Production Order doesn't show planned costs

Please,  help me!
When I save the order production, despite in configuration is set "Calculate planned costs when order is saved" & when is saving the order apears "Calculating costs" at the bottom of the window  the order doesn't show costs analysis when I review the order in CO02 or CO03.
I am using SAP ECC 6.0
Thank you!

Donald,
I think for your Order type / Plant combination automatic calculation of Planned cost is not defined,  you can check this in transaction OPL8, these defination would be in Controlling tab.
Check for Planned cost calc field:
The following options exist:
0: No planned costs are calculated when saving
1: Planned costs are calculated when saving, if the order has been released and having REL status.
2: Planned costs are calculated when saving.
I think in your case the option or 2 is being used, so you need to perform the Cost function manually for the planned cost for the order to get calculated.
Regards,
Prasobh

Similar Messages

  • Material product types doesn't show in line item detail

    Good morning,
    We have a problem with product popup of service order in line items.
    When we make a click in product ID on the service order search, a popup shows and it displays all products.
    But if we go to Detail Position Id and do the same, the popup shows but Material product types doesn't show.
    Regards,
    Euge.-

    Hi Abhi,
    Thank you for your advise.
    Yes, OBCN has been maintained with posting indicator "2".
    During the testing, when we did GR (MIGO) there is no tax calculated, will the tax calculated and show in separate line item when we do Invoicing (MIRO)?
    Thank you in advance.
    Regards,
    Izzat

  • After production order settlement, where does the cost go?

    Dear Experts,
    I understand after we did the "order settlement" for production order, the cost will be settled to material manufactured from the said production order.  Say, the total cost is $10,000 to produce 1000 units of finished goods (FG), then the cost settled to each individual FG at $10 each, am I right?  Where can I see the settled cost in the material master?..
    I checked in the cost center report, S_ALR_87013611, I can see the cost Credited from "production" cost center with a breakdown in settlement cost element such as machine hour, setup and personnel hour.  I understand the other side of Debit was to the production order, and only after order settlement, I'm not sure which cost center will be Debited.
    That would be the CO side, how about the FI, would there be any cost posted to the GL side after production order settlement to the material?
    Please advise..
    regards,
    Abraham

    Hi Abraham,
    It's not the button i mentioned. I was just trying to take u to the accounting document from the settlement screen. well just drill down the settlement screen and u'll get it. No big deal.
    But more important is the concept. I'll share my understanding here. (cost by production order)
    Any value that flow into controlling module should have a cost object. Here production order is the cost object.
    First u create a production order (cost object) for say 1 unit of X with a std price of Rs. 10
    Std price comes frm material master as a result of std cost estimate
    U start production - Raw materials are consumed - 2 qty x Rs.3.
    Entry RM Consumption Dr Rs. 6    Inventory Cr Rs.6 (Prod order is debited with Rs.6)
    Activity (Let's say machine hours - 3 Hrs x Rs.2) According to the routing it was  2 hrs but actual production took 3 hrs.
    Entry - None - But production order is debited with Rs. 6.
    When production is complete for 1 qty of X, entry flows
    Finished Goods Dr Rs.10    Change in Stock  Cr. Rs.10  (Production order is credited with Rs.100
    Abraham, now visualise both sides of the production order. It will have debit of Rs.12 and credit of Rs.10.
    Now accountant sees the production order and confirms the values are ok and puts the status of TECO to the order. which means the order is technically complete.
    Now when u run the order settlement, this production order is picked up by the system (due to it's status). System sees difference between debit and credit of Rs 2.
    So it cedits the production order with Rs. 2. Now both debit and credit of production order is equal (Rs.12)
    Entry Price diff A/c Rs,2     Change is stock A/c Rs.2
    Now this rs. 2 is settled to COPA. It does not flow to material.
    Reason:  in a std costing system materials are valued at standard cost and
    Hope this helps. Do revert in case of doubts.
    Best Regards
    Vimal

  • Production order status and MRP planning - CNF and DLV

    I am confirming a production order using CO15. I have a single operation. The control key of the operation says that there will be no goods receipt. The GR will be done seperately using MIGO to order. My order is for 24000. I do a GR for 23000 using MIGO and then do a final confirmation using CO15. The order is now in status CNF and PDLV. Now for planning in MD04 it still shows a pending qty of 1000. If I TECO the order or mark it 'delivery complete' then it is wiped out of planning.
    My question is if there is a configuration setting where if a order is in CNF but not delivered it should get wiped out of MRP planning?
    thanks a lot

    John,
    The problem is that doing so would lead to (business) inconsitencies and I do not advise you to TECO or DLV the order just to get rid of it.
    Whilst it may not be "nice" to see it appear in MD04 it is there for a purpose - to reflect the fact that a quantity is going to be goods receipted.
    EG:
    You have an order for 10  --> MD04 shows an expected GR of 10.
    You do a final confimration for 7 --> MD04 now shows an expected GR of 7.
    When you do the MIGO for the order for a qty of 7 , the order will disappear form MD04 - which is right.
    If that order was to disappear from MD04, during yur next MRP, SAP would generate another procurement proposal to cover any requirements you may have.
    As Vivek said, I would investigate doing an AUTO GR.
    Hope it helps.
    Edited by: Pascal on Jul 31, 2009 3:28 PM

  • Report for production order with actual and target cost for each

    Hi
    Is there any report that gives me the list of all production orders in a month with its respective actual and target costs?
    I can use COOIS to get a list of production orders, then double click on the prod order, then click on goto and then to cost analyis.. but can i avoid going through all this and get a report with the details i need?
    thanks in advance

    Thanks a lot for that.
    I'm a little confused with the columns in the report.
    Which columns should I keep for my requirement? -
    Production Order
    Total Target Cost
    Total Actual Cost
    Total Actual Qty
    Total Target Qty
    Thanks

  • Automatic creation of Production order when PP/DS planned order is CIFed.

    Hi PP Gurus,
    The requirement is when PP/DS Planned order is created and CIFed to ECC R/3, Automatically system should create Production order for that planned order. In this case, is Trigger points will serve the purpose or need to adopt for some other way? I think since APO PP/DS is in sync with ECC R/3, something SAP might have given in this regard?
    Thanks & Regards,
    Abu Arbab

    Dear Abu,
    In SPRO PPDS global parameters and defaults, you can set "create transfer events from conversion indicator".
    After this the planned order is transferred to R/3 only when a conversion indicator is set against planned order.The conversion indicator can be set through RRP3 or RRP4.  You can put mass conversion indicator.
    When such planned order is transferred, it will automatically create production order.
    Regards,
    Nitin Thatte
    Edited by: Nitin Thatte on Apr 20, 2009 4:59 PM

  • Notification on Receipt and Purchase documents getting fired on Production order having Items with planning method as MRP

    I have written a SP Notification to block adding of documents if block number is not provided. Notification is working fine on Purchase and Receipt documents. This notification also gets executed on Production Order where items included in Production order have planning method as MRP.
    Can anyone explain me the relationship between
    "MRP planned items"
    and
    "Purchase documents (Purchase Order; GRPO; Purchase Return; AP Invoice and Credit Memo) and Receipt of Production."
    Thanks & Regards
    Sonil Bhardwaj

    Hi Sonil,
    Can you post your SP , to look if there is any problem with SP ..
    Regards

  • I made payment for Creative Cloud but order doesn't show on my account. Only the free trial shows when I am going into my account. What can I do?

    I made a payment with my credit card for Creative Cloud. I have confirmation of payment on my phone by on the name to Digital River Luxembourg. Did the payment went to the right place?
    When I enter my Adobe account doesn't show any order purchase or any order pending?
    What can I do?

    Moving this discussion to the Adobe Creative Cloud forum.
    Tumaaka if you are facing difficulties placing your order then please contact our support team directly at Get help with orders, refunds, and exchanges.

  • Production Order wise List for  Target cost v/s Actual cost

    Dear Sir,
    We have make to order scenario . We want to have a list giving Production Order wise "Target Cost" and "Actual Cost" . The purpose of list is to analyze the Variances Production Order wise .
    I request to kindly guide us , how can the above list be generated please .
    Regards
    B Mittal

    KKBC_HOE - With Defined Summarization Hierarchy
    S_ALR_87013104 - Sales Order Selection
    KKAC - For Sales Order with Assigned Orders
    KVBI - Actual Costs
    KOB3 - Variances

  • Production Order Variance Split based on Cost Component Split

    Hi All,
    We want the material/labor/overhead variances on the production Order to go to different value fields in the P&L.
    We will be issuing Actual Material/Overheads to the Production order and there will variances for both Material and Overheads due to differene in Standard and Actual Qty issued.
    But Standard SAP Variance Split Functionality will club the Material/Labor/Overhead Variances as Input Qty Variances so we cannot split it into different lines in the P&L.
    Any ideas on how this can be done.
    Thanks and regards,
    Ankur

    Hi Ankur
    Its not possble in FI, but certainly possible in COPA
    Create as many assignment lines in PA Trf Str as your Cost Comp Structure...
    Assign the relevant GL/Cost ele in the SOURCE and choose the radio button "Costs/Revenues", instead of "Variances"
    You can then assign each assignment to a separate Val Field in COPA
    br, Ajay M

  • Production orders in place of planned orders in MRP run

    Hi,
    Please help me with this senario,
    we receive saleorders through CRM interface then these are chnged to redistribute to different plants by changing the plants in saleorders.
    we want to run and create production orders directly for these saleorders without creating planned orders.
    I tried using strategy 82 but it makes the production order online, but we want it to be created after mrp run.
    Is there a way to create production orders instead to planned orders in MRP run.

    Hi You used Right strategy only.Use Strategy '82',  Transfer requirement from CRM and execute MRP run in Background.It will generate Production order.But i didn't understand what you mean by 'Online' 3
    Pl.  Correct me If I am wrong.
    Edited by: Velmurugan S on Mar 4, 2008 10:02 AM

  • Production Order routing not showing process time

    Dear Guru's
    After creating production order , routing is not showing processing time, though its maintained in the standard values. What could be the problem?
    Thanks in advance.
    Regards,
    PPQMUSER

    Hi,
    U should check ur processing formula used in work centre. If it is correct and your routing is showing correct data then do READ PP MASTER DATA in your production order.
    It will help you.
    Regards,
    Alok Tiwari

  • Internal Order Report  S_ALR_87012993 showing settled cost

    HI ,
    The issue here is related to IO report  S_ALR_87012993 showing up settled cost against a particular Cost Element/GL account. However when we use the drill down function it says "No actual Line Item exist". I have checked the line item details for that particular GL account which does not have any posting to it with the said IO and moreover no FI Posting is done to that GL account during that relevant period. Hence the IO report is showing up variance .
    I have checked the Settlement documents for  that period for the said IO (Table AUAK ) through Transaction Code KOB8 , but none of these settlement indicates that particular Cost element/GL Account.
    I have executed KOB1 which does not show up any line item with the said combination.
    Any idea why the system /report showing up such settlement to that particular Cost Element/GL account which does not have any Actual Line Item posted with that particular IO.
    Regards
    Jaydip

    This is very very strange. Are you sure is not facing some profile problems to view information ?
    KOB1 and S_ALR_87012993 have the same information: actual.
    When you run settlement, it goes to inventory delivery account or to wip account depends on order status.
    Sometimes people set a different account for settlement.
    Check the balance account in transaction FS10N/FBL3N it must be the same because FI and CO are balanced for this account.
    Regards

  • Return Order doesn't show Relationship tab in service for Object in ECC 6.0

    Hi,
    When a Return Order is made from an Idoc, unable to see the relationship tab to be active in Service for Object. When tried the same in the old systm 4.6C it works fine.

    Hi,
    Search with that term in notes i.e. service.sap.com/notes or ask the functional consultant to take the help of abap and solve the issue.
    Regards,
    iqbal

  • MTO Production order planned cost

    Hello
    We have a MTO production order.Need to know plan cost of order.But unable to get in COEP or other csoting tables.Any other table where we can get the data.
    Thaks in advance.

    Hi,
    Check COSP table it is for planned cost.
    Regards,
    Sreekanth