PLanned order and PO item for a same material in MD04

A material with Procurement key as F.
In MD04, There is a planned order for 8657 nos. for a material..
below that there is a Dep Req XXXX
Below that there is a purchase order for 8657 Nos.again.
My question is if there is a open PO for the material,then why is the planned order created for the material.
The PO reads as
04/05/2012-POitem--- 4500016092/00050 04/09/2012 15----
8657
THe Planned order reads as PLdOrd----0000478483/stpo--
8657
Please help me out..

In MD04,planned order and dependent requirement dates are 2/4/2012
whereas the PO date is 5/4/2012.
Inside the planned order the order finish date is 30/3/2012
and inside the PO the delivery date is 2/4/2012..
Its bit confusing..can you help in this..
ANd for your information,the Planned order is now not found in MD04,it was there yesterday..

Similar Messages

  • Planned Order and Purchase Requisition for total Plan

    HI
    As per my client requirement whenever i am giving a plan in Demand Management in MD61 say for quantity 100. System should create purchase requisition for quantity 40 and Planned Order of 60.
    Please let me know if it is possible.
    Regards,
    Anand

    HI
    Thanks a lot. Its working with quota arrangement.
    Regards,
    Anand.

  • Multiple line items for the same POs in MD04

    Hi,
    There is Purchase Order created for a material with other 5 line items.
    When checking MD04 for a material it is showing multiple records with the same Purchase Order and the corresponding item number in the Purchase Order correctly, but with different quantities in each line in MD04 randomly.
    I am unable to understand the reason for this strange behaviour.
    Thanks
    Ramakanth
    Edited by: Ramakanth Y. on Jan 20, 2009 4:04 PM

    No.
    But if this is a must requirement, you can do an elaborate check during order save in ORDER_SAVE BAdI and return error. So, it will be only during order save.
    Eawar Ram
    http://www.parxlns.com

  • In MIGO two seperate entry for the same Material in Accounting Document

    Dear Expert,
    Hi
    Business is doing stock transfer transaction. Here with reference to stock transfer PO when business is doing Goods Issue.
    here there is two stock transfer PO.  in one PO there is two line items for the same material. in the second PO again same material with two line items.
    but at the tme of Goods issue it is showing two seperate line for same material stock account credit in accounting document. but in the other Goods issue with reference to second PO it is showing only one line for inventory account credit in the accounting dcoument.
    so pl. guide me on this.
    thanks
    H shah

    Hi,
    Step 1 : First we create the Stock transfer PO.
    Step 2 : Goods issue with ref to above stock transfer PO ( Movement type 351) - MIGO
    Step 3 : Goods Receipt with ref to above stock transfer PO ( Movement Type 101 )- MIGO
    Thanks
    H shah

  • Difference amount in sales order and billing document (For one line item)

    Hi Experts,
    User created sales order with 3 line items and billing document. but problem is that there is difference in value of sale order and billing only for line item 10. The remaining items values are same in sales order & billing doc.if I check in sales order condition I found that VPRS condition is used and the value is 692.13and the amount is 3245.26in sales order. But if suppose I check the same value in billing doc the value is 0.69 and the amount is 3245.28. Can u suggest me which configuration I have to check for this.
    I also checked change lock but there is no change in sales and billing document & Material
    Regards
    Sunina agarwal

    Morning Sunina
    Now consider this scenario
    Item a - 10
    Item b - 20
    Item c - 30
    and the validity of condition rec for item C is 31st of Jan
    after 31st JAN the record changes or there isn't any.
    In Copy control the pricing type is 'B' i.e., carry out new pricing.
    Now if the document is created in January it will take all the above prices. and this document is then billed in Feb. Now the copycontrol, whilst copying the prices, will predetermine the same.
    Now your task is to check if there was user intervention, check the pricing in order and check what condition types got affected in order and in billing.
    If your scenario is still not amongst the above cases...
    I don't know what to do, if you figure out please let us also know, god know when we would face the same scenario....
    Take care

  • Same material can exist on multiple line items for the same order.

    Hi
    Is there any specific customising setting or web shop setting through which we can restrict user to add same material on multiple line items for the same order ?
    Regards

    No.
    But if this is a must requirement, you can do an elaborate check during order save in ORDER_SAVE BAdI and return error. So, it will be only during order save.
    Eawar Ram
    http://www.parxlns.com

  • Creating Planned orders and Requisitions for a particular MRP controller and for all the others only Requisition is to be created.

    Hi Experts,
    Currently we run Program 'RMMRP000' as a batch job to create Planned orders and requisitions.
    The client wants that Planned orders and Requisitions should be created for a particular MRP controller and for all the others only Requisition is to be created.
    I implemented Exit 'EXIT_SAPMM61X_001' in the following manner by passing MRP controller to user_key.
      IF mt61d-dispo <> user_key.
        no_planning = 'X'.
      ENDIF.
    But as you can see that this will not meet my client requirement.
    If any of you has worked on similar requirement / if any one knows that this is achievable or not,
    please share your inputs.

    Moved from SAP ERP Sales and Distribution (SAP SD) to ABAP Development
    G. Lakshmipathi

  • How I can get the Billing Type for the sales order and its items

    How I can get the Billing Type for the sales order and its items. I mean from which SAP tables and how?

    Hi,
    You need to use two tables.
    First use VBFA. Enter the sales order number in the field Predecessar and the value M in SubCt field. This will give all the billing document number for the sales order items.
    Then use the billing document numbers in table VBRK, where in you can get the billing document type.
    Regards,

  • How BOM and routing is selected for Planned order and Production order?

    Hi,
    Can any1 plz tell me how BOM and routing is selected for a planned order and production order. ?

    Hello Mathisuthan,
    BOM and Routing selection for the planned order and production order through production version, If u have more than one BOM and more than one Routing then u can maintain this information as Production Version in the system.
    Production version you maintained
    MM01/MM02 -- MRP4--- Production version
    Or you can create Production Versions in Mass also with Transaction Code "C223"
    In the case no production version maintained/created  for the material, then system by default  will pick the first BOM and routing.
    I hope this information helpful to you.
    Regards
    Umesh Mali

  • Delta update for Cube :  0CRM_PRI  - Service Orders and Confirmations: Item

    Dear experts,
    For Cube : 0CRM_PRI  - Service Orders and Confirmations: Item
    Source data is from Two ODS 
       1. Confirmations (Item Data)  : 0CRM_CNFI and
       2. Service Orders: Item Data : 0CRM_PROI
    I have done Init upload to this cube from both this ODS.
    I am not getting delta option to this.
    When I am trying update Delta after init from ODS message is No new deltas in DataStore object 0CRM_PROI for update. No delta option available . It is showing  Initial and Full Update option only.
    How i can initiate delta option for this Cube ?  Please update us.
    Thanks in advance.
    Regards,

    Hi,
    you can use DTP's to laod data from ODS to cube .. it will take deltas ..
    With a data transfer process, you can transfer data either in full extraction mode or in delta mode. In full mode, the entire dataset of the source is transferred to the target; in delta mode, only the data that was posted to the source since the last data transfer is transferred. The data transfer process controls delta handling and therefore allows you to fill several targets with different deltas from one source. With a data transfer process, you do not need to explicitly initialize the delta method as you do when copying data with an InfoPackage.
    or you can create a sepeate Ip for delta apart form full and init .. that will laod delat data in cube ..
    Regards,
    shikha

  • Planned order not getting generated for FG

    Dear Experts,
    Planned orders not getting generated for the Finished Goods - X which is having MRP Type M0 - MPS fixing type strategy group 20 which is copied fron another FG - Y , its a new product and production plan has been updated through MC88 - Rough cut planning but the planned orders are not getting generated.
    And for the material valid production version exists with selection method 3 and individullcollective as 1.
    Please let me know what might be the possibalities and what all the key fields i need to check.
    Thanks & Regards,
    Sampath
    Edited by: sampath s on Jul 13, 2011 11:31 AM

    Dear,
    In general MPS is run for High value items ( if you use like Gold , Platimum or A class items. ).
    Always only single level is used for Explosion and planning. then only you can analyse the requirements at each stage before procurement.
    Otherwise if you run MPS to multi level, Bottom most high value will be procured without any notice to authorities. Even you may cancel the process in mid way. At that time what will happen to the procured high value material.
    So for that purpose only single item single level MPS concept is evolved.
    Fo that you run MPS at single level so that only for the first level MPS will be carried out.
    Check and revert back.\
    Regards,
    Alok Tiwari

  • Planned order and purchase req

    Hi,
    I have created a planned order and a pur req for a product in APO
    The ava date for the plnd order is 28.02.2011 and same for the Pur req
    The GR processing time was earlier 3 days when the proposals were generated . Now I  see that the user has changed to 1 day in R/3
    So there is a diff in the ava date for the planned order and the pu req in APO and R/3
    In APO it is 28.02.2011 and in R/3 it is 26.02.2011.
    I am able to see this in the CCR
    Does this mean that the proposals on getting CIFF'ed to R/3, have picked the new GR processing time from R/3 and adopted the new availablity date in R/3
    for this to happen, is a BOM explosion required again or just the CIF of the proposals to R/3 will do or anything  else is influencing this activity?
    kindly explain
    Thanks,
    SS
    Edited by: SAPSriman on Feb 24, 2011 10:45 PM

    Thanks.  SS

  • Link between Planned Order and Purchase Requisition

    Hi All,
    Is it possible to track a MRP planned order from the Purchase Requisition to which it was converted (using MD04 or MD14)?
    And is it possible to track a purchase requisition based on a planned order?
    Is there a clear connection - in DB tables - between MRP planned orders and different Purchasing documents - RFQ, PR, PO?
    Thanks in advance,
    Eytan.

    Hi Eytan,
    see some corrections for your understanding
    So, although it is not possible to track that connection, once you delete the PR that was previously created for the Planned Order, that same planned order becomes available again, and again you can convert it into a PR.
    not possible to come again same planned order once you deleted purchase requisition, system will create new planned order during after next MRP run for this requirement
    pls reward points and close this thread.
    Regards,
    Sankaran

  • Sales Order and Sales Item not copy over to table AFPO-KDAUF and AFPO-KDPOS

    Hi Expert,
    May I know why I run MRP and convert planned order to production order based on Sales Order, why the sales order and sales item is not copied and save in table AFPO-KDAUF and AFPO-KDPOS?
    I can see the sales order and sales item is appearing in MD04, but how is the linkage between production order and sales order/item?
    Thanks.

    Sales order No. and sales line item will only be transfer to production order in MTO ( Make to Order) scenario.
    If your scenario is MTO and the sales order reference is not getting  transfer, then check your requirement type and  requirement class setting in T.Code OVZH and OVZG.
    In standard SAP 'KE' requirement type  40 requirement class is used  for MTO scenario.

  • Firm Planned Order and receipt.

    Dear Master,
                         Here i am working on LTP or PP-PI industry but i am enable to understand meaning of Firmed Planned order and
    Frim Receipt pl tel me some differeinated point with sutiable example? also tel what is purpose of both.I want exact concept
    of frimed planned order and firm receipt. Pl give me your feedback early.
    Regards
    Ravi

    Dear ,
    Firmed Planned Order : It is used when you don't want certain planned orders to change during subsequent MRP runs.
    Say today you have created certain palnned orders. In a normal scenario, when you do the MRP run again, the planned order may get changed if the requirements have changed. However as a normal business practice, it is not desired to change the production plans everytime there is a change in the requirement...especially in the immediate future (maybe a week or so).
    We set this as the planning time fence depending on the MRP type settimg in the material master, you may have firm orders.
      Apart from MPS items, MRP will also generate firm planned orders for materials with MRP type P1 to P4. In addition to the above, any planned order that is manually changed is also firmed.
    Look in to Check MRP Type  in SPRO-MRP-Firming Indicator  and press F1.
    Firmed Reciept : Purchase Order , STOs, Production Order which are reciept element and adding stock to existing stock -unrestricted .
    Hope this  gives you some idea
    Regards
    JH