Replenishment delivery for material with MRP areas and Avl Check

HI We have MRP area at storage location level maintained for materials. Stock exists in the plant in the storage location which is part of the MRP area.
Now when I create STO and try to create delivery for the same, system is giving message 0 stock available and not creating delivery. Material has 02 Avl Chck group.If I deactivate the MRP area in the material master, it allows creation of delivery.
How can I ensure that system creates delivery even though stocks exist in MRP area relevant sloc only in the plant?
Sriram

1) According to SAP when inbound deliveries are used and your delivery item category is set up for mvt type 101, these should be received with transaction VL32N. If you use MIGO/MB0A instead the GR status in the delivery will not be updated. If you then report on open deliveries you'll notice that nothing is received in the course of time. Amazing. Now if you set up the delivery item category without the movement type your inbound will not even be GR relevant. Just one of these things that's nice to be aware of.
Check note 199703.
may b it helps...

Similar Messages

  • IQ09 - Different process for material with bacth Split and no Batch

    Hello,
    i want to know if IQ09 treats material with batch number and no batch in the same way for fetching the serial number.
    view V_EQUI_EQBS_SML is used to fetch the serial numbers.
    i just need to confirm if the process is same in case a material has batch & no Batch together.
    Thanks
    Renu

    Hi,
    We faced the same problem and went back to option:
    Cont.Ins Lot creation (QMAT-CHG) = "For each Material Document item
    This solves the problem and was in our case the solution for receipts from production. But at goods receipt for purchase orders we still use the option for each material document, batch and SL.
    There we pick up the materials in WM by hand by scanning the bar codes on the pallets (printed at GR). The transfer order creates a negative quant in unrestricted use that is later filled by the automatic usage decision that moves the stock from quality to unrestricted in the same bin.
    Hope this helps.....
    Arno

  • Purchase Order is generated after MRP for Material with MRP Type ND

    Hi Everyone,
    Material type := HAWA
    My material procurement type = F i.e. External Procurement.
    MRP Type = ND in Production server , and VB in Quality
    Lot Size = EX
    Material Status :- 15 Pre-release both for Quality and production server
    The Material is bulk material and bulk material indicator is set.
    Purchasing View is also maintained for the same.
    Planning Strat = Z5 Company specific
    Special procurement key:- Z7 Company specific
    I am running MD02 with following parameters.
    Create Pur Req =1, PR
    Create MRP List = 1, MRP List
    Delivery Schedule = 3, Schedule Lines
    Planning Mode = 2 Re- Explode BOM & Routing
    Scheduling = 1
    Issue:
    After MRP run, system is  generating PR, Though with MRP type ND purchase requisition should not be generated.
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.
    After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    We havent been able to locate the root cause so far
    Please guide us
    Thanks in Advance,
    Ayaz
    Edited by: Ayaz Alam Khan on Feb 16, 2011 2:41 PM

    IF the material is ND, system won't Run MRP for the material
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    There is no link
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    system will read the X plant  material status or plant specific material status first and then only system will read MRP type

  • MRP Areas and Delivery schedules

    We have managed to succesfully configure MRP areas, however we still have problems of transferring the MRP results to Scheduling Agreement. We can only set source list at plant level. Now same plant has different MRP areas. Please help.

    Hi TAJUDDIN,
    Let me rephrase my quiry. We have a customer that sends requirements to us, which we then send through to MRP, which gives us the nett requirements, which are then sent to the supplier.
    We have been running this at plant level with no problem as the supplier was seeing all the requirements (from our customers/ subsidaries) consolidated. But now this requirements must be passed to the supplier per individual customer or subsidaries. For implementing this we created a new plant with storage Locations representing each subsidary, each subsidary has to be planned separately and handed to the supplier as individual requirements.
    Hence we looked at MRP areas for this, the other option was to create each subsidary as a SAP plant but this is not neat. Our problem is that we are able to plan with MRP areas but we are unable to pass the MRP results to the agreement that we have with the supplier.
    JUst though to give more infor of the full scenario might help, but in short you've been very helpful. I've learnt quite a lot.
    I hope you'll still be patient with me while I try and understand as well as address the current issue we have.
    Thanks.

  • Report for material with sloc,qty available, and production order

    hi friends, i need advice on getting this report for material with qty and specific sloc with the corresponding Prodn order numbers. in mb51 i could get all these details except the prodn order no. could you advice me please?

    to make sure you know how to do this.
    In the material document list, hit "Ctrl+F8" on your keyboard.
    A window will pop up. Click on the button position and look for "order" in the list of available fields. That should do it.
    Rgds.

  • Hello I'm trying to create Apple ID without success for a long time. And after checking with the bank details are correct with no success

    Hello I'm trying to create Apple ID without success for a long time.
    And after checking with the bank details are correct with no success

    If you choose US as your country while your bank details and credit card or PayPal account are from another country, then you will get an error not related to your details, such as 'the CVV number is incorrect', although it is correct.

  • Schedule line getting created for material whose stocks are maintained

    Hi Friends,
    I am having an unusual problem of schedule line getting created for material whose stocks are there in the system. I have created an SO for some material, and all the material is having sufficient qty in the system but still the system is generating schedule line.
    Can someone please advice what could be the problem and the solution to it.
    Regards,
    Wasim.

    Hello Wasim,
    - In TCode MM02, Check Scheduling in MRP2 Tab of Material master (if MRP is active.)
    - In Tcode OVZ9 - AvC control, for your Availability check maintain (eg. 02) in material & Checking Rule:A-SD order.
    Whether Check availability without replenishment lead time is unchecked, as this Indicates whether, during the availability check, the system checks the replenishment lead time. So, Items for which the delivery date falls within the replenishment lead time, but for which there is no inventory, are confirmed for delivery after the replenishment lead time. In the case of items for which the delivery date falls after the end of the replenishment lead time, the system assumes that everything can be confirmed.
    Thanks & Regards
    JP

  • Subcontracting with MRP areas / Customer consigment

    Dear all,
    I'm currently looking for some information regarding subcontracting processes with MRP areas.
    On the first hand I need a general overview how subcontracting purchase orders would be handled with MRP areas. In addition I'm really interested in the replenishment of the subcontractor stocks. On the other hand some facts about the customizing would be fine.
    My second topic is consigment stocks at the customer. So I need similar information as for the MRP areas but regarding this customer consigment.
    It would be really great if someone has some literature recommendations or official documentations about these issue.
    Many thanks in advance!
    Regards
    Enrico

    Hi Enrico,
    Working with subcontracting and MRP area's gives you the option to plan the requirements for the subcontractor separately and you can then order the components separately. This functionality is used when working with scheduling agreements and direct deliveries to the subcontractor as there this is a requirement.
    A second instance where one would use and MRP area with sucontracting is that when a material is used both by the subcontractor and it's also used directly in the plant production. The requirements for the subcontractor can be separately planned using an MRP area.
    The following links may give you some more information regarding working with subcontracting and MRP area's
    [MRP area|http://help.sap.com/saphelp_470/helpdata/en/c4/106956ae8a11d1a6720000e83235d4/content.htm]
    [Planning for Components to be Provided in Subcontracting|http://help.sap.com/erp2005_ehp_04/helpdata/EN/c4/106956ae8a11d1a6720000e83235d4/frameset.htm]
    Edited by: Peter Pallen on Jun 5, 2011 7:19 PM

  • MRP Area and SA Schedule Lines

    Hello All,
        We are looking at using MRP Areas and noticed it can not be turned off once on (ECC 5.0).  Given that, is the following true with reference to schedule agreements:
    - Will seperate schedule lines be created for each MRP Area (same material)?
    - Does the receiving storage location come from the material master or the MRP Area (Does it matter if it is a type 01 or type 02 MRP Area)?
    - Is it possible to define differen't receiving slocs in a schedule line for a Plant MRP Area?
    Thank you,
    Jerry

    Thank you Charlie,
        The link is helpful however it doesn't come straight out and answer the questions - meaning there is a bit of ambiguity there.
    It would be appreciated if you or anybody that is using MRP areas with schedule agreements is doing the above.
    Regards,
    Jerry

  • How to remove Requirement of SL in  Delivery for a particular Sales area

    Hi Friends
    I have customised supplementary order type, delivery type and billing type. In supplemntary delivry item category, the relevance for picking, storage location required, determine storage location, fields are unchecked. It works well with a particular customr and for a particular sales area, particular materials. In delivery, we have PGI and saved delivery. Delivry did not have picking and it did not ask for any storage location.
    But when I am trying to create the same supplementary order type for a different customer and different sales area and scrap material, the delivery has no picking but its asking for storage location to do PGI. Pls tell me what I have to do to remove the requiremnt for storage location in delivery for this particular sales area.
    Thanks
    sangeeta

    Hi Bhaskar
    In VL01N, in delivery item, for scrap material, item category is coming as ZSUP. Because the item category for delivery is also maintained as ZSUP. In this Item category, the fields mentioned below are deactivated.
    Relevant for picking
    SLOC required
    Determine SLOC
    In material master for scrap, in Sales org2, item category grp is NORM, like all other material.
    Thus storage location is not supposed to come in VL01n as a required field.
    But in delivery item category determination, i did not find this item category zsup. But when I was making supplementary delivery for other materials, the system did not ask any storage location  and supplymentary delivery is duly created. here we delivering from an order not SA.
    Thanks
    Sangeeta

  • RIMODINI for CIF Object: [MRP Area Matl, MRP Areas]

    Hi Experts,
    We have Material maintained at MRP areas in R/3. Integration model is maintained with CIF object : [MRP Area Matl, MRP Areas] to bring the new material master at MRP Area changes through Delta mode(CFM3), but the changes to existing material in Integration model at MRP Area does not come over immediately to APO and not through DELTA mode.
    We have to execute Report: RIMODINI to bring the changes of existing material master changes at MRP Area level to APO. Since its a performance intensive it takes too long  to execute to bring changes over to APO.
    Is there alternative method of bringing the existing material master changes at MRP area level for CIF object : [MRP Area Matl, MRP Areas] to APO without executing RIMODINI.
    Additional Information: R/3: SAP_APPL     470     0030     SAPKH47030
                                     R/3: PI                2004_1_470     0015     SAPKIPZI5F
                                    APO:SCM                    500     0012     SAPKY50012
    Thanks,
    K Sendil Kumar
    Thanks,
    K sendil Kumar

    Hi Sendil,
    Are you getting this error only for Material or other master data also?
    Please can you quickly check below mentioned checks:-
    https://www.sdn.sap.com/irj/scn/wiki?path=/display/scm/cif
    Regards
    Samir

  • Prevent outbound delivery for material not in stock

    Hi Friends,
    I dont want to allow system to create outbound delivery for material not in stock. What configuration should i maintain for the same.
    My example is as below:
    I have an order with 5 qty of material A and as there is no stock system has split the schedule line based on an incoming PO and confirmed the Qty based on the incoming PO. We have not done GRN for this PO and there is no stock available but still system allows me to created outbound delivery for this order.
    How can I achieve this.
    Regards,
    Wasim.

    I dont want to allow system to create outbound delivery for material not in stock
    Standard will allow you to create delivery even if stock is not available; but you cannot do PGI.  If your requirement is even delivery should not be created, then go with delivery exit  V50S0001
    G. Lakshmipathi

  • FG in MRP AREA and ROH comoonents are in different MRP AREA

    Dear consultantas,
    please i need to check this scenario with you if applicable or not:
    i have ine plant 0001 and i created 2 MRP Areas 0001 (plant MRP Area) and 0002 (storage location MRP Area)
    my finished product is planned in MRP Area 0001 and its components (in BOM) are planned in 0001 MRP Area.
    do you think this scenario is applicable.

    Hi
    You can map this business process very well in the standard SAP .Only thing is you have to make sure that both the MRP area are activated for MRP  and Planning file entry to be done foe those FG and componenet which are in different MRP area .You can include them in SCOPE of Planning in the configuration and run MRP in MD01.Or u can run MRP in two different MRP area as per your requirement .
    Hope this will help you .
    Regards
    JH

  • MRP Areas and MRP

    Hi I've created MRP areas, and expect to run MRP by MRP area, however, when I click on the drop down list beside the field MRP area in MD01 I do not get a list to select an individual MRP area.  Is this right?
    Thanks

    Hi,
    we can use Total planning(MD01) for a single plant or use scope of planning to control whether total planning is to be carried out for single plant/sevaral plant/ for one MRP Area/sevaral MRP areas/ combination of plant and MRP Areas.
    Steps :
    1.Group together the plants which are to be planned in spro in --->Define scope of planning.(OM0E)
    2. Define the scope of planning as 999 for ex and give description.
    2. Now select that and Specify the sequence in which Plants and MRP Areas are to be planned,
    3.Goto new entries and enter the plant as 1000/MRP Area as 1000 with counter 1 and plant as 1100 with counter 2 and save.
    4.Execute the total planning either as online job or as background job.
    5.The planning run has to be always started with paralle processing.
    In SPRO in define parallel processing in MRP enter the destination for parallel processing for ex your server name and enter the no .of sessions as 1 and save.
    6.Tcode MD01 enter the scope of planning group and selet the parallel processing and enter. Hope the above points taken care and resolve the issue. Thanking you.

  • Partitioning an External 320gb drive for use with Time Machine and...

    I want to be able to use my Western Digital 320GB external drive for use with Time Machine and to use as extra storage space on both my Mac and when I boot into Windows Vista.
    Is this possible?
    I was playing around in Disk Utility and would I partition the part I want to use for Time Machine with the Mac OS Journaled, and whatever I want as space for windows, use a MS - DOS format?
    Has anyone done this before?
    Cheers-

    Unless you are using 64 bit version of MSWindows (64 bit XP/Vista), it won't be able to handle a disk with GUID partition table (GPT). Disks with Apple Partition Map (APM) or GUID partition table are the only ones that Time Machine will work with (not MBR disks). Note also that the MBR/APM/GPT are at the DISK level and not the partition level, so don't mix the format with partitioning scheme. Time Machine disks are meant to live in the Mac universe (for now, anyway) and sharing with the MSWindows 32-bit universe is not possible.
    See http://img87.imageshack.us/my.php?image=macpcdiskdd06sv8.png for some additional background.

Maybe you are looking for