Pre operative exp. of a WBS cost object

HI
I am looking for a soln to following issue.
1. In case of an Investment project under PS whether all the  pre operative expenses and issue of project material to a WBS including turnkey items are going to be first debited to a cost element( part of P&L item) and then settled periodically to a CWIP.
2. If yes, then till the time you settle  a WBS, the value of expenditure will appear in Profit and Loss Account of the company or Profit center.  
3. Is there any way to book the pre operative exp. to a WBS as a Balance sheet item and then settle from there?
Regards
Nirmal

Hi, you can post to wbs as a Project stock(eg via MIGO), and then when capitalize post Good issue to an Asset

Similar Messages

  • Cost Object in FI document with WBS Settlement

    Hi,
    I'm testing WBS settlement to G/L account which is cost element. I made some substitution rules because I met an error message saying that "Cost Object is needed"
    As a result I can settle WBS to cost elements such as COGS etc. I got a FI document, CO document and PCA document. Everything looked so nice.
    Suddenly I noticed, however, that there is no such a thing like cost object on FI document. When I look up the FI document using FB03, I found that the PS-POSID was empty. Of course, CO documents have Cost Object.
    What I wonder is as follows
    1. Is this standard? Is it natural that FI document with CO doc has no cost object on it?
    2. If I need to use FI document to determine WBS element, what is the best to way? Is it possible to enter Cost Object such as wbs element in FI document during settlement?
    Thank you for your kind advice in advance.
    Message was edited by:
            Namseok Kang

    Kang,
    In the message which you got, the word 'Cost Object' refered to a cost center, or order, or any other cost object.
    However, there is another account assignment object with the name 'Cost Object', which was not filled in the FI document. That is normal.
    Right now I don't have much information in the a/c assignment object 'Cost Object'.
    Regards,
    Vishal.

  • Validation Restricting Entry to One Cost Object

    I am trying to create a validation in GGBO to restrict postings of Vendor Invoices (KR doc type) and journal entries (SA doc type) to only one cost object (cost center, internal order or WBS element) on expense account lines.  I understand standard functionality limits posting to only one "real" object; however, getting the business to understand has proven difficult so I need a validation.
    I have the following in the Prerequisite:
    BKPF-BLART = 'KR' OR BKPF-BLART = 'SA' AND
    BSEG-HKONT >= '700000' AND
    BSEG-HKONT <= '799999'
    For the check I have tried numerous ways, but below is one attempt:
    BSEG-AUFNR <> ' ' AND BSEG-KOSTL = ' ' AND BSEG-PROJK = ' ' OR
    BSEG-KOSTL <> ' ' AND BSEG-AUFNR = ' ' AND BSEG-PROJK = ' ' OR
    BSEG-PROJK <> ' ' AND BSEG-AUFNR = ' ' AND BSEG-KOSTL = ' '
    Nothing is working and I am getting frustrated.  Any ideas?
    Thank you in advance!

    You should write it as below:-
    Pre-requisites:-
    ( BKPF-BLART = 'KR' OR BKPF-BLART = 'SA' ) AND
    ( BSEG-HKONT >= '0000700000' AND BSEG-HKONT <= '0000799999' )
    Check:-
    ( BSEG-AUFNR NE ' ' AND BSEG-KOSTL EQ ' ' AND BSEG-PROJK EQ ' ' ) OR
    ( BSEG-AUFNR EQ ' ' AND BSEG-KOSTL NE ' ' AND BSEG-PROJK EQ ' ' ) OR
    ( BSEG-AUFNR EQ ' ' AND BSEG-KOSTL EQ ' ' AND BSEG-PROJK NE ' ' )
    Message:-
    As you need.
    Regards,
    Gaurav

  • GL Account : Cannot be posted to cost object, please check your entry

    Dear All,
    I've problem in general posting or in FBCJ (cash journal) ....
    When I try to make journal  : Debit Expense  and Credit Cash in F-02 or in FBCJ then I chose Post an error appear " Cannot be posted to cost object, please check your entry " ..
    Because GL account "Expense" assigned to cost element, I need to fill cost object ... when I filled it with Internal order or WBS, the error appeared , but there was no error when I filled with Cost center ....
    For your info there was no problem with Field Status Group ( I thought ) cause I ticked with Optional entry for WBS and IO ...
    Beside it, I've assigned the company code in Controlling Area and Operating Concern ...
    Network in WBS was in optional
    Please give me solutions
    BR,
    David Sindhu
    Edited by: david_sindhu on Jan 26, 2011 12:06 PM

    Hi Alex,
    The posting key was 40 and there was no problem as I choose Optional ..
    My WBS was not statistical ...
    Any idea ?
    Edited by: david_sindhu on Jan 27, 2011 3:18 AM

  • UNABEL TO DO WRITE-UP FOR ASSET AS IT IS ASKING FOR COST OBJECT.

    Hi
    I am unable to do writ-up asset as error message is coming saying that cost element require a cost object assignment.
    But in asset master we have cost object assignment.
    I have checked my all configuration seems to be correct but i don't know why i am getting the erroe.
    Can anyone help me regarding this.

    Hi
    I am giving you the detailed description what error I am getting.
    Account 60210 requires an assignment to a CO object
    Message no. KI235
    Diagnosis
    You have not defined a CO account assignment for an account that is relevant to cost accounting.
    System Response
    Account 60210 is defined as a cost element.
    This means that you must always specify a CO account assignment.
    Procedure
    Enter one of the following CO account assignments
    Order
    Cost center / cost center/ activity type
    Sales order item (for a project or cost relevant)
    Project / WBS element
    Cost object (Process manufacturing)
    *Network/ Network activities*
    Business process
    Profitability segment
    Real estate object
    The posting row affected is 0000000002, account 60210.
    But in asset master we have done cost onject assignment.
    Waiting for quick response.
    Edited by: Smruti Mohanty on Nov 14, 2008 11:30 AM

  • Cost element report with cost object name column

    Hi,
    i'm looking for a report similar to S_ALR_87013601: Cost Elements: Breakdown by Object Type, but including a column with the cost object name. Does anyone know if such a report exists? If it doesn't exist, how can i create a report like this?
    Some of my company costs are assigned to cost centers and some of them are assigned to wbs elements. We would like a report where we could have all the information together.
    Thank you very much

    Hi Xavi ,
    Some of my company costs are assigned to cost centers and some of them are assigned to wbs elements. We would like a report where we could have all the information together.=>
    There is not standard report available..  which will display total cost per company code.. i,e cost booked on cost centers, internal order and WBS elements ... This is becuse each modules store data in seperate tables.
    You have to create a ABAP report to serve your pourpose. You have to collate all the costs booked in a company code for cost centers, IO and WBS elements . Pick up real costs only as per company code..
    We are using such custom report and its working fine.
    Regards
    Sarada

  • Cost Element Report for all cost objects

    Hello,
    Is there any standard SAP report where it can list down all cost elements, and their line item/total postings done to various CO Objects in one shot.
    We have CE/CCTR, CE/IO, etc, but if we can have one report which can list all cost elements and postings done via it to different cost objects - cost centers, internal orders, WBS, etc, might be very handy to us.
    Thanks
    Balla

    Hi Balla,
    Please use S_SL0_21000007 for your requirement.
    It gives cost element postings to different cost objects.
    regards,
    makrand

  • In VFX3,error is for GL requires an assignment to a cost object eventhough

    In VFX3, while releasing billing docu for Accounting  error is for GL40000000 requires an assignment to a cost object
    The below are Checked points :
    1.In OKB9 for this cost element  40000000 cost center assignments are there with Business area wise.
    2.Cost center Valid period is from 1.4.2007 to 31.12.9999
    in the begining  while releasing in VFX3, system throwed  error as that cost center  blocked for revenue postings,
    We deselected that check box(Actual Revenues in KS02)
    now the error is GL 4000000 requires  an assignment to a cost object
    Even though cost center assignments are there but why system is asking cost object  not able to understand.
    Please any one help me to solve this issue.
    Thanks

    Nope, no other ways.
    The cost center in question will receive a statistical posting - revenues aren't costs, and can't be carried in CCA as primary postings.  If they could, they'd be able to be included in rate calculation, allocations, etc, which is nonsensical.
    You'll have to have another receiver in CO that can receieve a real posting.  That's pretty much an internal order, WBS element, or profitability segment.  Profit center doesn't count; all postings to PCA are statisticial (PCA is a special-purpose special-purpose-ledger, if you get my meaning.)
    Two questions:
    1) Do you have costing-based CO-PA active in your system?
    2) Have you verified the business scenario?  Why do you want to record revenues in CCA in the first place?

  • Cost assignment-Multiple cost objects being selected by default from the EP

    Hi,
    I have created an expense report from the Portal and entered the cost object - a WBS element and saved the report. Now, when I check in table: PTRV_SCOS, it shows me the cost object assigned are - both - the WBS Element as well as the Cost center. This is incorrect as there should be only one cost object - either the cost center or the WBS element. However, when I book the expenses from the backend, it works fine. Only the WBS or cost center is displayed in the table mentioned above. Anyone has any idea as to why this is happening?
    Many thanks in advance for your efforts.
    Cheers guys.
    Hope to hear from you soon
    Best regards,
    Tanmay Dhingra
    Edited by: Tanmay Dhingra on May 17, 2011 10:05 AM

    Hi All,
    First of all, thanks for your responses..
    Right, about the issue, what I explained here was that I am indeed assigning only one cost object: the WBS element. The issue was that even though I am assigning only the WBS element, it was also assigning the cost to the cost center by default. I did some R&D and found the solution to the issue (I was also asked to look for OSS notes but was not satisfied that this issue needs an OSS note to be applied so tried my solution). The issue was in table: T788M (allocate costs to variable account assignment). Here, I created an entry and called it USERGROUP_2 (just a random name) and assigned the variable cost objects (only the WBS and the Cost center) to be displayed. In the next step, I assigned this usergroup to the country in quesion feature (TRVCO). By doing this, I tell the system that only these cost objects are to be considered when an employee wants to assign the cost object. If the system sees that there is no value from the drop down to choose from, it picks up the default cost object (cost center). This was a simple issue that I had to rattle my brains on... but the solution I mention above worked like a hot knife going through butter...
    If you guys face this issue, please try this else feel free to get in touch with me on my number below.
    Once again, thanks for your responses.
    Best regards,
    Tanmay Dhingra
    +91 880 6666 606

  • Splitting IVA by cost object at JVA

    Hi Experts,
    We´re finding difficulties when trying to split IVA in JVA (Joint Venture Accounting).
    We have an account/cost element for IVA (4601000017).
    When the invoices are generated from MM or FI and they have more than 2 cost objects (more than one line), ALL THE IVA has being generated at that account , BUT JUST has one object cost.
    We really need to split the IVA as many objects cost the posting has.
    I really hope for a help.
    We try that flag "split line" at GJZD (JVA setting) and we are also trying at OBCO (IVA setting).
    Do you have another clue?
    THANKS IN ADVANCE!!!

    Hi Kartik,
    I´ve found a manner to get the IVA splitted according the objects cost, as many cost objects the MM postings or FI Invoices have with Tax Code "taxable".
    It was a very peculiar/singular detail, even though necessary for this current rollout, in Bolivia (Petrochemicals Company rollout).
    I´ve applied RXD for this necessity, mapping the IVA accounts instead of Exchange accounts and solve this problem.
    Thanks for your help.
    Now I´ve been looking for a standard solution that save just (only one) document for JV Overhead (1 document per JOA).
    For example, I have a JOA "XPTO" and a lot of BI postings with a lot of Costing objects.
    I would like just one JV document for "XPTO" and I´ve been using GJ94 for Overhead operations.
    Do you have any idea if it is possible (standard solution)??
    Thanks a lot. If you could pass me your professional email, it would be very nice.
    Mine is "[email protected]".
    See you.
    Regards
    Dante

  • Please put a cost object with valid JV data for GL accoutnt (line 001)

    Dear All,
    When the user is trying to post ASKBN, They are getting an error saying "Please put a cost object with valid JV data for GL accoutnt (line 001)"
    So we tried to look up the error, and the WBS, Cost center, profit center and JVA details are all available in place. Still cant understand why this error comes. And why the system is asking to put JV details when they are available.
    On checking, WBS has an AUC and AUC has the cost center which has the JV details and PC details. So I think everything is in place.
    Can someone help please and let us know if we are missing anything else that needs to be checked ?
    Thanks,
    Hari Dharen

    Dear Hari Dharen,
    if something else in missung you'll get a error message if you run ASKBN in testmodus.
    regards Bernhard
    Edited by: Bernhard Kirchner on Oct 5, 2010 8:55 AM

  • Order Settlement to another B area cost objects

    Dear all
    In my requirement We are carrying the work at one Business area on behalf of another business area. The maintenance order has some expenses amount,after completion of the job i need to settle into another business areas cost objects. But sap is giving the error only. Is ot possible?

    Thenna,
    Message to all: you really should get an OSS logon - its free and would save us all a lot of time...
    However, this looks like a FICO issue... and here is the OSS Note text:
    During settlement error message KD256 is output
    "There are no accrued amounts; settlement is not possible".
    The error message and the long text do not supply sufficient information on the causes for the error message.
    Additional key words
    CJ88, CJ8G, VA88, KO88, KO8G, CO88
    Cause and prerequisites
    Preconditions for message KD256 are:
    1. The sender carries a results analysis key
    and
    2. it is
    a) a sender with revenue
    or
    b) a production order with FUL rule to product which in the settlement period has neither the status DLV nor the status TECO
    or
    c) a WBS element which does not have the status TECO
    or
    d) an order, which in the settlement period has neither the status DLV nor the status TECO, and the indicator 'WIP on dependent orders' is in the results analysis version.
    In these cases, only data from accrual calculation is settled. In the cases b) to d), no actual costs are settled to the receiver of the settlement rule.
    The error message is now output
    1. if no accrual calculation has been carried out,
    or
    2. the accrued data have already been settled
    or
    3. the flag 'Settlement to FI' has not been set in any of the results analysis versions
    or
    4. no posting rules have been defined for any of the results analysis categories.
    Solution
    1. Check for the cases b), c) and d) whether the sender already had the status GLV or TECO in the settlement period, that is, whether the delivery date or the date of the technical closure is prior to the posting date of the settlement. If this is not the case, the system continues to determine and settle in period WIP.
    Note: Prior to Release 4.0, the system did not update the date of the technical closure with WBS elements. This is why the date of the technical closure was not checked in Release 3.0/3.1. This was an error in Release 3.0/3.1.
    2. Check the settings in the Customizing of accrual calculation, that is, check the flags 'Settlement to FI' in the results analysis version and check the posting rules.
    3. Check the previous settlements for the sender. For this use the function 'Extras -> Previous settlements' on the initial screen of the settlement.
    4. If necessary, start accrual calculation for the sender again and start the settlement again afterwards.

  • Cost Objects

    Hello All,
    Can someone provide a list of all the cost objects.  I've been searching on the internet and SAP documentation  and can't find a list of what is considered a cost object.  For now here is my understanding of what are cost objects:
    Cost Center
    Internal Order
    Production/Process Order
    Sales Order
    WBS Element
    The reason I ask is that we have an "RV" doc type that posts to Primary Cost Elements.  In the line item detail there is a material #, Profit Center and a profit segment number from COPA.  I'm trying to figure out which one of those numbers is being recognized as the cost object. 
    Thanks in advance for your help,
    Moderator: Please, consult help.sap.com

    Hi
    Your list of CO objects is almost complete
    Just add profitability segment also to that list... So, in case of SD billings, the Prof segment that you are seeing is a CO object
    Regards
    Ajay M

  • Report Painter/Writer Ctr & WBS costs

    I think I've tried every possible variation to bring the appropriate CTR/WBS costs. Here's what I'm trying to do:
    1. See in one reprt both the CTR planned costs and the WBS planned costs where the cost center is assigned to the WBS as a responsible CTR.
    2. Added the characteristic "Import CTR Data" into either a row or general data selection as well as adding object types WBS, ACT, PRJ, and CTR.
    3. I can get the WBS to display as a line item with the planned costs, but when I do it changes the credit balance on the CTR to a positive value. This is after I run plan reconciliation for the CTR, and I have integrated planning turned on.
    Example:
    Postings:
    WBS Labor CE: $100
    CTR Labor CE: -$300
    Report:
    Total CTR LAbor balalnce $100
    WBS displayed with $100.
    When I remove the WBS and Import CTR Data i get the $-300 balance on the CTR. So I'm guessing it's not possible to bring these two objects into the same report to show the CTR over/inder absorption with WBS visibility.
    Any suggestions would be appreciated.
    Jim

    Cost center...that's the abbrev. used in report painter. As an update the problem seems to stem from the fact that I've added the WBS charateristic to the line and exploded it. when I do this I lose the credits to the cost center. Any idea?

  • Account Assignment - Derivation of Cost Object

    Hi All,
    On doing payment through transaction F-58, automatic line item of exchange rate gain n loss (P&L Account) is added automaticallly due to configuration done in FBKP -> Excng Rate Difference. The problem is, is there a possibilty to derive cost object which is used in Invoice of which the payment is being processed.
    Regards,
    Nayab

    Thanks Eli for your reply.
    Yes, I found the same i.e. the best practice is to assign CO through OKC9 on particular G/L Accounts. The issue is reports in Joint Venture Accounting "GJRG_5J1B" that shows all cost on particular job (cost center, wbs, network etc.) doesn't potray the right result after settlement of network. For instance
    Invoice is booked and cost element is charged on Network
    CJI3 show all amount
    GJRG_5J1B show all related amount.
    When payment is processed and in automatic RXD line item, constant Cost Center of Other Income is provided
    CJI3 doesn't show RXD amount
    GJRG_5J1B show RXD amount
    On settling Network, i.e. Roll up its cost to WBS level following happens
    CJI3 is settled, gross amount is 0.
    GJRG_5J1B show 0 as well other than RXD amount which still needs to be settled.
    The solution we found is to charge automatic line item to particular cost object so it will get settled while rolling up network amount to WBS
    The other solution is to settle such cost at period end but to do such activity I'm in search of standard way.
    Thank you again for your response.