Hi,
Recently our SCM system was upgraded from SCM 4.0 system to SCM 5.0. After the upgrade I find in /sapapo/msdp_admin the planning areas in status red with message "No initialized Planning Version(s) exists". If I check the planning area it says "No errors found when checking the planning area".
Please help. How to initialize a planning version. I am new to SCM.
with regards,
Mohan.

Hi,
Thanks Mikhail.
When I try to Create Time Series Objects for a Planning Area from /sapapo/msdp_admin
I get the error "Master planning object structure 9ADPBAS is inactive".
Then I tried to activate the planning object structure 9ADPBAS from /sapapo/msdp_admin but I get "Error occured during activation". I do not find any log also. The long text shows as below.
=============================
Error occured during activation (see log)
Message no. /SAPAPO/TSM154
Diagnosis
An error ocurred during activation.
The planning object structure has not been activated.
Procedure
For detailed information, see the corresponding log; a log is only created if logging has been switched on. You switch on the application log from the main screen for editing planning object structures under Extras -> Log on/off.
=============================
ow to activate these structures and also how to activate the log for it ?
Please help,
with regards,
Mohan

Similar Messages

  • "no active plan version exists" while adding system in partner profile

    Hi,
    i am getting "no active plan version exists" while adding logical system in partner profile. while duble click on this it showing "set active plan version".
    Can anyone answer me how to do the set active plan version. I asked my functional team and  they didnt know how to set it.
    Thanks,
    Gowthaman.

    Thanks Sonia,
    in OOAP i could not able to edit so i maintained plan version in OOPV and in sm30 in table T77S0 maintained PLOGI group.
    Now i am getting different error while creating partner profile in we20..
    *Object type US, ID CENTRALADMIN unknown (please observe upper/lower case)*
        *Message no. E0624*
    *Diagnosis*
        *Object CENTRALADMIN of type US is not known in the system.*
    *Procedure*
        *Enter a valid object and check the type.*
        *Make sure upper case and lower case are used correctly.*

  • Error while copying the planning version : "S001 001 doesn't exist in P44V"

    Hi Leads,
    I am trying to copy the planning version for S001 (Version - 001), from the Transaction MC8V. But, it is giving error sayin "S001 001 doesn't exist in P44V".
    How can I solve this issue.
    Please do suggest.
    Thanks,
    Sandeep

    Check this thread
    [Re: SOP Confituration- Maintain Copy Profiles version A00 not maintained   |SOP Confituration- Maintain Copy Profiles version A00 not maintained;
    thanks
    G. Lakshmipathi

  • Error While copying the Planning version : S001 001 doesnt exist in P44V

    Hi Leads,
    I am trying to copy the planning version for S001 (Version - 001), from the Transaction MC8V. But, it is giving error sayin "S001 001 doesn't exist in P44V".
    How can I solve this issue.
    Please do suggest.
    Thanks,
    Sandeep

    Check this thread
    [Re: SOP Confituration- Maintain Copy Profiles version A00 not maintained   |SOP Confituration- Maintain Copy Profiles version A00 not maintained;
    thanks
    G. Lakshmipathi

  • Copying transaction data between planning version - Not delete existing dat

    Hello all.
    I made copy from one version, like 000.
    The result is Version A1 and A2. I copied everything(Master Data and Transaction Data).
    For each version, i ran a MRP. But in differents periods. Like October and November.
    After MRP, i have a lot Planning Orders in A1 and A2. But in differents months.
    My question is: I want to merge A1 and A2 in another version(Merge only  Planning Orders). How i can do this?
    Using /SAPAPO/MVM or /SAPAPO/VERCOP i can copy all data from source to target. But always delete previous data.
    Thanks
    Best Regards.
    Marcelo

    This isn't the answer you WANT to hear.   But there's no way to my knowledge to achieve your requirement using standard version copy functionality in APO.
    One way to preserve the data for alternate / merged versions that I've found useful is to use the /SAPAPO/REL_TO_OLTP transaction to send volume data to the ECC client.  If you are loading both inactive versions to BW, then you should be able to release that data from BW to ECC inactive/"long-term" simulation versions where it can be aggregated.  That is to say, you could send A1 and A2 separately and they will simply add to one another, not overwrites (delete and re-create).
    This being said, requirements using this transaction are sent as planned ind. requirements in ECC.  This may not be the desired outcome that you're looking for, so you might have to be careful which key figure you send to represent volumes.

  • HOw to set our Existing Active plan version to The new Created Client.

    Hello experts,
    I  have create two new Clients for idoc processing .
    But when i am creating partner profile for my Model View  the system  gives an "error that no active plan version exist."
    is there any way to solve this problem ????
    Regards,
    Dakshaini.
    Moderator message: only one thread per issue, please.
    Edited by: Thomas Zloch on Oct 14, 2011 3:43 PM

    Please try uncommenting the following line in your method call.
    * IS_PRINT = GS_PRINT
    Regards,
    Rich Heilman

  • Tcode KEFC and message:"Plan version is not supported"

    Hello all,
    Please is someone aware of solution for this situation:
    - I upload with tcode KEFC forecast datas from excel file in CO-PA
    - receiver records are created with errors
    - when I check for the errors system tells me that "Plan version is not supported, diagnosis : Plan version "0" has not been created in operating concern "1000", Procedure: Transfer version "0" to operating concern "1000" and maintain the attrributes for that version"
    - my concern is that when I check in customizing Planning, Initial Step: display view settings in operating concern details the version "0" is existingin the operati,ng concern "1000"
    So do you have a solution for this issue?
    Thanks and best regards
    JCO

    Hi Sudhakar,
    Thanks for answer but version "0" is tickled for Plan Actual, WIP and variance and I don't understand what to do about KEPM.
    Best regards
    JCO

  • INVALID PLANNING VERSION error

    Dear All,
    When i try to log into planning book ,i am getting an error INVALID PLANNING VERSION(Time series still existing). What could be the problem ,can any one help me out.
    Regards,
    Chetan.

    Hi Chetan,
    Have you tried to reinitialize the Planning Area?
    Data will not be lost if you reinitialize. Try doing that.
    Regards,
    Raghu Kishore

  • Planning version

    there are one new cost center has been added into a existing cost center group and when we are trying to pull one report s_alr_87013620 and putting a planning version 0 and planning version BI , output of report in 0 version is showing all the cost center where as version BI is not showing the new cost center in the report.I have checked it in kSB1 report for new cost center there is no any line item present. 1)what can be the reason that two version is not showing the new cost center and
    2) what is the logic,   3)how it can displayed.
    Edited by: SDeepakKr on Jul 29, 2010 2:09 AM

    Hi,
    you could check, whether the indicator 'print zero rows' is deactivated in the report layout.
    Execute the report, go to Menu: Settings/Report Layout/Rows
    You can only use this indicator for those rows where the zero values result from the read data.  If you want to print all report rows, irrespective of whether posted data exists, you should set the Form printout indicator.
    If you use a section layout, then check the settings for 'print zero rows' in that too.
    Regards,
    Greta

  • SAP - Cost Center Planning - Version 1

    Dear All
    Recently we have started to use the cost center planning through KP16 under plan version -1
    However we are unable to down the plan data in excel with a cost center break up through KSBP report.
    We are not using any special ledger
    System is showing the following error
    No plan cost line items recorded.
    Message no. KB419
    Diagnosis
    No planned costs line items are written to controlling area DXES in version 1 of fiscal year 2009.
    System Response
    The report cannot be executed.
    Procedure
    Check your selection criteria or activate the line item update function.
    Note
    The line item update function is controlled depending on the application:
    Cost center planning
    Here you can define the update for each version and fiscal year. You can maintain the corresponding indicator (integrated planning) in the version maintenance (settings for the fiscal year).
    This indicator you can either
    set manually when creating a version or
    set later via the menu sequence "Planning -> Planning aids -> Integration active".
    Regards
    Anilkumar

    Hi,
    The impact is that the planning is stored also as line items and the planning is integrated between the CO-PCA components. In SAP words:
    - All available plan records for controlling area/version/fiscal year are posted as line items. The R/3 System posts these line items to the AC interface.
    - Any existing line items in the plan allocation transactions (plan assesment, distribution, or accrual calculation) are posted to the AC interface as well and made available to other components.
    Regards,
    Eli

  • KP98 - Actual Prices do Not copy to plan version

    Hi everyone,
    I'm attempting to do a KP98, so that I can have a copy of  my actuals in my plan version. The transaction works fine in copying everything I selected, however when I check my activity prices using for example Tcode KSBT, it does not show me me any prices for my activities.
    In other words my activity quantities are successfully copied into my plan version, but NOT the prices.
    In version '000' prices exist, but not in my plan versio '100'. Any ideas?
    Am I missing something?
    Thanks.
    Edited by: Ehab Mansour on Jun 23, 2009 10:22 AM

    Hi Ramesh,
    So if I understand you correctly:
    Even after setting the "Price" and "Activity Qty" flag in KP98, it doesn't actually copy the price from version 000 to my plan version 100. I still have to run KSPI to get my price posted in my version 100?
    If that's what I understand correctly............... then what's the benefit of setting the "Price" flag in KP98? That's what I'm trying to understand.
    Of course if I change my planned values then I have to run KSPI again to calculate the new price.
    But if I just do a KP98, WITHOUT making any changes to my planning in version 100, should KP98 just copy the prices from my actuals, and I would only need to run KSPI again only if I make changes to my planning dollars?

  • Planning Version Mgmt

    Hello Gurus -
    I have a few questions in planning version management. Appreciate if you can help me out.
    <b>Scenario</b>: I have some planning data in the active version 000 and I have used "/SAPAPO/VERCOP - Copy Planning Version" to create a new version 001. Now I have the same data in both 000 and 001.
    Then I went on to change some planning data in 001 to do my what if analysis and I arrived at a final plan which I want to see in 000.
    Question: How do I do this? Since we cannot just copy it back to 000. Do we have to replan it in 000? Or do I have to delete the existing 000 and then copy/create 001>000? How is this normally done?
    Appreciate your help!
    Varun

    Thanks Harish -
    I am copying order series data, so I would be using the merge functionality. However the help document says :
    <i>SNP orders are not permitted to be published directly into the SAP R/3 system. Communication with the SAP R/3 system is only permitted to take place using the Production Planning and Detailed Scheduling (PP/DS) component. The system performs a technical check of the corresponding Customizing for this.
    It is not permitted for any releases to be made into or out of SNP until all the planning versions that came from an active version have been copied back into this active version</i>.
    AND when I tried to copy my simulation version results back into the active version, system does not let me do it and gives a message "<b> Function not possible because of transfer to OLTP systems"</b> and says I should try avoiding transfer to OLTP system.
    But I do need to transfer the Preqs(both SNP and Deoplyment and POs from TLB) to R/3 and my SPRO settings for " Configure Transfer to OLTP System" is setup in such a way that I transfer all output of SNP/DEP/TLB to R/3.
    Any idea what could be done here?
    Thanks a lot..
    Varun

  • Plan Version - FI/CO

    Hi,
    I am relatively new to FI/CO. I have some queries with regards to version.
    1) What is the significance of version? Are version and Plan version synonymous
    2) With respect to plan cost there is something called plan version.Does actual cost have something similar? Does budget have something similar?
    3) If the answer to Q.2 is 'NO', then does make sense to use 'plan version' to actual costs/budget. Does SAP provide this logic.
    Could someone provide me some link/documentation regarding the above mentioned issues.Mail them to [email protected]
    Regards,
    Roshith

    Actual version is zero. The plan version is mapped to
    actual in config. there is only one actual version. You can have many plan versions. This allows companies to be flexible to change the plans as needed. Your reports can then be set up to run against the plan version you designate. Version 1 maybe set up a the start of the year. Version 2 could be set up later based on new information. Here's some documentation on version in the IMG for FI.
    POINTS ASSIGNED are appreciated
    The same concept holds true in CO but the plans are entered independently.
    Define Plan Versions
    You can define plan versions in this activity. You have the option of posting planning data from each fiscal year to an unlimited number of versions.
    Example
    You can define several versions of your annual budget plan and base each version on different conditions. You can also create several versions for your financial reports, whereby each report is based on different sales revenue.
    Activities
    1. To create a new plan version, choose New entries. You can also change an existing plan version.
    2. Enter 0 in the column Ld (Ledger). This is the general ledger, and is the only ledger in G/L Accounting where planning can be undertaken.
    3. Enter the key for your new version in the Ver column.
    4. Specify how the planning data is to be posted:
    a) If you want to plan data manually for the specified combination of ledger and version, select Man. plan.
    b) If you want to transfer the data from the Overhead Cost Controlling (CO-OM) or Profitability Analysis (CO-PA) component for the specified combination of ledger and version, select Plan Integ.
    5. Enter a name for the plan version.
    6. Save your plan version.

  • Evaluation Path and Plan version

    Hi Experts,
    Can anyone please help me understand the concept of Evaluation Path and how the Evaluation path and the plan version settings are used in real time scenarios.
    Thanks,
    Sindhu.

    Hi,
    See, a reporting structure, staff assignment, organization structure are all evaluations paths themselves. The relationship between objects is defined.
    A lot of standard evaluation paths exist. But in case you dont have the path which meets your requirement you create a new one.
    Suppose you want to find out which all Tasks are linked to a job which is linked to a position which reports to an Org Unit
    so your evaluation path will traverse Org unit then position then the job then the tasks assigned.
    A relationship between an object is also a evalution path
    hope this helps
    Ajay

  • Simulative planning version : problem

    Hi ,
    I created Planned independent requirements for a material Called "TestA" in sap r/3 and moved to apo.I am unable to veiw my requirements in my own simualtive version.so i done /n/sapapo/vercop and maintained all tha parameters like category and planning area, materials, location etc and executed the transaction.It is displaying the message that " Target version already exists . should it be  overwritten". they are 3 options. 1) yes . 2) No 3) cancel.If i execute NO and cancel , the transaction is not executing. so i choose Yes , the system is deleting all the previous planned material which are executed in SNP . so I am unable to see my REquirements in /n/sapapo/rrp3.what shall i do?.
    second time i created  Planned independent requirements for a material called "Test B" in SAP R/3 and moved to APO. I DONE THE SAME PROCEDURE what i explained before.Now i am unable to see the requirements for material "Test A " which is planned in SNP HEURISTICS IN BACKGROUND. Totally orders and stocks are overwriting, if i execute the Trnasaction /n/sapapo/vercop . please help me how to rectify this error

    Hi Alper Myumyun ,
      I used the report /SAPAPO/VERSION_COPY_TRANS.a gain the same problem occuring.do u have any idea gow to rectify this.why it is not execting when i press NO. If i press YES, why it is overwritting the other material numbers forecast. do u have any idea.
    I am doing some proto typing work. I have to move Planned independent Req from sap r/3 to apo for testing .once we cif the planned independent req from sap to APO ,why i am unable to view the Forecast in rrp3  .WHAT IS THE PROBLEM?

Maybe you are looking for

  • Albums in the "Pictures" app

    how do I create albums in the "Pictures" app to organize my photos

  • When I save connection object I get the following error

    An exception occurred that is explained in detail below. The exception, which is assigned to class 'CX_SY_DYN_CALL_ILLEGAL_FUNC', was not caught in procedure "OPEN_FI_PERFORM_PM000070_E" "(FUNCTION)", nor was it propagated by a RAISING clause. Since

  • Help : Flash Media Encoder and Dazzle

    Can some one please help me with this. I bought a Dazzle usb capture card but FME won't allow it to work. I keep getting error messages saying "Video format provided by capture device is not supported by this application." Any ideas on how to get aro

  • How do you burn multiple folders to disc?

    I couldn't select them all at once, so I burn the first folder and then tried to add more, but I can't figure out how to do it. File > Burn to disc doesn't seem to work a second time, nor does clicking and dragging the folder onto to the disc drive i

  • [Solved]Archive Manager 3.14.1 won`t open RAR5 archive

    Hello again Today I make a RAR5 archive for testing if Archive Manager can open, but he cant. In vbox I have Ubuntu 14.10 and use Archive Manager 3.10.2.1 an can open archive. How repair this bug on 3.14? I use LXDE, file-roller for pcmanfm. Tks Last