Production Order - Segregating Costs for different cost elements.

Hi Experts,
I am a QM Key User and have been asked to look into improving our current Non-conformance / re-work process.
My plan is to include the rework operations within the original PP01 Production Order.
So far:
Three Work Centres have been created:
1. NCRTEST u2013 1st WC to collect hours
2. NCRTEST2 u2013 2nd WC to collect hours
3. NCROUTSO u2013 To collect costs associated with outsource operations i.e. weld repair, shaft straightening.
NCR-02: Activity Type Created
Two new control keys created
1. NC01: Confirmation of hours
2. NC02: Outsource operations (requisition generated)
NCRTEST-CC: Cost Centre Created
The Price Planning for Cost Centre/Activity has been specified (KP26 and KPB6)
Two new Cost Elements have been created:
1. 43001201 u2013 Costs associated with the outsource operation
2. 94301021 u2013 NCR Labour Hour Costs 
On a test production order we have managed to isolate the NCR hours to cost element 94301021 and the outsource operation costs to 43001201; however these costs are automatically settling to the production order material which then settle to the WBS (that is my understanding).
Is there any way of stopping the costs associated with the two cost elements from settling to the Production Order material? The costs cannot be settled this way as my intention, is for a new development which allocate the costs to the relevant notification QM Order.
The QM Order will then be settled in the normal way. Settling the production order and the QM order will result in duplicate costs.
I am not sure if this is a possible solution but is it possible for a negative cost to automatically post to the production order material for the two cost elements. The production order value would be correct and the QM Order could be posted as normal.
Thanks in Advance
Ben

Hi,
   I would expect that the costs get settled to the material only when you settle the production order to the receiver material. I don't think that happens automatically....it will have to be done explicitely
regards
Waman

Similar Messages

  • Production Order wise List for  Target cost v/s Actual cost

    Dear Sir,
    We have make to order scenario . We want to have a list giving Production Order wise "Target Cost" and "Actual Cost" . The purpose of list is to analyze the Variances Production Order wise .
    I request to kindly guide us , how can the above list be generated please .
    Regards
    B Mittal

    KKBC_HOE - With Defined Summarization Hierarchy
    S_ALR_87013104 - Sales Order Selection
    KKAC - For Sales Order with Assigned Orders
    KVBI - Actual Costs
    KOB3 - Variances

  • Production Order Variance Split based on Cost Component Split

    Hi All,
    We want the material/labor/overhead variances on the production Order to go to different value fields in the P&L.
    We will be issuing Actual Material/Overheads to the Production order and there will variances for both Material and Overheads due to differene in Standard and Actual Qty issued.
    But Standard SAP Variance Split Functionality will club the Material/Labor/Overhead Variances as Input Qty Variances so we cannot split it into different lines in the P&L.
    Any ideas on how this can be done.
    Thanks and regards,
    Ankur

    Hi Ankur
    Its not possble in FI, but certainly possible in COPA
    Create as many assignment lines in PA Trf Str as your Cost Comp Structure...
    Assign the relevant GL/Cost ele in the SOURCE and choose the radio button "Costs/Revenues", instead of "Variances"
    You can then assign each assignment to a separate Val Field in COPA
    br, Ajay M

  • After production order settlement, where does the cost go?

    Dear Experts,
    I understand after we did the "order settlement" for production order, the cost will be settled to material manufactured from the said production order.  Say, the total cost is $10,000 to produce 1000 units of finished goods (FG), then the cost settled to each individual FG at $10 each, am I right?  Where can I see the settled cost in the material master?..
    I checked in the cost center report, S_ALR_87013611, I can see the cost Credited from "production" cost center with a breakdown in settlement cost element such as machine hour, setup and personnel hour.  I understand the other side of Debit was to the production order, and only after order settlement, I'm not sure which cost center will be Debited.
    That would be the CO side, how about the FI, would there be any cost posted to the GL side after production order settlement to the material?
    Please advise..
    regards,
    Abraham

    Hi Abraham,
    It's not the button i mentioned. I was just trying to take u to the accounting document from the settlement screen. well just drill down the settlement screen and u'll get it. No big deal.
    But more important is the concept. I'll share my understanding here. (cost by production order)
    Any value that flow into controlling module should have a cost object. Here production order is the cost object.
    First u create a production order (cost object) for say 1 unit of X with a std price of Rs. 10
    Std price comes frm material master as a result of std cost estimate
    U start production - Raw materials are consumed - 2 qty x Rs.3.
    Entry RM Consumption Dr Rs. 6    Inventory Cr Rs.6 (Prod order is debited with Rs.6)
    Activity (Let's say machine hours - 3 Hrs x Rs.2) According to the routing it was  2 hrs but actual production took 3 hrs.
    Entry - None - But production order is debited with Rs. 6.
    When production is complete for 1 qty of X, entry flows
    Finished Goods Dr Rs.10    Change in Stock  Cr. Rs.10  (Production order is credited with Rs.100
    Abraham, now visualise both sides of the production order. It will have debit of Rs.12 and credit of Rs.10.
    Now accountant sees the production order and confirms the values are ok and puts the status of TECO to the order. which means the order is technically complete.
    Now when u run the order settlement, this production order is picked up by the system (due to it's status). System sees difference between debit and credit of Rs 2.
    So it cedits the production order with Rs. 2. Now both debit and credit of production order is equal (Rs.12)
    Entry Price diff A/c Rs,2     Change is stock A/c Rs.2
    Now this rs. 2 is settled to COPA. It does not flow to material.
    Reason:  in a std costing system materials are valued at standard cost and
    Hope this helps. Do revert in case of doubts.
    Best Regards
    Vimal

  • Maintaining percentage for different cost centers

    Hi All,
    we have one Expense GL a/c: 45010 (Electricity)
    when the expenses occur... the amount hits this GL a/c
    Example GL amount = 50,000
    Now we want to maintain the percentage for different COST CENTERS....
    & that 50,000 should be distributed automatically to respective cost
    centers depending on %
    So how do we go about it...please advise

    Hi,
    look here:
    http://help.sap.com/saphelp_47x200/helpdata/en/49/4398375ae2f84ae10000009b38f8cf/frameset.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/08/514e2143b511d182b30000e829fbfe/frameset.htm
    A.

  • How to make a production order type default for a Plant.

    Hi All,
    I want to know the setting to make production order type ZP01 default for a plant so that when I create a production order using CO01 for that particular plant, it should always use ZP01 as order type?

    Hello Friend,
    One more method is to achieve this is by using Production Scheduling Profile. In transaction OPKP, for your Plant create a new production scheduling profile or use the existing one created in your plant. Inside the production scheduling profile, in order type section, for make to stock field, maintain the value as ZP01 (which you want to come automatically all the time while creating the order by co01) and save.
    Now assign this production scheduling profile in material master of all Semifinished and Finished materials.
    Now create new production order by co01. On initial screen of this transaction give only material code and production plant and enter (don't give anything in order type field).
    After giving material code and production plant, press Enter. After pressing enter system will take you inside the production order .
    Check here by default system will take order type as ZP01.
    Check and Confirm.

  • Report for production order with actual and target cost for each

    Hi
    Is there any report that gives me the list of all production orders in a month with its respective actual and target costs?
    I can use COOIS to get a list of production orders, then double click on the prod order, then click on goto and then to cost analyis.. but can i avoid going through all this and get a report with the details i need?
    thanks in advance

    Thanks a lot for that.
    I'm a little confused with the columns in the report.
    Which columns should I keep for my requirement? -
    Production Order
    Total Target Cost
    Total Actual Cost
    Total Actual Qty
    Total Target Qty
    Thanks

  • VA01 Sales order (line items) and different Cost center assignment

    Hello gurus,
    im searching for solutions how to assign different cost center to sales order line items, but only thing that i found is the substitution (Using Substitution (GGB1) to change Cost Center assigned in (OKB9))
    Trying to do this i was unable to create something that could work, since there was no Logistic.
    Could somebody explain me the Line item in SO assignment to Different cost centers?
    I know alot about OKB9, VKOA and other transactions, but still cant find anything suitable to solve this issue
    Best regards
    Laurynas

    What i mean is that, on the end of every month we are gathering information for Statistical Key Figures (from Controlling) entering as CO document and then distributing the costs using KSV5 TC on Internal Orders according those entered statistical key figures.
    i.e. we got INCOME 1000000 from 10 internal order, which we distribute on even percentage parts like 10 cost center, each getting 10% of the income.
    I tried to create the SO, but the Profit center field, after i entered a number, was changed automatically into another.
    And the posting didnt reach Controlling and the assigned Cost center. I think it is a lack of configuration.
    Regards
    Laurynas

  • Production Order doesn't show planned costs

    Please,  help me!
    When I save the order production, despite in configuration is set "Calculate planned costs when order is saved" & when is saving the order apears "Calculating costs" at the bottom of the window  the order doesn't show costs analysis when I review the order in CO02 or CO03.
    I am using SAP ECC 6.0
    Thank you!

    Donald,
    I think for your Order type / Plant combination automatic calculation of Planned cost is not defined,  you can check this in transaction OPL8, these defination would be in Controlling tab.
    Check for Planned cost calc field:
    The following options exist:
    0: No planned costs are calculated when saving
    1: Planned costs are calculated when saving, if the order has been released and having REL status.
    2: Planned costs are calculated when saving.
    I think in your case the option or 2 is being used, so you need to perform the Cost function manually for the planned cost for the order to get calculated.
    Regards,
    Prasobh

  • Shipment Cost for different Forwarding agents in one Shipment Document

    Hi.
    I have an requirement, can we create one shipment type, which is based on multiple Forwading Agents,
    i.e suppose if we have a Route with priliminary & subsequent legs having forwrding agents different at each stage.cost has to be  calculated according to the forwarding agents with in the document according to the ROUTE .plz suggest..
    Regards.
    Sujith.

    Hi Sujith,
    This situation may arriase anytime.
    it is possible to create one shipment cost document for more than 2 forwarding agents.
    Standard SAP gives all the option in such scenario.
    No Z developments required for achieving seperate costing for individual forwarder.
    Regards,
    Dnyandeo H. Ainarkar

  • How to track cost for different Vendors through SAP PM

    Hi
    Maintenance needs to discuss with SAP PM Consultant for tracking the different vendor for civil, painting and external services jobs from asset locations and class. It means that total expenses of Civil, Painting and external services jobs for different locations should be easily gathered.
    Also ,As temporary solution of identifying posting for different vendors, how maintenance will be able to find actual amount posted for different vendors
    Regards
    chand

    Hi
    can you tell me where we can make control
    When RFQ is created the PR is not allowed to change when the PR is manually created & it is working perfectly.
    but when PR is created thorugh work order then even if RFQ is created/released  it is allowing to change PR when created throogh work order
    Please tell me where is control
    Regards
    chand

  • When will EK02 appear in the Sales Order?? For different planning strategy?

    Hi Experts,
    In our SAP system ,when you create a sales order with a material which planning strategy is
    50 Planning without final assembly (MTO) , in the item detail screen , on the "Conditions"
    TAB, we will see condition type EK02 and its value.
    But when I create a sales order with a material which planning strategy is 40 Planning with
    final assembly (MTS),in the item detail screen , on the "Conditions" TAB, condition type
    EK02 will not appear.
    I have checked the customizing of our SAP system ,as follows:
    For planning strategy 50, the Requirements class is "045"(MTO val. with cons.),and on the
    configuration screen of Requirements class,we see "Condition type for copying costs from
    line items" (CndTyLineItems) is null ,no value ,not "EK02".
    And for planning strategy 50,the the Requirements class is "050"(Warehouse consumpt.) and
    and on the configuration screen of Requirements class,we see "Condition type for copying
    costs from line items" (CndTyLineItems) is also null ,no value ,not "EK02".
    And on the configuration screen of Sale Order Type screen(VOV8), we see  "Condition type for
    copying costs from line items" (CndTyLineItems) is "EK02" for all the sales order type we
    have used.
    So I am very confused.
    Why material with planning strategy 40 there is no EK02 in the sales order?
    Why material with planning strategy 50 there is EK02 in the sales order?
    Where is the EK02 come from? The requriement class ? Or the Salse order Type?
    Are there any other customizing for Condition type EK02 determination?
    Thanks very for any reply!!

    Hi,
    In MTO you will create Process order.
    And to Produce a Item you use Sub components that is Raw material
    That raw material cost is EK02 which you maintain in the Material Master - Accounting View 1.
    You can see cost in the Process Order also .
    Note : Dont post same in different posts

  • Allocation of cost to different cost center

    Hi Techies,
    I have to allocate cost from one cost center to different cost center according to percentage (%). Company wants to show same cost on sender and then breakdown according to % on receiver cost center.
    Example: Company wants to allocate cost from CCenter A to Ccenter B1, B2, B3.... according to % like 74.1% to B1, 14.8% to B2. Now which allocation functionality (Assessment, Distribution) I should use to solve this problem. I would really appreciate if you have method or process step to perform this process.
    Thank You,
    Kenny

    Use transaction KSU2 to call the Assessment Cycle.
    Click on "First Segment" and in the segment header, under Sender Values, select Posted Amounts and key in 100% (since you wish to assess all the costs). Under Receiver Tracing Factor, select Fixed Percentages.
    Click on the "Senders/Receivers" tab. Now under "Senders", do an F4 (dropdown list) in the Cost Centres field and select your Cost Centres (or groups).
    Similarly click on the Cost Elements and dropdown to select your Cost Elements or groups.
    Now under Receivers, in the Cost Centre field, key in the Cost Centres you wish to post costs to.
    Click the next tab Sender Values
    Here, enter Share in % as 100% (default) and under version, enter 0.
    Now click on the Receiver Tracing Factor tab. You should see all the Cost Centres you entered under Receivers in the Sender/Receiver tab. Enter the %s you wish to apportion to each Cost Centre.
    Save this cycle and run this for the period in question. Before you run this, make sure you post some costs to the Sender Cost Centres. Else the system will find nothing to assess and come back with the same error.
    Hope this helps.
    Cheers.

  • Additional  Cost for Item cost

    Hi all!
    My production ordr have additional cost: labor, electric. I don't define standard cost for them. I want to fill in production order these costs equal x% of Itemcost. Can i do that. Or if you have other ideas to use additional cost, you can help me solve this problem.
    Thank you!

    Some reading about FMS
    [https://websmp108.sap-ag.de/~form/sapnet?_FRAME=CONTAINER&_HIER_KEY=701100035871000437965&_OBJECT=011000358700003625432006E&_SCENARIO=01100035870000000183&]
    You can set up a calculation for the value you need based on values of the current Production Order and return the value to the Item added to add Labor cost to the Production Order.
    Franz

  • Multiple production orders  are generated for same requirement

    hello guru's
    For a MTO (make to Order) scenario, where the Material requirement quantities are generated from Sales Orders.
    Ex: Sales Order created for 500 Qty.
    I had run the MRP using MD03 with the following parameters
    Processing key              NETCH      Net Change in Total Horizon
    Create purchase req.     1                  Purchase requisitions in opening period
    Delivery schedules       3                  Schedule lines
    Create MRP list            1                  MRP list
    Planning mode              1                  Adapt planning data (normal mode)
    Scheduling                    1                  Determination of Basic Dates for Planned
    System had generated Planned Orders for Qty 500 and these are converted to Production order for Qty 500 for which the Purchase Order for 500 are created.
    Goods receipt of 480 has been made against the Purchase Order for the Ordered 500 Qty.
    When I re-run the MD03 the system is generating the new Production Order Qty 0f 20 which is not supposed to be as this 20 Qty was already part of the existing Purchase Order and yet to be delivered .
    Could you please explain me why this is happening?
    regards

    Dear,
    MRP will consider the firmed PR for the completion date contained in the PR. If the requirements date is different, then MRP will create a new proposal (PR).
    If you wish for MRP to RESCHEDULE the dates of existing firmed purchase reqs, instead of just creating new proposals, you have to set the Rescheduling horizon. OPPQ> Rescheduling (plant) or OPPR >Recheduling Horizon (MRP Groups). Start with a small horizon,  Also check the tick mark for firm reciept there.
    Are you getting any expection message in front of PR?
    MRP will 'assume' rescheduling by configuration, by managing the rescheduling horizon, and by setting the rescheduling tolerances. These config can be found in
    OPPQ select Rescheduling
    or, for MRP groups
    Please check and come back.
    http://help.sap.com/saphelp_erp60_sp/helpdata/EN/f4/7d2c9744af11d182b40000e829fbfe/frameset.htm
    Regards,
    R.Brahmankar

Maybe you are looking for

  • Everytime I open a Pdf  file using Acrobat pro 9 ( part CS4 )it crashes

    Hello All, Did someone was able to find a solution? Here's the crash report Process: AdobeAcrobat [2129] Path: /Applications/Adobe Acrobat 9 Pro/Adobe Acrobat Pro.app/Contents/MacOS/AdobeAcrobat Identifier: com.adobe.Acrobat.Pro Version: 9.3.4 (9.3.4

  • Select in stored procedures 11g

    I come from MS Sql Server, so select statements in Oracle are confusing, I have only 3 days experience with Oracle 11g I have managed to use SELECT INTO in my SP Can anyone provide an example of select using a for loop_+  AND  an example of select us

  • What is the purpose of standby redo log files

    Hi, What is the purpose of the standby redo log files in DR? what if the standby redo log files are created? or else not created? Please explain Thanks

  • JavaServer Faces or Struts - New insights anyone?

    Hello Everyone: JSP or Struts???!! I'm really lost. I've read almost every posting on the subject (on this and other forums), yet, I couldn't come with a solid conclusion (may be only inclinations). I've started developing my very first real-world we

  • Paste function

    Hi All, What i would like to do is add a sort of 'paste' function to my site. http://www.milesmemorials.com/product-GH54.html As you can see there is a drop down menu for 'Inscription & Verses' with a list of codes, each code refer's to a sample of t