Project Server 2013 Poor Performance

Hi Guys
On a new build of Project Server, we are experiencing poor performance across the board, Site Collection, Central Admin, everything is slow.
We have allocated 12GB and Quad core (lower end of the recommend scale). However as there are no users, I would expect it to be fine at the moment (Search is not setup or anything, just a simple service app with a pwa site provisioned).
What things can we check? From looking on the internet, Distributed Cache crops up a lot. Can this bring performance right down?
For the record, we have March 2013 PU and Oct 2013 CU applied.

Hello,
There could be a number of causes, it is very difficult to diagnose without understanding the farm infrastructure. Can you give details of:
Number of servers in the farm + Specs
If virtual, is the host server over committed? Have you set up reservations for memory and CPU?
What is the storage?
What is the network speed between servers / storage etc?
Do you have any Anti-Virus software installed on the servers? If so, have you tested with it disabled on all servers in the farm?
Paul
Paul Mather | Twitter |
http://pwmather.wordpress.com | CPS

Similar Messages

  • Help needed Regarding Project Server - 2013 Workflow

    Hi All,
    I am new to Project server 2013 Workflow, hence please help me regarding this. Pardon me if this question is too trivial. 
    I have created a project type associated with a workflow and my workflow is as follows :
    So I am not doing anything here, I am just testing the workflow as mentioned by technet site : http://technet.microsoft.com/en-us/library/dn458865(v=office.15).aspx
    But it is mentioned that, after a minute or 2, the workflow state will change, also they have mentioned to press the Submit button.
    But in my case, the workflow is not moving to next stage [It just says 'The workflow is still processing - which never changes after hours] or I am getting the submit button (Submit button is disabled on the ribbon). Below is the state of my workflow :
    PS : I have made the user added to Portfolio managers group as well. But still I am having this same issue. 
    The Workflow manager is installed properly, and it is working fine in case of List workflow. I am facing the issue only wrt Site workflow for Project server 2013.
    Please help me to solve this issue.
    Thanks,
    shanky

    Hi Kiran,
    I am now facing issue while assigning a task to a person in the workflow.
    I am having a person named say 'John' , who is included in Project Manager as well as Portfolio Manager.
    And I am using a workflow as :
    Stage : Conceptual
    Assign a task to John (Task outcome to Variable: Outcome5 | Task ID to Variable: TaskID3 )
    Transition to stage
    Go to Approval
    But this is again giving issue as :
    Workflow Internal status : Cancelled
    Details: System.ApplicationException: HTTP 401 {"error":{"code":"-2147024891, System.UnauthorizedAccessException","message":{"lang":"en-US","value":"Access denied. You do not have
    permission to perform this action or access this resource."}}}
    PS : I have used the same Sharepoint admin account for 'Account Name' in ‘User Profile Sync' , Is this causing the issue? Please let me know.
    Thanks,
    Shanky

  • Publication of the big-sized Enterprise projects from Project Professional 2013 to Project Server 2013 takes about 60+ minutes.

    Dear Sirs,
    I need your support over the following MS EPM 2013 issue:
    Publication of the big-sized Enterprise projects from Project Professional 2013 to Project Server 2013 takes about 30+ minutes. We
    need to reduce this total publication time down to acceptable working values 10+- minutes.
    Environment information:
    Single App Server (Virtual): 16 Gb RAM, x64 4xCPU, HDD > 50 GB free disk space, OS Windows Server 2012 Standard Edition x64 Service
    Pack 1, MS SharePoint Server 2013 and MS Project Server 2013 with CU December 2013 (KB 2850024) applied.
    Single RDBMS MS SQL Server (Virtual): 8 Gb RAM, x64 4xCPU, HDD > 200 GB free space, OS Windows Server 2012 Standard Edition x64 Service
    Pack 1, MS SQL Server 2012 x64 SP 1 Enterprise Edition.
    We have 1Gbit LAN between APP, DB server and 1Gbit LAN between APP and Proj Prof Client.
    Yes, we are on the way of migrating to the Prod environment
    with 3-tiered architecture (with SP1 slipstream and CU December 2014 applied), but this issue also
    presents there.
    Project’s file information:
    Tasks in the file: [~4900], resources in the file [~396] enterprise task’s custom fields used in the file [~23].
    Project save procedure for this new project would last about 7 minutes. Project publication would last about 47 minutes. We noticed that
    tasks synchronization process took about 1 second for each ~2,5 tasks, to add them to the sharepoint tasks list. So for all 5148 tasks it took about 5148/3/60 =  34 minutes. Other 13 min was used for reporting database publication and other tasks relevant
    for new sharepoint site creation.
    Case 1: Issue description:
    During the Enterprise project’s file save and publication we have the following sharepoint 2013 log messages:
    07.31.2014 12:43:17.22 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope
    (Persisting list changes). performing time =376.068676326181 22dca99c-4696-70f1-e9e2-06851d0bcffd
    07.31.2014 12:43:17.69 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope
    (Persisting list changes). performing time =361.652807828928 22dca99c-4696-70f1-e9e2-06851d0bcffd
    It shows that sharepoint spend at least ~350 milliseconds (or 0,35 sec*4900 tasks = 1715 sec, or 28,5 min) for each task update during
    project publication. And we also have another log file that shows that about 0,7 sec (or 0,7 sec*4900 tasks = 3430 sec, or 57 min) sharepoint spend for save each task in project file to project server. So total save and publication time more then 60+ minutes
    for that project file. The same result we have even if user didn’t do any changes at the project file.
    We use only enterprise projects (dbo.MSP_EpmProject_UserView.projectvisibilitymode = «False»), and do not use sharepoint tasks lists,
    but the synchronization between MSP Plan and SharePoint tasks list works at any case.
    Case 2: Issue description:
    - For the second test we created a new project with new sharepoint project’s site on basis of our «issue» project, with total amount
    of tasks in it of 5148 (yes, we increased the tasks list default limit at the sharepoint site up to 6000 items in it – standard limits for sharepoint view list – 5000 items).
    - Project save procedure for this new project would last about 7 minutes. Project publication would last about 47 minutes. We noticed
    that tasks synchronization process took about 1 second for each ~2,5 tasks, to add them to the sharepoint tasks list. So for all 5148 tasks it took about 5148/3/60 =  34 minutes. Other 13 min was used for reporting database publication and other tasks
    relevant for new sharepoint site creation.
    -Then we deleted the
    tasks list for that new test project from the sharepoint site and republish the project plan one more time. This time project save procedure took about 7 minutes, project publication about 2 minutes and 3 minutes for other relevant queue jobs. So total time
    is 12 minutes.
    As a conclusion: yes, we have determined
    the exact problem - during synchronization process (from Project Server to SharePoint) it perform copying all tasks and related data from Project to SharePoint in spite of fact that you changed only ONE task or ALL of them. At any case, synchronization will
    copy ALL of them from Project Server to SharePOint task’s list.
    Our workaround is to disable the task’s synchronization for such big-sized project plans:
    – to delete the SharePoint «tasks» list at the SharePoint site tied with project plan.
    - or deattach the SharePoint site from the project plan.
    Thank you for reading this topic, please if you also forced with such issue provide us any known workaround or maybe any official response
    \ feedback from MS about it.
    Thank you in advance,
    Best Regards, Andrey

    Regarding my topic, I also said that every time when sync works it updates All items from project’s plan at Project Server to corresponded task’s list at SharePOint server. Inspire of the fact that you changed only One task or group /
    all of them at your project’s plan.
    And it seems to me and my colleagues that it’s probably (maybe) a “bug” at the product. Here is what we have if looked a little bit closer to the code:
    Share Point determines what task to sync from Project’s plan to sharepoint list. To do that sharepoint needs to know was that task changed or not, based on the following fileds (check SQL stored procedure “[MSP_READ_TASKS_FOR_SYNCRONIZATION]”):
    TASK_UID    TASK_NAME    TASK_START_DATE    TASK_FINISH_DATE    TASK_PCT_COMP    TASK_PARENT_UID    TASK_OUTLINE_NUM   
    WSS_LISTITEM_UID   TASK_ID    TASK_IS_ACTIVE
    We noticed that at any case synchronization performs for all tasks, EXCEPT the ROOT one. Then we looked at the comparison of TASK_PARENT_UID field. So sharepoint compares TASK_PARENT_UID with ParentID (this is internal name for lookup
    field “Tasks” at the Sharepoint, and it stores their values at the format "ID;#Title").
    And comparison performs like following:
    SharePoint looks for Task at the Tasks’s list corresponded to Project’s plan with ID represented at the TASK_PARENT_UID field. Then it takes SharePoint ListItem ID (“int” type) and store it to the “num” parameter;
    num = this.GetCachedListItemByUniqueId(listItem.ParentList, nullable.Value).ID;
       2.Then it compares “num” with task’s “ParentID” at SharePOint as follow with operator “!=”:
    ((SPItem) listItem)["ParentID"] != (System.ValueType) num
       3. If comparison was success (true) – then it tell us that values (at the Project’s plan for tasks) was changed, then it need to be synchronized. Corresponded Method setup “true” flag, and then returns it.
    The “bug” is that this expression at the Step 2 will always return “true”, because in fact it compares “string” (see above – that this is lookup field at SharePoint side)
    with “number”. For example if the parant task ID is “55”, then we get:
    "55;#Task 1" != 55
    And by the rules of .Net the “string” will never equal “number”
    Furthermore this is approved by the SharePoint logs:
    In that case we always get the note “Setting ParentID to” at the logs (we see it if turns on Verbose for “Project Server” -> “Sharepoint Integration” category).
    So at any case of publishing project’s plan we always get that note at the logs for tasks that have Parent task, and we have Parent for all of them EXCEPT the ROOT one, exact logs represented further:
    10/15/2014 02:37:32.26    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server    Sharepoint Integration    ado0d   
    Verbose    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.62    Microsoft.Office.Project.Server (0x07D8)    0x06E8   
    Project Server    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.63    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.67    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.69    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 5    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d
    The following is the complete Method’s code from the corresponded reflector:
    private bool UpdateParentID(DataSet taskDS, DataRow row, SPListItem listItem, Dictionary<Guid, SPListItem> redoEntries)
    bool flag = false;
    int index = taskDS.Tables[0].DefaultView.Find((object) DataRowExtensions.Field<Guid>(row, "TASK_PARENT_UID"));
    if (index >= 0)
    Guid? nullable = DataRowExtensions.Field<Guid?>(taskDS.Tables[0].DefaultView[index].Row, "WSS_LISTITEM_UID");
    int num = -1;
    if (listItem.Fields.ContainsField("ParentID"))
    if (nullable.HasValue)
    try
    // STEP 1
    num = this.GetCachedListItemByUniqueId(listItem.ParentList, nullable.Value).ID;
    catch (ArgumentException ex)
    if (redoEntries != null)
    if (!redoEntries.ContainsKey(DataRowExtensions.Field<Guid>(row, "TASK_UID")))
    redoEntries.Add(DataRowExtensions.Field<Guid>(row, "TASK_UID"), listItem);
    //STEP 2
    if (num != -1 && ((SPItem) listItem)["ParentID"] != (System.ValueType) num)
    ((SPItem) listItem)["ParentID"] = (object) num;
    ULS.SendTraceTag(845443U, (ULSCatBase) ULSCat.msoulscat_PS_ProjectSharepointIntegration, ULSTraceLevel.Verbose, "Setting ParentID to {0}", new object[1]
    ((SPItem) listItem)["ParentID"]
    //STEP 3
    flag = true;
    else if (((SPItem) listItem)["ParentID"] != null)
    ((SPItem) listItem)["ParentID"] = (object) null;
    ULS.SendTraceTag(2495056U, (ULSCatBase) ULSCat.msoulscat_PS_ProjectSharepointIntegration, ULSTraceLevel.Verbose, "Resetting ParentID to null");
    flag = true;
    return flag;
    Any thoughts about it would be much appreciated!

  • After installing Project Server 2013 (without updating SharePoint Server 2013 SP1))

    I am facing the problem while opening project web app. I configured the SharePoint 2013 and project server 2013. Here is the detail what I performed the steps:
    OS Server 2012 R2, SQL Server 2012, SharePoint server 2013 version
    15.0.4420.1017, Project Server 2013 version
    15.0.4454.1000. SharePoint configured and running successfully. After project web app site provisioning successfully completed. I got the below error.
    Microsoft.Office.Project.PWA.WebParts.PWAPart' from assembly 'Microsoft.Office.Project.Server.PWA, Version=15.0.0.0, Culture=neutral, PublicKeyToken=71e9bce111e9429c' cannot reduce access.
    I run this psconfig -cmd upgrade -inplace b2b -wait -force. But still getting same error.
    Previous steps:
    Earlier I had also tried to install SharePoint Server 2013 SP1 "3823428". After the installation SP1 some of sharePoint site features suddenly stopped e.g: Cannot  browse "Service Applications -->
    Manage service applications"  option even after re-start the server. This was previous error after upgrading SP1
    "Method 'get_IsClientValid' in type 'Microsoft.SharePoint.WorkflowServices.WorkflowServiceApplicationProxy' from assembly 'Microsoft.SharePoint.WorkflowServices,
    Version=15.0.0.0, Culture=neutral, PublicKeyToken=71e9bce111e9429c' does not have an implementation"
    Anyone can help me!!! Thanks...
    Faisal Numan

    hello,
    For SP2013 and PS2013 to work properly on Windows Server 2012 R2 you need to use the SP1 install media for both, download SharePoint 2013 with SP1 and Project Server 2013 with SP1
    http://support.microsoft.com/kb/2891274
    http://blogs.technet.com/b/office_sustained_engineering/archive/2014/03/03/announcing-availability-of-slipstreamed-office-2013-and-sharepoint-server-2013-with-sp1.aspx
    http://blogs.technet.com/b/projectsupport/archive/2014/02/25/project-2013-and-project-server-2013-service-pack-1.aspx
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Allow collaboration on un-published / checked-in project on Project Server 2013 and Project Online

    Hi All,
    Before a project is officially published specific resources in the project team need to be able to "collaborate" i.e. create tasks, change dates, etc. before the project is published. The complication is that we need this collaboration to happen
    on un-published / checked-in versions of the schedule. For example, the primary Project Manager adds tasks and makes changes to a published version of the schedule, saves and checks-in the project (doesn't publish), tells a secondary PM to go in and review
    the changes, the secondary PM should be able to see the changes the primary PM made, even though the schedule changes weren't published, be able to check-out the schedule, review what the primary PM did, make some more changes, save and check-in the schedule
    (again, without publishing it), and tell the primary PM to review. Then the primary PM could go, check-out the schedule, review it, save it, publish it, and check it in.
    Can Project Server 2013 or Project Online allow to do this? I looked into permissions and Server settings but I couldn't find anything that would indicate it is possible.
    Any help will be greatly appreciated!
    George

    Hi George,
    If you perform some tests, you'll see that even from PWA, the schedule can only be edited from the draft table. When you access the schedule in read only (as a team member for example), you see the published version, but as soon as you edit it (after clicking
    on the edit button assuming you have the appropriate permission), you'll open and update the draft version of the project.
    As far as I can remember (I don't have it in front of me now), you have a "line" in the schedule PDP (don't know how to call it in english) that will tell you if you are accessing either the draft or the publish version.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project server 2013 csom save and publish

    Hi,
    In Project server 2013 PWA when you edit project custom fields and save the queue job execute the following jobs: 
    - "Project Update from PSI"
    - "Project Publish Summary"
    - "Reporting (Project Publish Summary)"
    In my code (CSOM)  i can only use : " QueueJob Job = projChechedOut.Publish(true);"
    which is creating all these jobs:
    Project Update from PSI
    Project Publish Notifications
    Project Publish
    Project Checkin
    Prepare Project Web App Permission Synchronization For Projects
    Reporting (Project Publish)
    Project Workflow Check-in
    Synchronize Project Web App Permissions to Project Web App
    Synchronize Project Web App Permissions to Project Site
    Reporting (Project Sync)
    Is there way to "simulate" the save from PWA instead of fully publishing the project using CSOM,  because it is a lighter solution since my code is supposed to only set custom field value (if i only update, not publish it is written to the
    Draft) and secondly performance (less jobs) is better ?
    Thx in advance !!

    Hi,
    as an update to my post:
    - In PSI the method is project.queuepublishsummary(guid jobid, guid projuid)
    http://msdn.microsoft.com/en-us/library/office/gg200290.aspx
    the description says: Publishes the stage summaries of the specified project, in a partial publish operation.
    I am wondering if the equivalent method exists in CSOM. There is this method: PublishedProject.UpdateVisibilityCustomFields() but it seems doing exactly the same thing as publishing a DraftProject.
    Any ideas ?
    Thx

  • No PDP found after restoration of Project Server 2013 !!

    Hi All,
    I have an issue while performing database restoration of project server 2013. I have followed below mentioned two links for backup and restore procedure
    http://technet.microsoft.com/en-us/library/dd207307.aspx
    http://technet.microsoft.com/en-us/library/dd207305.aspx
    Everything works great ! restored successfully all projects, custom tables, group settings etc. But while opening the projects it prompts error that unable to find PDP etc something like that.
    Can anyone please help in such situation as how can we get the PDP pages in database restoration and what is the reason behind that ? Is there anything that I am missing?
    REGARDS DANISH DANIE

    Hello,
    Sounds like a new PWA site collection was created as part of the restoration? The PDPs are stored in the content database. If you are rolling over between environments (prod to test for example), see the post below:
    http://pwmather.wordpress.com/2013/05/02/projectserver-2013-environment-migration-rollover-steps-powershell-ps2013-msproject-sp2013/
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Which sharepoint service applications & services are required for Project server 2013 to work fine.

    HI,
    Can any one help me,
    I am planning to install project server 2013,  what are the service applications and Services ( Manage services on server in central admin ) in sharepoint  are required for project server 2013 to work fine, so that i will run only  service
    application and services to increase server performance..i don't want to configure all service applications  when i  am configuring.
    Thanks in Advance..
    vijay kommireddi

    Hi Vijay,
    If you are installing Project Server on SharePoint farm, You need to start the service Project Application Service which would be available after you install project Server 2013.
    For Project Server Reporting you need to start Excel service and Secure Store service.
    http://technet.microsoft.com/en-us/library/ee662106(v=office.15).aspx
    Thanks,
    Phani

  • Using multiple resource cost rates in Project Server 2013

    Greetings,
    We use Project Server 2013 to manage resources that often perform multiple roles within projects and also have different rates between projects. The Standard Rate from the user's profile is somewhat helpful but, as we all know, it carries over to every
    project that the resource is part of.
    I have tried opening Project Professional 2013 and using the additional Cost tabs in the user's information to enter different rates in tabs, B, C, D and E (tab A is the default Standard Rate from Project Server).
    My experience has been that as soon as I close and check in the project file, this data disappears. Next time I open the file the default rate is available but tabs B-E are blank. This behavior does not occur if I open a stand-alone project
    file not connected to Project Server. 
    I realize that Project is not meant to be a financial management tool and has its limitations but I'm looking for suggestions and would appreciate any feedback.
    Thanks
    Ray

    Dale is right in that an Enterprise Resource can only have its rates (or any details) set by the administrator. Unfortunately you are limited to 5 rates (A-E).
    I have done a macro for a client that reads rates for a resource for a project from a database (or Excel) every time the project is opened. So you see the correct rates and calculated costs.
    These rates get over-written next time you open the project, hence the need for the macro to update rates every time the project is opened.
    Another option in the macro is to zero the rates so a copy can be emailed to clients etc without sensitive rates data.
    Rod Gill
    Author of the one and only Project VBA Book
    www.project-systems.co.nz

  • Error while creating a Timesheet - Project Server 2013

    Hi everyone,
    One of user of PWA encounters an issue when he tries to create a timesheet. This error only occurs with a timesheet of
    a specific period, he can create all the other timesheet.
    So, when he creates the timesheet, this error occurs : "The timesheet creation failed, because of problems with Project Web App or with data validations"
    After reloaded the list of the timesheets, a link to go to the specific timesheet
    is available but if we click on it, we have this error :
    "View Failue - The view failed to load"
    I think , this error occurs
    because the timesheet is not realy existing even if we have a link to it.
    In the log (full log at the end), I've got this error :
    Exception occured in method 'TimeSheet.CreateTimesheet' System.ArgumentException: These columns don't currently have unique values.
    I've found this link with the same kind of problem :
    http://social.technet.microsoft.com/Forums/projectserver/en-US/b0a92afc-11fc-40ef-9a44-357d953b31f6/unable-to-open-or-create-timesheets-these-columns-dont-currently-have-unique-values?forum=projectserver2010general but I've checked and published all the
    user project but still have the error.
    Have you got any idea where are these columns ? How can I found them without checked every project of PWA ?
    Thanks,
    Patmol
    Full logs, for information :
    [bucketHash:E3B9DED0] Exception occured in method 'TimeSheet.CreateTimesheet' System.ArgumentException: These columns don't currently have unique values. at System.Data.ConstraintCollection.AddUniqueConstraint(UniqueConstraint constraint) at System.Data.ConstraintCollection.Add(Constraint constraint, Boolean addUniqueWhenAddingForeign) at System.Data.DataTable.set_PrimaryKey(DataColumn[] value) at Microsoft.Office.Project.Server.DataAccessLayer.Generated.TimesheetDalBase.ReadCustomFieldsForAssignments(ISet`1 assignmentUids) at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.ImportCustomFields(HashSet`1 assignmentUids) at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.ImportActualsAndCustomFields(IEnumerable`1 assignmentUids, ISet`1 userImported) at Microsoft.Office.Project.Server.BusinessLayer.TimesheetLoaderForGrid.Load() at Microsoft.Office.Project.Server.BusinessLayer.TimeSheet.CreateTimesheet(TimesheetDataSet dsDelta, PreloadType preloadType) at Microsoft.Office.Project.Server.Wcf.Implementation.TimeSheetImpl.<>c__DisplayClass45.<CreateTimesheet>b__44() at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions) StackTrace: at Microsoft.Office.Project.Server.Native.dll: (sig=6ea170d1-988e-4153-9f1d-0305c0ea0309|2|microsoft.office.project.server.native.pdb, offset=3C1E) at Microsoft.Office.Project.Server.Native.dll: (offset=1255D)
    Watson bucket parameters: Microsoft Project Server 2013, ULSException14, 070f6ea0 "project server", 0f0011db "15.0.4571.0", ea364808 "system.data", 0400766f "4.0.30319.0", 52310bef "thu sep 12 02:33:51 2013", 00000e02 "00000e02", 00000020 "00000020", 44395864 "argumentexception", 00101621 "aeby7"
    Error is: GeneralUnhandledException. Details: General Unhandled Exception in _TimeSheet.CreateTimesheet_ Attributes: System.ArgumentException: These columns don't currently have unique values. at System.Data.ConstraintCollection.AddUniqueConstraint(UniqueConstraint constraint) at System.Data.ConstraintCollection.Add(Constraint constraint, Boolean addUniqueWhenAddingForeign) at System.Data.DataTable.set_PrimaryKey(DataColumn[] value) at Microsoft.Office.Project.Server.DataAccessLayer.Generated.TimesheetDalBase.ReadCustomFieldsForAssignments(ISet`1 assignmentUids) at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.ImportCustomFields(HashSet`1 assignmentUids) at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.ImportActualsAndCustomFields(IEnumerable`1 assignmentUids, ISet`1 userImported) at Microsoft.Office.Project.Server.BusinessLayer.TimesheetLoaderForGrid.Load() at Microsoft.Office.Project.Server.BusinessLayer.TimeSheet.CreateTimesheet(TimesheetDataSet dsDelta, PreloadType preloadType) at Microsoft.Office.Project.Server.Wcf.Implementation.TimeSheetImpl.<>c__DisplayClass45.<CreateTimesheet>b__44() at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions) . Standard Information: PSI Entry Point: Project User: i:0#.w|wavenet\cev Correlation Id: 9709e41b-9a18-e411-941e-00155d029b05 PWA Site URL: http://intranet.wavenet.lan/PWA SA Name: Project Server Application PSError: GeneralUnhandledException (42), LogLeve...

    Hi Patmol,
    Have you tried to go to the previous or next timesheet and then navigate with the "previous period" or "next period" to the timesheet in question.
    Also have you tried to open it using a delegation session?
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Issue while installing Ms Project Server 2013 on MS Server 2012 R2 with Sharepoint Server 2013

    Hello MS Support Team,
    I installed SQL server 2012 & Sharepoint server 2013 and after that the MS project Server 2013 is not installing on the same server -- pls hv a look the enclosed screenshot. sent at [email protected] and guide me to resolve it on priority.
    A windows poped up - Installation Error - This Project requires MS Sharepont Enterprise edition... (Which is not available on the MSDN Server)..only standard edition available.
    Please reply asap @ [email protected] - Call @ 0120471384
    Kind Regards,
    Vinay Bhardwaj
    Network System Administrator - GREC (IN)
    Rockwell Automation | A-66, Sector 64 | Noida | India
    LISTEN. THINK. SOLVE
    IP : 71384 | E : [email protected] | W : www.rockwellautomation.com

    Hi Siriosus,
    Indeed you do need Sharepoint Server 2013
    Enterprise for Project Server 2013.
    See article below where it is mentionned:
    Project Server 2013 requires the Enterprise edition of SharePoint Server 2013. Prior versions of SharePoint Server and SharePoint Foundation 2013 are not supported.
    http://technet.microsoft.com/en-us/library/ee662114(v=office.15).aspx
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project Server 2013 on Windows Server 2012 R2

    Can we install Project Server 2013 on Windows Server 2012 R2? Is it supported? I searched a bit but couldn't find any concrete information if it is supported or not.

    From the article:
    http://blogs.technet.com/b/office_sustained_engineering/archive/2014/03/03/announcing-availability-of-slipstreamed-office-2013-and-sharepoint-server-2013-with-sp1.aspx
    Today, aligned with the SharePoint Conference, we’re announcing availability
    of a slipstreamed SharePoint Server 2013 with SP1. SharePoint administrators
    will be able to use this updated installer to deploy on Windows Server 2012 R2.
    which I got linked from the following
    http://blogs.technet.com/b/projectsupport/archive/2014/02/25/project-2013-and-project-server-2013-service-pack-1.aspx

  • Task custom field and formula custom field don't correspond Project Server 2013

    Hi people, I have an interesting case in Project Server 2013 SP1 CU Apr:
    I have a custom task number field called AM. This field get's filled by a PSI action with actual material costs from an external system.
    I also have a custom task cost formula field that is called AM*. This field is a formula field that has the formula [AM]. And summary tasks use the formula field as well.
    As soon as I create a project, assign costs in the external system and let PSI fill the values within AM I get correct values in AM. But nothing is calculated on AM*. If I edit the project in the browser and publish, check in and revisit the project
    AM* still isn't filled.
    If I open the project in MS Project Pro the calculation comes through nicely, however I do not want to use MS project Pro to see correct data in browser.
    Some tests I have already done:
    I have noticed that when I create a new calculated task field AM2*, this get's calculated correctly on the already existing task.
    I have also noticed that opening the custom field in server settings and just saving the field creates correct values on AM*.
    What is going on? I don't want to save the custom formula field every day... There are 11 custom formula fields in the environment at the moment.

    Hi Gary,
    Thank you for the quick response. Please note that the fieldnames are [AM] and [AM*]. There is a difference in field name due to the astrix. However I did think about the situation and changing one of the field names all together didn't do anything for the
    situation at hand.
    It looks like some kind of refresh thing, because without changing anything in the custom field just saving the field in server settings will turn op good values. However, values already turned up good in Project Professional 2013. And that suggest
    that there is a calculation error on the PWA side wouldn't you say?
    Anyway, thank you for taking time to look into this matter.
    Erik

  • Project Server 2013 - This webpart was unable to load

    Hi all,
    I am getting the following error in project server 2013 project sites:
    This webpart was unable to load. For more information, please contact your server administrator.
    <Guid>
    I only get this error message on 'Project Summary Web Part'.
    Any idea what it could be?
    Thank you,
    SJ

    Hi there!
    I got similar problem in a PDP that was working perfectly even after migration to 2013. On this case, my PDP was showing the webpart that let you to choose what fields and custom fields want to show on a specific PDP.
    I created a copy of the crashed PDP and got the same error. So I bet for remove all the custom fields and add one by one to see what happens. The surprise came up when it started to work when my PDP had just pair of custom fields. With this procedure,
    I found that the problem was on some specific custom fields created that had null values to all the projects created before. Once I forced value on those fields it worked properly!!
    Sometimes EPM2013 has a very strange behavioural and in some cases just clicking on EDIT and SAVE  without any change have solved some of my problems too.
    I hope it helps this to you and feel free to contact me if I can somehow help you :)
    Diego

  • Can't open Project Server 2013 word documents with office 2010 installed

    hello forum members,
    we having issues opening a word document in a Project Server 2013 . we have Office 2010 on our computers installed. 
    when I click on a document link, i get a message "The webpage cannot be displayed".  the only way to open a document is to right click on link and select "Open". 
    Does Project Server 2013 require Office 2013 installed? If not, is there a way to open documents in Project Server 2013 without right clicking on links?
    tatiana
    tatiana

    Hi Tatiana,
    This is the know issue. I have experienced this issue with one of our client. The cause of issue as below -
    Scenario
    You have 2007 Microsoft Office installed on a computer.
    On the same computer, you also have a Microsoft Office 2013 application installed, such as Microsoft Lync 2013 or Microsoft Word 2013.
    SOLUTION
    To work around this issue, remove the Microsoft SharePoint Foundation Support program component from the Office 2013
    installation on the affected computer or computers. To do this, follow the “Install or remove individual Office program components” section of the following Microsoft Office website:
    Install or remove individual Office
    programs and components
    (http://office.microsoft.com/redir/HA010354261.aspx)
    After you complete these steps, repair 2007 Office. For more information about how to repair the installation, click
    the following article number to go to the article in the Microsoft Knowledge Base:
    924611
    (http://support.microsoft.com/kb/924611/ )
    How to install the individual 2007 Office features or to repair the installed 2007 Office programs
    Note When
    you follow these steps, set the Microsoft SharePoint Foundation Support
    component within Office Tools to Not Available.
    This solution doesn't apply to scenarios in which SharePoint Designer 2013 is installed on the affected computer.
    You can find further details here at Microsoft support site -
    http://support.microsoft.com/kb/2888015
    Hope this helps you.
    Cheers, Badal

Maybe you are looking for

  • How to reinstall 10.4.11 without disk

    how to reinstall mac os x 10.4.11 without disk

  • Need info on Universal worklist

    Hi all, Need some info on universal worklist - 1. What is Universal worklist? 2. How do we configure it? If someone has some good documents, please mail them to [email protected] Kind Regards, Ashwini.

  • Check In documents using BAPI

    Hi Forum, I hav a scenario like, I hav to perform check in/out da originals in to vault using 3rd party application. m using a  BAPI DOCUMENTCHECKIN2 to run the above scenario. once i executed da bapi i got return value as 000 and then i run Commit b

  • ABAP Joins or Separate select statements?

    Hi,    I am working on a simulation of an implementation project as part of my in-house training programme. I am a rookie to ABAP and am now doing a print program that requires master data selection from tables ANLZ, LFA1, MSEG and CSKT, and also rel

  • When I try to download a trial version of any of the Adobe programs I get a blank page

    On Mac I have tried downloading via the Firefox, Chrome, Safari, Opera. Via PC I have tried with IE11, Chrome, Safari, Firefox. Both my computers are connected to different internet connections so I know it's now a network issue.