Hi
Can you please guide me what exactly is the role of an BW consultant.. For ex: One XYZ  company is Using BW3.1 c now they want to upgrade the systems to BW 3.5 . In this scenario what is the role of an BW consultant and what exactly we are going to do...
Please send any kind of documentation to my mail id <removed> regarding Upgadation of project.
Thanks & Regards
Ajay

Hi Ajay,
Please go through this document: How to SAP BW 3.5 Upgrade Prep and Post- Upgrade Checklist
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/472443f2-0c01-0010-20ab-fbd380d45881
Hope this helps...

Similar Messages

  • Upgrading a project from Weblogic Integration 8.1.3 to Weblogic Integration

    Can anyone offer any advice to assist me in upgrading a project from Weblogic Integration 8.1.3 to Weblogic Integration 9.2.1?
    Here are some nuances of the project:
    * The JNDI, JDBC, & JMS server resources are secured; access is controlled by Deployment Descriptor run-as/security-role/... tags and custom CSPs
    * The application is currently build for deployment using wlwBuild ant task (class in workshop.core.WlwBuildTask which is located in the 8.1.3 {weblogic.home}/workshop/wlw-ide.jar - so far I can't find this class/task in my 9.2.1 install)
    * The following are the application characteristics (and utilized WLI features): multiple web apps, EJBs, JMS, Page flow/netUI, web services, WLI controls (process, java, transformation), XMLBeans
    * One of the project goals is to not make any functional changes and modify as little code as necessary (the only expected justification for a modification is a) fallout out from the JVM 1.5 upgrade or b) something is no longer available in WLI 9.2)
    I know there is a edocs page with a tutorial for upgrading from 8.1.4 or 8.1.5 to 9.2, but I am interested in knowing if anyone has insight on upgrading directly from 8.1.3?
    Thanks in advance for any and all assistance.
    Regards,
    Andy Frank

    just as a followup to my original message.. regarding the 8.1.4 install log that had all the warnings with the msi it expected and the different one it found... at the bottom of the log..this is what I got;
    Property(S): SourcedirProduct = {AC76BA86-7AD7-1033-7B44-A81300000003}
    MSI (s) (6C:30) [11:11:23:828]: Product: Adobe Reader 8.1.4 - Update 'KB408682' installed successfully.
    MSI (s) (6C:30) [11:11:23:828]: Product: Adobe Reader 8.1.4 -- Installation operation completed successfully.
    when i go into adobe reader -> help -> about i stillget 8.1.3

  • Error when trying to upgrade a project to RH9

    I'm attempting to upgrade a project from RH 8.0.2 to RH9. My other projects have upgraded fine but I have one particular project that is giving me the following error:
    Error - node %Rel_420_NeoTool_Product_Help/rhsharedresource.apj already exists.
    I have the source of the projects kept in RoboSource so after I click OK, I get the following message:
    Cannot check out all the files that needed to upgrade this project.
    I noticed that this file does not reside in source so I figured that RoboHelp created it so I tried to delete it but am getting the same error.
    Any ideas would be greatly appreciated.
    Thanks

    Thank you Mona for your suggestion. Unfortunately it didn't work. The rhsharedresource.apj & SearchOptions.xml files do not exist in source in either the root or the branch but I deleted them from both local projects (root and the branch) and attempted the upgrade and received the same error message.
    Answers to your questions:
    Steps I took to upgrade
    I upgraded the root project first by opening the project on my local machine and when presented with the dialog that this project was created in an older version of RoboHelp, I selected the Upgrade button.
    RoboHelp automatically checked the files out of source and performed the upgrade and all was well with the root.
    Next I opened the branch on my local machine using RoboHelp.
    When I received the message that it was created in an older version, I again selected Upgrade.
    It churned for a short time and the bottom of the RoboHelp window says, "Adding Files(s) to Version Control Project" then I get the error message that rhshaerdresoruce.apj already exists.
    When I click OK on the error dialog, I get another error dialog that says "Cannot checkout all teh fiels that needed to upgrade this project"
    Checking out of source
    Based on your questions regarding starting from source I tried the following experiment which also unfortunately didn't work:
    I checked the entire branch project out of RoboSource before attempting to upgrade.
    Deleted the rhsharedresource.apj and SearchOptions.xml file from the local version.
    Opened it in RoboHelp and selected to Upgrade when presented with the dialog that the project was created in an older version of RoboHelp.
    I received the same error messages.
    Branch Properties
    I'm not entirely sure what you mean by Branch Properties but here is a screen capture of the Settings tab. On the Rights tab all items are checked. There is nothing in Notes. The Local Path tab has the location of my local copy. The Links tab lists my root project $/Operations Monitor_help
    Thank you for your assistance,
    Nita

  • RH8 won't upgrade RH7 project. He'p Me!

    RH8 starts, and then I open the RH7 project, and then RH8 says it will "upgrade" the project, and then it says "Error reading RHFrameStyleMappings.apj file". Yes, that file exists, size 0, in the local copy of the project. I have not set up RoboHelp Server 3.1 to point to the server, yet. What do I have to do to get moving? Thx.

    Hi Eileen
    In one thread you were talking about four files that were not present in the upgraded project and RoboHelp was giving you grief about the four missing files. I suggested you create a totally new project to create them and copy the missing files to the upgraded project.
    I'm not sure I saw a reply from you as to whether you had tried this or not. As you still seem to be stuck, I'm guessing that this failed? Or that perhaps you failed to see it? I was curious if what I suggested was a possible workaround.
    Cheers... Rick
    Helpful and Handy Links
    RoboHelp Wish Form/Bug Reporting Form
    Begin learning RoboHelp HTML 7 or 8 within the day - $24.95!
    Adobe Certified RoboHelp HTML Training
    SorcerStone Blog
    RoboHelp eBooks

  • Jar will not launch after upgrading a project to Netbeans 6.5

    Hi,
    I created a project in NetBeans about 2 years ago, then I upgraded the project to NetBeans 6.5 just now. The .jar file that is created when I build the project gives me the error:
    C:\>java -jar Checkers.jar
    Exception in thread "main" java.lang.NullPointerException
    at sun.launcher.LauncherHelper.getMainClassFromJar(Unknown Source)
    at sun.launcher.LauncherHelper.checkAndLoadMain(Unknown Source)
    If I create a new project in NetBeans, the jar file it creates will work correctly. It seems to be something related to the upgrade or maybe the state of the original project (I didn't try the .jar file when I was running with the old version of NetBeans.)
    Anyway, I need to know how to make the fix from within NetBeans. I look at the project properties and there is an entry point defined. It runs fine from within NetBeans. I don't know what changes to make in the project config to fix this.
    Thanks,
    Bill N.
    Cincinnati, OH

    First, these forums are for Java language questions, not NB configuration and support questions. If you wish to pursue this question further, please do it at the NB site.
    NB has tutorials and FAQs that show how to configure a project so that it can be executed outside of the NB IDE.

  • Regarding Upgrade

    Hi Guru's,
    I have two doubts regarding upgrade work.
    1. when we are doing unicode remediation for the obslelute function modules, if in older system if they handling any exceptions how we can handle those in ECC new system. I mean to say if they are displaying some messages according to the exception how we can handle??.
    2.Describe field statement with addition in CHARACTER MODE or BYTE MODE?..When to use CHARACTER MODE and when to use BYTE MODE??
    Please clarify..
    Thanks & Regards,
    SASTRY R.

    Hello,
    1. When replacing a obsolete function module, if any exceptions are handled, you will have to manually map those exceptions in the newer function module and handle accordingly.
    2. The type of the field on which the DESCRIBE statement is used will determine if it should be a CHARACTER or BYTE mode. If the type is C,N,D,T,S go for character mode else BYTE mode.
    Vikranth

  • Upgrading from Project Server 2010 to 2013 ConvertTo-SPProjectDatabase gives error (Convertto-SPProjectDatabase : Action 15.0.38.0 of Microsoft.Office.Project.Server.Upgrade.PublishedDatabaseSequence)

    Getting the error on subject line when I try to upgrade from Project 2010 to 2013

    Hi,
    Do you get and error when the command is executed or when you try to start the execution (the command is not valid)?
    If you get the error when you try to start the execution, I would suggest re-typing the command and make sure all parameters are valid.
    Please give us the error details if you get the error when the command is running
    Paul

  • This is regarding upgrading problem

    Hi,
    This is regarding upgrading problem.
    I am Upgrading 4.7EE IDES to ECC 6.0 but I got the problem with Solman key
    When I given the Solmman key it shows illegal solman key. what is the problem ?
    system Id    -
    >   F06
    nstance number --->    30
    Hostname is -
    >      saibaba
    Thanks,
    Narshiha rao

    Hi,
    You genereate new solman key according to your system name and put that. This will work very well. Because when we create solman key then we have to define what is server name etc.
    Anil

  • Regarding Upgrade project

    Hi I want to know about upgrade project from 4.7 to ECC 6.0.
    The points to be known is........
    1. What are the steps to be followed during upgradation?
    2. Any phases are there in an upgradation?
    3. In an ABAP program run what are the statements giving the problem (Few examples)?
    Help would be appreciated.
    Thanks in advance
    Ramesh

    Hi Ramesh,
    When we go for upgradation, first we read upgrade guide thoroughly and implement accordingly then we will do very fast and with out problem. Please ready carefully and implement.
    Regards,
    Anil

  • Info regarding upgrade project

    Hi Experts,
    am going to join to do upgrade project (ECC6.0) till now i ve worked on up to 4.7 only, so what is required knowledge for upgrade project.
    and what is unicode is it required for this?
    Thanks in advance.
    sudha.

    Hi,
    ECC 6.0 does not support MDMP installations. For those systems, a Unicode
    conversion needs to be done before the upgrade to ECC 6.0. A combined Unicode
    conversion / release upgrade is another possibility. In such a project, the system is
    upgraded to ECC 6.0 and migrated to Unicode in one step.
    All this does not apply to your environment. Non-Unicode, single code pages systems
    are still supported in ECC 6.0. You have to option to an upgrade to ECC 6.0 and migrate
    to Unicode at a later stage. If you want, you can also do a combined Unicode
    conversion / release upgrade project which does both in one step.
    I cannot predict the expected downtime as it depends on many different factors such as
    the database size, size of the biggest table, number of CPUs and amount of memory in your system.
    OR Check these links....
    http://searchsap.techtarget.com/expert/KnowledgebaseAnswer/0,289625,sid21_gci1242699,00.html
    http://www.saptechies.com/upgrade-from-sap-47-x110-to-ecc6/
    for upgradation project guide.....
    http://www.sappressbooks.com/product.cfm?account=&product=H2903
    Reward points if useful....
    Regards
    AK

  • Looking for the New Upgradations in Project Costing from 11.5.3 to 11.5.10

    Hi All,
    Iam looking at the New Features added in Project Costing as we need to give a demo for the client on the advantages of Upgrading from 11.5.3 to 11.5.10. any record on these lines would be of great help to us.Appreciate your kind suggestions in this regard.
    Thanks in Advance,
    Satyam Team

    Hi, a basic brief of the upgrade the principal steps are:
    1.- Cloning your 11.5.3 OEBS to a new server (IBM AIX 5.2), with similar characteristics to the final server in Production.
    2.- To continue with the steps described in the note of metalink 316365.1 - Oracle Applications Release 11.5.10.2 Maintenance Pack Installation Instructions.
    3.- To do a set of tests that include cycles of revenue and expenditures, this way as technical tests, and review all customizations.
    This basic step must be led to end in an environment of test, and when all the tests certified the environment , to do it in production server.
    Good Luck

  • Benefits of upgrade from Projects 11.5.6 to 11.5.9

    I'm trying to define the functional benefits for a client organisation of their impending Projects upgrade from 11.5.6 to 11.5.9. Can someone tell me the main benefits of this please?

    Hi,
    There is a lot of new functionality added in 11.5.9
    That was not included in 11.5.6.
    I can recall the following:
    1. Bugetary Control
    2. Customer Retention Billing
    3. Receipt Accruals
    4. Automatic expenditure batch reversal
    5. There is a web enterface for projects.
    6. You can run your project in any currency
    7. You can run your budget and agreement in any currency
    8. Changes in client extensions. (Transaction Control ect.)
    9. Issue management
    10. Change management (If you use plantype budgets)
    If your client do not really need more functionality I would not recommend the upgrade. But most times they want more out of the system.
    Is there any specific enhancement they requested?
    Regards
    Matthew

  • Upgrade Lightswitch Project from VS 2012 to VS 2013

    Menu -> Project -> Upgrade Project
    How I can upgrade Project?

    Hi Vadim,
    Welcome to lightswitch forum.
    First, you should make sure that you can open and successfully build the project in the earlier version of LightSwitch. If the project has errors, the upgrade is likely to fail.
    When you try to open a project that was created in an earlier version of LightSwitch, the
    Review Project and Solution Changes dialog box appears.
    After you choose the OK button, the project files will be converted to the new format, and the project will appear in
    Solution Explorer. A backup copy of the original project will be saved in a
    Backup folder under the Solution folder. In addition, an
    UpgradeLog file will be created in the Solution folder. This file contains information about the changes that were made and any further modifications that you may need to perform. See:
    Upgrading Projects Created in Earlier Versions of LightSwitch
    If this is lightswitch extension project, you can follow this guide to do that, see:
    Upgrading LightSwitch Extension Projects to Visual Studio
    2013
    Best regards,
    Angie
    We are trying to better understand customer views on social support experience, so your participation in this interview project would be greatly appreciated if you have time. Thanks for helping make community forums a great place.
    Click
    HERE to participate the survey.

  • Regarding upgrade of web report\web templates functionalites BW 3.5-BI 7.0

    hi all,
             I m working on a Upgrade study from BW 3.5 to BI 7.0 for Web Templates,web items and java scripts.
    Below is the scenario of the client system:
    New web templates are created from the 6 master web templates available for publishing to a custom Portal (created using BSP and hosted on the WAS). TOOLBAR and FOOTER are custom web templates used in all Master Templates and contain various JavaScript functions and footer code respectively.
    TOOLBAR provides the Toolbar, header and buttons functionalities in the Master Templates via the contained Javascript functions. FOOTER displays the date and time of issue as well the logged in user.
    FOOTER1 and FOOTER2 are web items derived from FOOTER web template. They have different set of web item properties and are used to create web templates used through the custom Portal.
    It is observed from BW Tables that out of 100 unique Web Templates available in the system, 90 are using TOOLBAR template and 95 are using FOOTER template.
    No external Javascript .js files are used in the Web templates. Most of the Javascript functionality is contained in TOOLBAR and no other custom javascript in master templates. However, there are some derived web templates where custom javascript is contained.
    Following is the process to create custom Web Templates in development server that are eventually transported to QA and Production:
    1)     The appropriate master template is identified and saved with new name in developer role.
    2)     Dataprovider is added to corresponding web items.
    3)     From the library, properties are transferred from master template to the custom template.
    4)     Report title is added in HTML tab.
    5)     No changes are needed in the Web Templates Properties except change of value in  “Show Jump Target in” field to the portal Frame ConPortal or _self in case RRI is to be used.
    6)     Some properties like Title, Width in Pixel, Affected Data Provider, etc. needs to be adjusted. Changes can be done to web items seen in Overview tab except the FOOTER and TOOLBAR web items. These web items are saved as reusable components in Library.
    7)     After all the changes the web template created is transported from development server.
    To summarize, all master data for creation of web templates like reusable master templates, web items in library, web templates containing Javascript code are stored in dev. server. Custom web templates created from these are transported.
    I want to validate the sequence of migration as below:
    Following sequence has to be followed for the Web Templates and Queries Migration in development BI 7.0 Server:
    1)     Migrate the Individual BEx Queries first and perform functional testing.
    2)     Migrate the TOOLBAR template manually (create as new in BI 7.0 Toolset) and FOOTER template automatically (using Migration Tool).
    3)     Manually migrate the JavaScript code in TOOLBAR. Please refer to section ..for more details.
    4)     Migrate the library of reusable web items, if any.
          (What to do if web item is custom or is not supported in BI 7.0)
    5)     Migrate the Master Web Templates manually (create as new in BI 7.0 Toolset) and automatically (wherever possible) and perform functional testing.
    6)     Migrate the custom web templates automatically (wherever possible) and manually, if automatic migration is not possible. Perform functional testing and data provider binding.
    7)     Perform jump target binding wherever applicable.
    8)     Transport custom templates, TOOLBAR and FOOTER to QA and Production subsequently.
    Also i have the following questions:
    1. How to migrate functionalities accessed thru web templates like jump queries, general navigation blocks with filter, table interface, and are data providers automatically linked to web items or have to be done manually post migration.
    2. Do we need to migrate the library of reusable web items also.
    3. After migrating the master  web templates and javascript containing templates to BI 7.0, can we migrate automatically the custom webtemplates derived from master templates and containing the custom javascript that is now avaialbe in BI 7.0, will they pick up the custom code automatically.
    thanks in advance
    Regards
    praveen

    No resolution found

  • Fields Missing After Upgrading the Project in peoplesoft

    I had transferred a project from Qa to prod. User is not able to see some of the fields on prod, while on Qa everything is working fine. I have even compared the project it is same on both env. Onr thig is there that it contains app engine but i dont see section folder in upgrade tab. please suggest what could be the reason.

    To insert all the Sections, Peoplecode  and record structure in App Designer, go to Insert > Definition into Project (Cntl + F7) then next to definition type select Application Engine, enter your app engine name, to the right under related definitions select all the options. and then click on insert, so that all the objects will be added to the project.
    once you migrate the project make sure you alter the records so that new fields will be built to the database.

Maybe you are looking for

  • How to change the data provider of the tree with the selection of combobox

    This is my XML data in a file named `nodesAndStuff.xml`.     <?xml version="1.0" encoding="utf-8"?>     <root>         <node label="One" />         <node label="Two" />         <node label="Three" />         <node label="Four" />         <node label=

  • TSV_TNEW_PAGE_ALLOC_FAILED during extraction

    Hi Experts, during extraction I receive TSV_TNEW_PAGE_ALLOC_FAILED short dump. More information from ST22: The internal table "\PROGRAM=AQZZSYSTBWGENER0SY000000000022\DATA=%DTAB[]" could not be further extended. To enable error handling, the table ha

  • Itunes wont re install

    Itunes wont re install, says i need to log on as administrator.  I am administrator, there is no other log in id for the computer.

  • Security question for Apple ID

    Why would the security question for Apple ID be different to those I answered when I set up the account.

  • Copying to drives

    can i after setting up drive in ix2 dl can i turn it off remove drive to usb enclosure copy files to disk and replace it boot ix2 up and not lose any data becuase copying is real slow does any one know? Solved! Go to Solution.