dear all,
       How can  100% cenvat be availed in case of capital goods in case of transfer from  one plant to another.
        The T-code used  is J1IH

    Yes, this is std behaviour of the system,as per the law the AED will be allowed to take 100% credit in first finanacial year only.
    For more information refer the below link.
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/808c60ca-013b-2c10-34a2-94d1eb442e6f?quicklink=index&overridelayout=true

  • PO Lead Time cannot capture the time taken for shipping!

    Dear All
    I understand that we have PO lead time = PO Processing Time (Working Day) + Planned Delivery Time (Calendar Day) + GR processing time (working day).
    And this PO lead time will be added on top of my PO Creation Date to defer the actual goods availability date.
    My question:
    1. Planned delivery time is the time taken from vendor place to send out the goods to my warehouse. What if it is overseas purchase where goods leaving vendor's Port will first arrive in my country custom, and it will take 3 days to do clearance. once it is cleared, forwarding agent will delivery goods from my country custom to my warehouse. In this case, how do I capture it in SAP system for the planned delivery time as it has 4 periods of time now
    a. Time taken from vendor's port to reach my country's port
    b. Time taken for my country custom to do clearing
    c. Time taken for forwarding agent to fetch goods from custom to my warehouse
    d. Time taken for unpack, take out , count, inspect and put for use (GR processing time)
    Do I need to use user Exit?
    Thanks
    Edited by: Daimos on Apr 27, 2009 6:52 PM

    Dear dogboy.
    I think we must use feature on the PO Confirmation Control (CC) Key at PO Item Level:
    ED - Estimated Time of Departure from Overseas Port.
    EA - Actual Time of Departure from Overseas Port.
    EA - Estimated Time of Arrival
    AA - Actual Time of Arrival
    And the purchaser will maintain the value of each of the CC Key each time they are notified by the vendor.
    And we need to come out with a Customised Report to capture those CC dates entered so that finance is able to prepare $ in advance if the moment the EA is maintained, meaning the estimated date of arrival at the Custom there.
    But the problem is that PO User Exit is only at the header of Confirmation Control Key but not capture the DATE field we entered for each CC.
    That was the problem I last encountered.

  • New Users!  Need best settings for Import

    I have just installed FCE 4. I have footage on MiniDV (1080i) as well as Canon 5D Mk 2 footage at 1080p (30fps). I want to edit these together. What settings are recommended for import.

    There is no good solution for your media. You need to set HDV 1080i60 to capture the HDV media. That media is 1440x1080 interlaced. You need to convert the Canon EOS material as it uses H.264 which is not a production codec, but one designed for delivery. You can use MPEG Streamclip to convert it to QuickTime using the Apple Intermediate Codec.
    Here's your next problem you can convert it to 1440x1080 at 29.97fps, in which case it will match the HDV material and not need to be rendered in FCE. Or you can convert it to it's original format 1920x1080 at 29.97fps, but then you'll have to render in the FCE sequence. In either case the audio should be converted as uncompressed stereo 48K. Never heard of 42K. No idea why of earth Canon decided to to do that.
    In FCE you can set your sequence item properties to have no field dominance. This will prevent interlacing your material that's not interlaced. The interlaced material of course will remain as it is.

  • VAT ON CAPITAL GOODS,

    Dear EXPERTS,
    I am using  condition type  JVCD  AND  JVCN    for  calculating  tax on capital goods  purchase,  I have maintained condition type JMOP & JMXI.   The  Excise base value is calculating fine, but  VAT is  NOT calculating  in PO,  Please suggest me what setting i have to  do,
    W\ith regards,
    ARABBAS

    Hi
    first check the all conditions assign with pricing procedure.
    check tax code assign with co code and for vat condition type created the condition records or not ?
    check the validity periods of condition records.
    laxman

  • Procurement cycle of capital goods

    all gurus,
    can u pls let me know how to procure and take part 2 entries of capital goods
    thanking
    ujwal

    Hi,
    Procurement Cycle of Capital Goods: -
    Domestic Purchase of Capital Goods: -
    1. ME21N u2013 Create Purchase Order
    2. ME2N u2013 List of Purchase Orders
    3. MIGO u2013 Goods Receipt against PO
    4. J1IEX u2013 Post Excise Invoice
    5. J1I7 u2013 List of Excise Documents
    6. MMBE u2013 Stock Overview
    7. MB51 u2013 List of Material Documents
    8. MIRO u2013 Enter Vendor Invoice
    9. MIR5 u2013 List of Invoice Documents
    Import Purchase of Capital Goods: -
    1. ME21N u2013 Create Purchase Order
    2. ME2N u2013 List of Purchase Orders
    3. MIRO u2013 Enter Customs Invoice
    4. J1IEX u2013 Capture Bill of Entry
    5. MIGO u2013 Goods Receipt against PO
    6. J1IEX u2013 Post Bill of Entry
    7. J1I7 u2013 List of Excise Documents
    8. MMBE u2013 Stock Overview
    9. MB51 u2013 List of Material Documents
    10. MIRO u2013 Enter Vendor Invoice
    11. MIRO u2013 Enter Clearing Agentu2019s Invoice
    12. MIR5 u2013 List of Invoice Documents
    Note: - This includes Reports along with Transactions.

  • Partial qty MIRO and GR for import PO

    Hi,
      For import PO first we are creating PO for vendor and we enter only qty and 0%  tax for import PO  after getting material as per schedule qty we are creating new PO for the recieved qty only and we are adding all the custom condition as delivery cost in second PO then we process further like MIRO  and GR ,  but to avoid this we are trying to make only one PO on import vendor and adding all the custom codnition in that PO in development server and we process the MIRO, J1IEX, and GR process for partial qty for one material and for one material we have taken ful qty. first time it works OK  ,  now when second time we want to do MIRO , J1IEX and GR againt same PO we are facing probelm like In MIRO when we enter PO number it is showing some amount in Balance amount filed which is generally 0 ,  in MIRO it is also showing the some material for which no open qty and also for partial qty if we enter qty more than open po qty system is not giveing any error,
    Can you some stpes and tips  what configurationwe need,  actual requirement is we want that we will create import PO o etime by adding all the custom condition as delivery cost and ref. to that material we want to do MIRO, J1IEX and GR  for partial qty.
    regards,
      zafar

    Hi,
      I have two points,
    While after  recieving import material first we do the miro for custom condition in this we enter the custom vendor code in the invoicing party, and below next to PO number field we generally select option no. 3 i.e Goods / service item + planned delivery cost with this all conditions come in the miro but our requirement is only those codnition should come in which invocing party is which we have enter in the header fied of MIRO ,
      so insted of 3 option Goods / service item + planned delivery cost ,  if we select option 2 Planned delivery cost our problem get solve so i want to know what is the effect if insted of 3 option we select option 2.
    regards,
      zafar

  • Import PO Secess dot get post (for capital goods)

    1)     created import PO(capital goods material)
    2)     capture excise
    3)     Made GRN
    4)     Post excise invoice
    when post in J1IEX, and simulate, Secess dont come. remaining all comes
    ex
    CENVAT OH     S Debit     719.87
    CENVAT on CG-ADC     S Debit     619.45
    CENVAT on CG-BED     S Debit     698.75
    CENVAT on CG-ECS     S Debit     13.98
    Unappl cstm-CVD     H Credit     2,052.05

    Hi
    In following path check
    SPRO-Logistic general-India-account determination-specify Excise account per excise transaction
    here for CAPE RG23 AT1 account should be there for debit
    Regards
    Kailas Ugale

  • Additional Excise duty credit to be taken in current year for capital goods

    Dear All,
    I am using SAP 2007 B PL12. My client buys capital goods where BED + Additional Excise Duty is also there. Now the client wants that credit of 50 % of BED should go to next year but credit of AED should be taken fully in this year. How to configure the above scenario in SAP 2007 B PL 12 as i have configured the capital goods on hold % as 50 % in GL A/C Determination. The system automatically passes 50% of all CENVAT type duties on capital goods to the on hold a/c.
    Regards,
    Rahul

    Hi,
    I have raised this issue to SAP support but they say that they need to do some more research into this.
    They have also suggested passing JE. But the issue with JV is that it show up as a separate line in RG 23C Part II register which is not acceptable to most of the clients. Plus the excise no. changes.
    Regards,
    Rahul