Revenue Recognition Accounting in PS Results Analysis

I am trying to understand certain aspects in the accountng involved for the process of Results Anaysis. In my case, we have configured RA for revenue recognition and all is working well. We have a project that has a billing element and an account assignment element under it.  Invoices go to the billing element, costs go to the aa elemet. RA key is entered on the billing element. RA calculates Revenues and COS and the billing element settles them to PA. While calculated, defered and unbilled revenue post to FI using OKG8 configuration settings. All is fine on the mechanics of this.
What I do not understand is the treatment for the actual costs. Are they supposed to be settled to PA as well? If so...then, the costs seem to double up in PA (COS from RA calculated based on the actual costs via the billing element and Actual costs themselves from from the aa element). Are the actual costs supposed to remain in the aa WBS element and not be settled? It seems unbalanced. Can anyone explain?

Hi,
Settlement process involves a sender object and a receiver object. Receiver object is the cost object on which actual cost incurred in the sender object is settled. RA is one of the receiver objects for settlement, but not the only one.
Your scenario seems to be periodic calculation of WIP (result analysis) and final settlement of production orders.
The periodic WIP (RA) postings done in FI are reversed and replaced with COGM when the production order is finally delivered. The entries in FI at this stage is based on the "Standard Price" maintained in the material master (depending on the valuation variant). Then the final settlement of production order takes place and the total actual cost is arrived at. The difference in cost between "actual cost" and standard price" is settled to RA as a separate entry.
The reversal of entries when the production is delivered (as explained above) ensures that cost is not reckoned twice.
Hope this explanation meets your requirement.
If so, you may like to close the thread. Otherwise, please revert.
Muraleedharan.R

Similar Messages

  • SD Revenue Recognition-Account settings for deferring COGS

    Hi Experts
    In the current process, COGS, cost of goods sold is getting posted into the COGS G/L account, while creation of billing document.
    In VF44 transaction, we find option for VPRS cost being captured against every line item & are available for posting along with revenue line.
    In that case, if we have to defer the COGS while creating the billing document & would recogonize it while running VF44 alone with the revenue lines, could you suggest me the account setting to be done for the same?
    Anticipating earliest responses
    Thanks
    Banu

    hi
    820417 - Implementation Guide for Revenue Recognition
    779365 - Best Practice document for revenue recognition
    REVENUE RECOGNITION
    In revenue recog. you can create your billing documents and they will be passed to accountings.But in this case your customer account would be debited and deferred accounts would be credited.
    The purpose of revenue recognition is that you can post all the revenues from a deferred account to sales revenue account for a particular period together for all the docs. through transaction VF44.
    if you can se your sales docs no. in VF44,then your revenue recognition is successful.Press on collective processing inside VF44 for posting the revenues from deffered acc to sales revenue account.
    Configuration part includes the setting of revenue recog. in item category by following the path sd-basic functionsaccount assnmnt/costingrevenue recog.
    Then you have to assign G/L accounts.In the first column of assigning g/l accounts ,enter your sales revenue account and in the second column enter deferred revenue accounts.Deferred revenue account is a spcl g/l account.
    Don't forget to enter reconcilliation account in your customer master as well.
    It may happen that in revenue recog item categories fields may greyed out but you have to get authorization for your id from a basis guy.
    :The point at which revenue (income) is credited to a revenue account in General Ledger. There are three possible types
    Time-based : Revenue is recognized in equal proportions between specific start and end dates based on the number of posting periods defined at the company level. Revenue recognition for time-based documents can occur before, during, or after the invoice process.
    Performance-based : Revenue is recognized based on the occurrence of certain events such as goods issue or the performance of a service. Revenue recognition for performance-based documents can occur before, during, or after the invoice process.
    Standard : Revenue is recognized at time of invoice:
    The specified item was not found.
    Re: Revenue Recognition
    CONTRACTS
    Lets take standard CQ contract type:
    First maintain customer - material info record in VD51 T-code
    Secondly maintain pricing for customer / material or only material combination in VK31 / VK11 T-code
    Then use VA41 T-code to create a contract
    VA42 to change contract
    VA43 to display / view contract
    In VA41, enter the document type CQ, followed by the sales area details,
    Enter Sold to party.
    Enter PO number
    Enter PO Date
    Enter Validitiy from Date
    Enter Validity to Date
    Enter Material
    Enter Quantity say 999,999,999 or any other higher quantity as it is referred again and agaain
    Hit Enter.
    Save.
    regards
    balajia

  • Revenue is not visible within results analysis

    Hi Experts,
    Am SD consultant , am not ware of about KKAK transaction and can you please throw ur ideas on below issue.
    In Tcode- KKAK Actual result analysis for the sales order , revenue is not visable with in result analysis for sales order.
    Can you please give your suggestion how can it get update tehre.
    And also let me know this KkAK transaction details can see after creation of billing document or before billing document creation

    The show interface command should give you a lot of details on the link usage.
    You could watch the load, 5 minute input rate/output rate fields before compression and after compression to find
    the realistic usage.
    I am pasting a sample show interface output below
    Router#sh int s0
    Serial0 is up, line protocol is up
    Hardware is HD64570
    Internet address is 192.168.100.2/24
    MTU 1500 bytes, BW 1544 Kbit, DLY 20000 usec, rely 255/255, load 1/255
    Encapsulation HDLC, loopback not set, keepalive set (10 sec)
    Last input 00:00:00, output 00:00:00, output hang never
    Last clearing of "show interface" counters 13:32:47
    Input queue: 1/75/0 (size/max/drops); Total output drops: 0
    Queueing strategy: weighted fair
    Output queue: 0/1000/64/0 (size/max total/threshold/drops)
    Conversations 0/2/256 (active/max active/max total)
    Reserved Conversations 0/0 (allocated/max allocated)
    5 minute input rate 3000 bits/sec, 4 packets/sec
    5 minute output rate 2000 bits/sec, 4 packets/sec
    98631 packets input, 8680095 bytes, 0 no buffer
    Received 30857 broadcasts, 0 runts, 0 giants, 0 throttles
    2 input errors, 0 CRC, 0 frame, 0 overrun, 0 ignored, 0 abort
    98332 packets output, 8924943 bytes, 0 underruns
    0 output errors, 0 collisions, 0 interface resets
    0 output buffer failures, 0 output buffers swapped out
    0 carrier transitions
    DCD=up DSR=up DTR=up RTS=up CTS=up

  • Results analysis and settlement for projects with Sales Order

    Hi Costing Gurus,
    We are implementing SAP for ECO business in ECC 6.0 with SD, FICO and PS modules and we have contracting jobs which will run for longer periods. we are planning to POC method based on actual cost and Progress billing methods in projects. my understanding is that Reasults analysis will be used to calculate the WIP, Reserves, Losses etc.. however revenue has to be recognized using sales and distribution module with (SD-BIL-RR) component. How ever i have started testing this scenario in test system and i have couple of clarifications and seeking some help from experts to correct my understanding.
    i have below questions.
    1. KKA* . results analysis only calculates the amounts (WIP, reserves, losses etc.) or it can update the accounting.
    2. i found from the blogs and online documents FI posting only happens through settlement and it specifies the Profitability segemnt should be used as receiver in Project . is it madatory to use profitablty segemnt. as we are not implementing COPA can i use any other object and what would be the impact of it.
    currenty i have selected update RA key and i could find no FICO documents created with that.
    3. Do i need to use Revenue recognition in SD along RA in controlling to get my accrual posting for recenues. RA can only serve Cost part of the project or it can Revenue accrual also ?
    Seeking expert suggestion on this.
    Thanks
    Murali

    Hello Murali-
    To answer your questions,
    1. When you perform Results analysis, it does not post any accounting documents. Results analysis only does calcuation of WIP etc and when you do corresponding settlement like CO88(production order) or VA88 (sales order), it will post accounting entries.
    2. It is not mandatory to have profitability segment as a receiver. If you are using COPA, then you would need to settle it to COPA in the end. For example in case of make to order environment, sales order can be used as  a cost object and hence the receiver would be a sales order where all the costs would get settled.
    Hope this helps.
    Shail

  • Project Results Analysis KKA2 Enhancement

    In SPRO - Project System - Revenue & Earnings- Automatic & Periodic
    Allocation - Result Analysis - Edit result analysis key & version -
    Maintain Result analysis version,
    If, CO Area 1000 & RA Version 0 selected, system is not allowing cross-
    company valuation check box activation due to "Transfer to Financial
    accounting active" check box is selected.
    However if "Transfer to Financial accounting active" check box is un-
    selected, system is allowing to save with option "cross-company
    valuation" check box. But during KKA2, system is showing error due
    to "version relevant to settlement" is selected.
    Now the problem is that, if "cross-company valuation check box" is not
    selected the system is not skiping steps as mentioned in screen.
    Hence, enhancement KKAG0001 cannot be activated.
    Kindly provide the solution.

    Do you have an OSS ID? There is a document to describe the setting of RA for IAS in service.sap.com/erp, access the sub-node of management accounting -> product cost accounting -> media library.
    Or access the URL
    [https://websmp206.sap-ag.de/~sapidb/011000358700006305122006E.PDF]
    If you don not have any OSS ID, please reply my message.
    Flex Yang

  • Pricing procedure not to bill customer but revenue recognition

    I'm looking for guidance on how to setup a pricing procedure conditions.   First let me explain the situation.  What happens is the customer buys say 2000 software licenses on a sales order. The customer is billed and the customer account is debited and a deferred account is credited. Now the customer activates one of the licenses. The pricing from the sales order is copied to a contract. This contract has a start and end date for the license. Now that license can start to be recognized based on the period of the line item contract dates.. The issue we have is that normally for deferred revenue billing takes places. Problem is customer was already billing on the sales order. Somehow the pricing procure has to credit the deferred account that was posted on the sales order and then credit the revenue recognition account that can be used by transaction VF44.
    So on the invoice associated with the sales order Invoice  from sales order
    Dr Customer $1000
    Cr 2370 $1000
    The account 2370 is the deferred account. This part is fine.  
    Now we activate 1 of the licenses.
    So the pricing procedure has to do the following with no billing to the custo0mer account Invoice from contract
    Dr 2370 $120
    Cr 2371 $120
    This is the problem part. crediting the deferred account 2370 and then posting into the revenue recognition account 2371
    Rev Rec – VF44 for Period1
    Dr 2371 $10 Cr 4340 $10 Any ideas would be appreciated

    Hi
    In SD billing documents customer is always debited or credited based on nature of transaction. For posting in two different G/Ls instead of customer account there is only one possible way which I know. In free goods pricing system can post debit and credit entries to different G/Ls and these G/Ls are controlled through account keys which you assign to condition types in pricing procedure.
    Do you have any Idea of free goods pricing and its posting? Explore this and give it a try. I am not sure about this because I didn't test this. You can test and see if it helps.
    In this for contract item category you have to use free goods pricing which you set in item category settings in VOV7.
    Thank$

  • KJ280 Message Results Analysis KKA1

    Hi All,
    I am Trying to do a Results Aanalysis on one Serivce Order in KKA1 and it throws the following Error , I changed the status TECO, and changed the RA Key ,Just a try, but still gives the same Error Message, If anyone can Help me in this I really appreciate that.
    Thanks,
    Sandhya
    Order without revenue: Only RA types F and Z permitted
    Message no. KJ280
    Diagnosis
    The order type of the order on which you are attempting to perform results analysis does not allow revenue posting.
    In the results analysis version, you specified that work in process for this order is calculated separately instead of through results analysis for the sales order item or WBS element. This means that the work in process will be calculated through the results analysis key in the order until the order has the status DLV (delivered) or TECO (technically completed). Once the order has one of these statuses, the actual costs for the order are included in results analysis for the higher-level sales order or WBS element.
    Procedure
    Enter a results analysis key in the order that is suitable for calculating work in process. To do this, choose a results analysis key for which a valuation method with results analysis type F (calculate work in process) or Z (cancel work in process) is defined.
    If no results analysis key has been defined for WIP calculation, you must go into Customizing and change the valuation method of the results analysis key accordingly.

    Hi,
    Plz check u r RA version. In the version check under calculate WIP or RA for section. I think in u r version there is tick box on Internal and service orders w/o revenue. In conjunction with this check which is more appropriate between first and last option in this section.
    If last option selected, it wont allow if you have any revenues on your order. Then check u r valuation method statuses and u r order status.
    Regards
    Sudhakar Reddy

  • Revenue Recognition Functionality through Result Analysis (RA) key

    Hi all,
    We have a requirement for Revenue recognition, Can anyone guide me Revenue recognition functionality through Result Analysis (RA) key  and functions of RA Key .
    Regards,
    Lal Maheswararao

    Hi Makrand,
    Thank you for your Valuable reply. Actually I am looking Specifically for the Revenue Recognition functionality in Cloud computing Business Scenarios. Like the income has to be recognized over the period of time on the basis of service provided. And it should calculate Percentage of completion for calculating revenues and Cost and how much profit it has to be recognised over the period.
    These functions will possible through Result Analysis method. but i have very limited knowledge about RA method.
    Can you please explain in general how Result analysis method will work and if possible with necessary configuration.
    Regards,
    Lal Maheswararao

  • What is RESULT ANALYSIS,REVENUE RECOGNITION in PS

    hi gurus
    can any one explains me abt revenue recoginition and result analysis in Project Systems
    thx
    regards
    mahesh

    RA cannot be done with out POC
    POC is an essential requirement to calculate the accruals and deferrals
    There are various RA methods which basically calculate the POC
    eg
    Cost based -> POC = act cost/ plan cost
    Rev based -> POC = act rev/ plan rev
    Statistical -> POC can be entered manaully using statistical key figures
    Progress Analysis -> POC is based on value from Progress Analysis - you need to set this up if you are using Progress analysis
    So basically you can do RA without Progress Analysis to calculate POC. The determination of this depends on your company's financial policies and regulatory requirements in the country you are operating

  • Result Analysis , Settlement and Revenue

    Dear Gurus,
    I really appreciate if you can help me in resolving the below issue.
    We are using results analysis and settlement processes in our project
    We want to recognize the revenue before billing.
    Is there any way I can post actual revene to financial accounting before doing
    billing through Settlement.
    I would be greatul to you guys if some one can help me at the earliest .
    Thanks,
    Viswas Anantharangachar

    Hi,
    In my understanding this is the requirement of Revenue recognition functionality implementation. This is more SD than PS function. Please use T-Code ‘VF44’ , or ‘VF47’.
    Please remember that the RR functionality was not enough stable in the ver 4.7 so you must have ECC5 in place.
    Enjoy SAP….
    Don’t forget to give points if its useful ans.
    Namskar,
    Ketan Dave

  • UNBILLED RECIEVABLE ACCOUNT- SERVICE CONTRACT WITH REVENUE RECOGNITION

    Hi SAP Gurus,
    I want to draw your kind attention towards my problem:
    I have created  service contract with one year contract and created an invoice for the whole year in advance.
    Now in-between i cancelled  a contract (after three months) and want to recognised a revenue for the contract period , so i'm creating a revenue recognition for the three months one by one using  transaction code-VF44,
    first month revenue recogniton is working fine as first month amount is going from deffered account to revenue account
    But for second month instead of deffered account ,system is using unbilled recievable account  ,which is wrong .
    Can anybody tell me why the system is picking unbilled receivable account instead of deffered account in case of second month revenue recogniton.
    This may help us:
    "When i was cancelling a contract ,at that time i was entering a billing plan end date in billing plan tab at an item level.
    and just after entering end date ,system was creating two lines instead of one in billing plan tab and i think because of that extra line system is picking unbilled receivables in second revenue recognition."
    Thanks in advance
    Ujjawal
    Edited by: Ujjawal Singh Karki on Dec 29, 2010 12:05 PM

    Hi,
    Thank you for your reply.
    I am doing a contract billing for overall period that is for 12 months (contract is of 12 months).
    Just after 3 months i have realized that somehow we have to cancel the contract and we canceled that in 3rd month.
    I had created the created a contract with periodic billing plan and for canceling that contract i'm putting contract end date in BILLING PLAN TAB as 31/03/2011 (Let say contract is from 01/01/2011 to 31/12/2011).
    Can you/anybody please tell me whether is this the correct way of canceling the contract with periodic billing plan?
    As per your analysis:
    "It seems you have done the billing document for one period and you are doing the RR document for multiple periods and hence the revenue is going to unbilled receivable account for the period for which billing document has not been done"
    As i have billed the customer for 12 months but contract was only for 3 months so i'll create RR for only 3 months and for rest of the period (i.e. 9 months) i'll create credit memo and send it to customer.
    "Please use a billing type where you will specify only start date and end date of the contract and not the billing plan in contract"
    How can we use billing type for contract start and end date .
    I think as soon as i'm changing the dates in billing plan tab system is proposing another line item with different  billing dates and that is not getting covered under deferred account that is still unbilled amount .
    Waiting for your valuable inputs.
    In case of any clarification kindly revert to me.
    Thanks,
    Ujjawal
    Edited by: Ujjawal Singh Karki on Jan 20, 2011 11:10 AM

  • What is Importance of Financial Accounting in Result Analysis

    hi sap kings........
    please give me details of result analysis in financial accounting.

    Hi,
    Results analysis valuates the relationship between the costs and a measure of the order's progress towards completion, such as the revenue or the quantity produced.
    Eg:
    If the measure of an order's progress is the actual revenue, the cost of sales approriate for that revenue is calculated. The revenue, cost of sales, and reserves for imminent loss (if calculated) represent the profit on the order for the period, and are settled to Profitability Analysis.
    The calculated cost of sales is compared with the actual costs, and either work in process or reserves for unrealized costs are created for the difference. Postings are made for these values in <b>Financial Accounting.</b>
    Regards,
    Senthilkumar SD

  • Revenue recognition and error message" Missing data: Provision account Message no. VU019

    Hi,
    I have configured revenue recognition type "B" for my item categories and I am using BOMs where pricing is set at item level. The issue is that when I have more than one components in my BOM then I get an error message (Missing data: Provision account Message no. VU019) at the time of saving sales order though I have configured the provision account. However If I enter the same component/material in the sales order without BOM which will have same pricing data then it does not through the above error message. Please help what could be the potential issue.
    Best Regards
    Javed

    Have you checked the Analysis from condition tab once you created a BOM?  If so, what is the message you could see for pricing.
    G. Lakshmipathi

  • Result Analysis - Profit Percentage based on Revenue

    Deare Gurus,
    While executing Result Analysis, we see profit percentage on the right side as percentage onthe basis of costs. We would like to view such detail as a percentage of revenue
    eg: standard
    Revenue - 100
    Costs - 80
    Profit - 20
    Profit percentage = 20/80 = 25%
    We want it to be 20/100 = 20%.
    Please help!!!!

    Hi Babu,
    I think your example is not totally clear. From what I understand, you need to calculate a result in percentage based on the result of two other columns. What you can do is to use the first result (from the two columns) as a CKF. And then, to this CKF, use the result calcultation options of the query desinger for percentage.
    Hope this helps.
    Regards,
    Diego

  • No accounting document generated at time of result analysis settlement

    No accounting document generated at time of result analysis settlement, but controlling document and profit center document are generated. problem is cost has been settled but accounting does not generated.

    No accounting document generated at time of result analysis settlement, but controlling document and profit center document are generated. problem is cost has been settled but accounting does not generated.
    i am asking at the time of  WIP calculation or settlement
    cost can be settled but does not generated any accounting document .