Project system; external processing costs flow in cn41?

Dear PS gurus,
Kindly help in giving solution how to activate/get the costs flown materialwise or services in external processing of network.
in CN41, costs in External processing of Newtork are flown at header level is., material level or Service level only. but line items of materials or services are coming in report (cn41), the values of planned costs or actuals costs are not flowing in line itemwise.
pl help
Thanks & regards
Srihari

Hi pp,
we make pr- thru network only in external processing for material/service.
eg; in ext. processing purchase materials -
>
in component overview i give material 1 - rs. 10
material 2 - rs. 20
pr is created per line itemwise and two pos made or single po
in cn41, we get only
                                      planned costs  actual costs
purchase maetrials               30                    30 (after migo-gr)
material 1                             0                       0
material 2                             0                       0
my requirement, how i can get Rs. 10 for material 1
Rs. 20 for material 2
hope i have clarified, pl let me know how i can get values line itemwise either materials or services.
pl note pr material is line itemwise only
regards
regards

Similar Messages

  • Production Variance Analysis for External Process Cost

    Dear all,
    We are on 4.7 R3.
    In production order we have routing/operation with mutliple external processes. The problem is production order cost analysis (CO03) displayed the external process cost variance in lump sum (it adds multiple external processes cost into a single line).
    We need to be able to analysis the external process cost variance by each process. We want to generate a report that displayed the external process cost variance for each processes, however in table COSPA there is no information of the external process name, it also displayed the cost in a lump sum amount.
    How to enable the external process cost variance by each process? What table capture the external process cost with the information of the external process name/ID?
    Thank you very much in advance for your kind assistance.
    Rgd,
    Dahlia Tan

    Hi
    Use KKO0 reports..
    Assign Cost Comp Structure in OKN0 and choose Prod Group = Material Group in OKN0
    Transport these settings across to all clients...
    Run KKRV to collect data and then run KKO0 reports
    Br, Ajay M

  • Project System - Report Painter - Cost roll up issue

    Hi,
    We have an issue with the roll up of the costs in Report Painter report in Project Systems. The problem occurs only with those costs which have been settled to an internal order from a WBS element.
    We are using the same cost elements to settle to the Cost Center and Internal order and roll up of the costs work fine for those settled to cost center. But the roll up does not happen for the costs settled to an internal order. Would appreciate if someone can guide on how to fix this issue.
    Raj.

    Here are the values:
    Period/year     000.1900     Remainder 1900     PERIO     Period/year
    Value Type     4     Actual                                                 
    Value Type     10     Statistical Plan                                                 
    Object ind.     P     Project item                                                 
    Object ind.     1     Order plan values: appended, apportioned     9     Order values: not appended, deleted
    Debit type     1     Costs and credit-side payments                                                       
    Thanks for your help.
    Raj/

  • Project Systems: Profit and Cost Centres

    Hi
    When maintaining a WBS element through transaction CJ02 or CJ20N for example; it is poossible to link a profit centre, ressponsible cost centre and requesting cost centre to each WBS element.
    My question is: When cost gets incurred against a WBS element the profit centre gets updated with the cost as well. However, the cost centres (responsible and requesting) do not get updated. Is there any automatic effect on these cost centres (such as is the case with profit centres)?
    I know that the requesting cost centre will be the cost centre allocated to AUC's assigned (if applicable) and that to get cost onto the cost centre a settlement rule must be maintained. What therefore is the use of having responsible and requesting cost centres assigned to a WBS apart from this?

    Hi
    Cost center and WBS elements are both cost objects hence at a time real posting can happen to only one of them. Since WBS elements are getting debited , it will not simultaneously debit a cost center. However profit center it is not the case , hence the data flow to the profit center happens as an when a posting is done to WBS element and also when WBS is settled to cost center then also there will be a posting to profit center.
    Anand

  • Project system network activity cost distribute

    it is possible that i distribute the plan cost of external network activity to period wise. if yes then how ..........
    thanks

    Hi
    You can't plan the cost of external network activity period wise. The lowest level you can plan period wise is WBS Element level.
    Regards,
    Suraj

  • How to allocate external process cost on the units of Production order

    Hi Gurus,
    I am facing a cost allocation issue.
    The scenario is a make-to-stock scenario in discrete manufacturing industry. I am using production order (PP01) and confirming the material issued to production and operations manually. There is an electrical cost incurred by the client. The total cost of electricity is allocated on the number of units that comes out from the production. Say, total electrical cost is 1000, number of units produced using the production order is 100, then per unit is charged 10 (1000/100).
    Can anyone help me how can I perform the cost allocation? Should I go for an activity type in work center OR should I use the cost sheet. Kindly help me.
    Thanks and Regards,

    Hi
    activity type would be better choice...
    Ajay M

  • How can we explain the process from project system to final asset

    Dear masters,
    how can we explain from project system to final asset flow in the configuration level.
    thanks
    Moderator: Please, refer to basic SAP material

    Hi,
    Project & its related WBS will be initial cost collector (i.e invoices are booked against them). Once the status of Project/WBS is set to tech complet and AUC is assigned in the settlemnet rule. That particular asset record will recive values when we run the suttlemnets.
    This is an broad line view. Specific will depend on case to case.
    Thanks
    Vaibhav

  • Sales order with project system

    Hi,
    Is any one can explain for the mentioned scenerio pl:
    In production cost by Sales order, is production / process order will be linked for production booking or always is it best to implement the make to order with project systems - Sales & Process / production order is used as WBS element?
    Also, can u pl. exlain me how to activate the same?
    Rgds
    SMK Ganesh

    Hi,
    Is any one can explain for the mentioned scenerio pl:
    In production cost by Sales order, is production / process order will be linked for production booking or always is it best to implement the make to order with project systems - Sales & Process / production order is used as WBS element?
    Also, can u pl. exlain me how to activate the same?
    Rgds
    SMK Ganesh

  • Regarding configuration cycle for sales order linking with project systems

    Hai Sap professionals,
    i have a scenario like engineer to order. where i manufacture PC's for my customer as per their request.
    Some may order AMD's and some Intel processor etc... now how i should start linking everything a brief idea if any can tell it will be helpful...
    with regards

    hi,
    In make-to-order production with cost management using a project, all costs and revenues relating to the make-to-order item are collected and allocated to a project in the SAP Project System. The costs are allocated to profitability analysis.
    Prerequisites
    Make-to-order production is controlled by the requirements type. The requirements type is determined on the basis of the MRP group and the strategy group in the material master record.
    Up to Release 3.0, the requirements type is determined on the basis of the item category. For this reason, special item categories are used up to Release 3.0 for controlling make-to-order production. To carry out make-to-order production for a material with cost management using the project, you must maintain the following fields in the material master:
    MRP 1
    MRP Group
    MRP 2
    Strategy Group
    Screen
    Field
    In addition, a plant must be assigned for make-to-order items in the sales order.
    for detailed set up please refere the foll link:
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/dd/5600b1545a11d1a7020000e829fd11/frameset.htm
    regards,
    Siddharth.

  • Project system planned quantiy

    Hi all
    I maintain the unit cost price and quantity at general cost activity master data but problem is that the quantity is not show in any reports. please guide me. is this any configuration problem......
    thanks
    shabbir

    This is related to project system activity(general cost activity) not controlling activity type.
    i need report that show the plan quantity that maintain in ps activity master data .....
    thanks

  • Regarding the process flow of project system

    Dear Sapgurus,
    I am working new ps project in our client place . The process which i mentioned for a ps flow is sales enquiry,
    design approval, procurement, production, deliveryetc apart from this anything i mention so i request anybody to suggest the business process while starting a customer project and new project development.
    regards,
    muralidhar.t

    Dear Murali,
    Welcome to PS World.
    See link which is given by Venkat Sir.(It shows process)
    Its very tough to explain whole process.
    Plz refer this link.
    Deffntly it will help you.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/80/ea89395eb58c4f9d0c3e837cf0909d/frameset.htm
    PS cycle
    Re: Enterprise structure for PS
    Re: Why we use Project system?
    Regards
    Chandra

  • Product Costing:External Processing

    Hi Gurus,
    My doubt is I am comparing standard cost estimates of production client with another client which is its copy. The product cost estimate of a material, the cost component 'External Processing' is showing value 700 in PN client and 1000 in the New client. The cost element for 'External Processing is 700000000H as primary cost element and another as secondary cost element. I tried checking the GL account report in FBL3N regarding the postings happened in the GL accounts.
    1. My question is why there is a variation of 700(of PN client) and 1000(in NEW client).
    2. The second question is, from where these values are flowing.How we can trace back the flow of values for this particular cost component of External Processing' of a material cost estimate?
    Is it anyway related with Exchange Rate differences? If so, how and where it is linked?
    I'll be really grateful for your answers.
    Looking forward for you reply soon.
    Thanks,
    Prithwi.

    Hi,
    I have checked the valuation variant 001. The startegy sequence is same only. There's no change in configuration settings as the new client is copy of production client only.
    I wanted to know, the 'External processing' data or values from which.postings. How it gets picked up and how we can check its origin?
    Thanks in advance for your help.
    Prithwi.

  • How to pass process flow input parameter to unix script external process

    Hi,
    I'm trying to pass a process flow input paramter (string) to an external process which is a unix script. I've been working on this for the last 2 days but can't get it to work. Here is the design. I have a process flow with 3 maps that create a file in the unix file system. I have a suffix, which is an input parameter to the process flow, that will need to be passed to the unix script to rename the file appending the suffix to the filename. I've tried different things and nothing works for me. Has anyone done something similar in OWB?
    Thanks much!

    I tried using useBean inside the Jsp for this.
    But following error comes:
    OracleJSP error: oracle.jsp.parse.JavaCodeException: Line # 13, oracle.jsp.parse.JspParseTagExpression@102e37e
    Error: Java code in jsp source files is not allowed in ojsp.next mode.
    Please explain why?
    How can set POST request params when calling to an external servlet?

  • Problem in Assembly Processing in Project System

    Hello All,
    My Client want to implement Assembly Processing. We have configured the system as per SAP Standard. we are testing this in Quality System along with SD & PP Modules. we have template which contain Material WBS Process WBS & Other Cost WBS But we are getting all cost of material and process cost on one Material WBS after Production order confirmation. How can we divide this cost separately for Material & Process WBS.
    As SAP Standard Process we maintained activities for different process also but when we tested this we are not clear about the use of these activities. We are not getting any cost or don't have any relation in any way for these activities.
    Please Help me about this Assembly Process.
    Thanks
    Warm Regards
    Sunil

    1. Create a Inquiry in VA11 --OK
    *2. Create Quaotation in VA21 wrf to Inquiry*--OK
    3. Create a Sales order in VA01, while creating sales order, as soon as we assign the material component in SD line item a pop will come for entering std wbs, std ntw, network profile. once we enter this at bottom we can see that scheduling is carried out. Note: if we define material/std wbs/std ntw in CN08 then pop will not come. Now check for errors and save the sales order, at bottom we can see that project order is created. Note: Project number is same as sales order no:---OK
    4. in Billing plan tab at item level we can see the milestones for new project.--In sales order i don't see any milestone or any type of setting. can you please tell me about this we are not able to execute milestone billing in our case.
    Ans to Query: For Milestone billing to work you need to do the following settings in SAPSD
    1.     Create Billing Plan in SD and assign the Billing Plan to Sales Document type you are using. Path: IMGSDBillingBilling Plan
    2.     In the above node , do settings for Define Billing Plan Types, Define And Assign Date Categories, Maintain Date Proposals For Billing Plan Types, Assign Billing Plan Types To Sales Document Types, Assign Billing Plan Types To Item Categories.
    By doing above settings you will get an additional tab u201CBilling Planu201D in Sales order where you can get the milestones generated for new project. For exiting project you can copy milestones to SD from project.
    If you want Billing Plan at sales document item level, assign the billing plan type in Item category.
    5. In Sales order we can see that billing lock is set against the milestones.---Not Found
    Ans to Query: By doing the above settings as in slno 4, you can see the billing block against the milestone*6.Now open the project in Cj20n and go to network we can see sales order no with line item no.*---OK
    7. Now verify the mile stones in the project.--Adding milestone but no effect in billing
    *Ans to Query : you can see that milestone no in Sales order and Project will be same. Note: Subject to in your standard network you should have milestones, so that we you create a sales order new milestones will get generated wrt to milestones in Std network. So when project is created you can see mile stones are also created.*8 .check the requirement list in MD04 against the Finished product we can see that requirement is generated againt project wrt to sales order.---No requirement is displayed .
    To generate the requirements. Check the settings in requirement class.
    9. Run MRP in MDBT/MD02/MD01, based on procurement type in MM , PR's and Pld order will generated. Note: ALL PR's and PLD Orders are account assigned to WBS.---When we execute this MRP this is not picking requirement from project. BOM created by CS01. if we assign material to activity than this MRP is picking requirement from project.
    10. Now do Pr>PO>GR>(ALL all accounted against project.--OK
    11. Convert Pld order to Production order> release the order> Goods issues against production order.--OK
    12. Confirm the Procution order wrt routing operation one by one in CO11N.--OK but we want sageregated cost for material cost and process cost to different WBS as we have material WBS and Process WBS.
    Ans to Query: This is not possible because in Assembly order processing single account assignment is only possible for the finished products, and for that finished product routing is also account assigned to the WBS assigned to Production order. So operation cost comes and sits in same WBS. If at all you want to track separately you can  transfer the actual cost for process to process WBS in tcode:KB11N
    Using KB11N tcode we can manual transfer cost from one WBS to another WBS.13. in cost element reports at projects we can see the cost breakup for all production activities as well as for material.--you mean CJI3 report 
    *Ans to query: Yes you can see in CJI3 report or in SALR_870135452 report also_*14. settle the production order.----where to settle this production order? and how?
    *Ans to Query: For assembly processing account assignment is u201CQu201D so automatically in production order we can see the settlement rule is set against the WBS. So the cost from production order is settled to WBS and subsequently from project to the respective receiver as per settlement rule in project.*
    15. conform all activities in Project.----OK CN25 or CJ20N
    In any of the above tcodes
    16. Do billing in SD as when when mile stone reaches to post actual revenues.----OK
    17. run RA in KKA2 and save the RA results--OK
    18. Run settlement in CJ88 ---Not using any settlement
    19. set the status of Project as Teco and Clsd.---OK
    Please let me know if you need more clarifications
    Regards
    kishore
    Edited by: Virendra Pal on Jun 1, 2011 11:53 AM
    Please do not use bold and underline text message short cuts etc - in future your posts will be removed
    Secondly all that you are mentioning is available in SAP Help or in the wiki

  • Cost flow in Refurbishment process

    Hello Guru,
    can you plz explain me below Refurbishment process more of in accounting side, ie. I want to know how cost flows?
    1.Create Refurbishment Order.
    2.Issue Damaged material (Movement type 201)
    3.External service procurement
    4.GR for External Services. - what is impact of this amount on material?
    5.GR for Refurbishment material (Movement type 101) - how the amount get calculated? Is it a Moving Avg Price of Material?
    (can both cost incurred in step 4 & 5, will get settled against material?)
    6.TECO of Refurbishment Order
    7.KO88 of Refurbishment Order
    If anybody can explain with example then its good for understanding.
    Thanks in Advance.
    Regards,
    Amol.

    Hi Maheshwaran,
    Thanks for reply but my question is little bit different from the link which you mentioned. for ex.
    Material - ABC
    Cost are C1(New) - 1000 INR & stock -1
                   C2(Damage) - 0.01 INR & Stock - 1
                   C3(Refurbished) - 600 & Stock - 2
    Material sent externally for Refurbishment & the service cost is of 400 INR
    Internal Labour cost &  material cost = 0 INR
    1.Created Refurbishment Order -> Planned & Actual Cost = 0 INR
    2.Issued C2 material against Order -> Planned & Actual Cost = 0 INR
    3.GR for Services of 300 INR      -> Actual Ext service Cost = 400 INR
    4.GR for Refurbished Material C3 ->Actual Material Cost = ? (i think its -600 INR, moving avg price of C3, which will get credited to order)
    5.Order Confirmation = 0 INR
    6. TECO
    7. KO88 =? ---How much cost will get settled against Material ABC & after settlement, how much will be the moving avg price of C3 material?
    Regards,
    Amol.

Maybe you are looking for

  • Using TransX to load data -- unsuccessful

    Hi everybody, I am trying to use TransX to load into the database some sample data provided by Oracle, but the attempt is unsuccessful. First, I have the following sample XML schema registered successfully into Oracle: XML Schema: <?xml version="1.0"

  • Regarding Mail step in a workflow.

    Hi All, I have a Mail step in the work flow and the mail needs to be send to all people in a particular position. But the position number is not a static one it is determined dynamically in back ground step and is available in an element of the workf

  • Is System.gc() recognized in AIR 3 for iOS ?

    is System.gc() recognized in AIR 3 for iOS ? Or am I putting on a line a code that's just for pasterity ? I have made every effort to dispose(),null and removeEventListener any unused Object, hence to be able to tell the Garbbage Collector to "go ahe

  • 7510 e-ALL-IN-ONE not printing black ink.

    I have a Photosmart 7510 e-ALL-IN-ONE printer that has worked beautifully until the last time I replaced the black ink.  The printer screen says the ink cartridge is full, yet nothing will print.  I checked the vent on the cartridge, it seems to be f

  • Best backup program for iPhone 3GS??

    I am looking for the BEST backup program for the above - not only a program which makes backups of the programs, but ALO the contents of the programs - of everything! Any recommendations, thanks!