Hi PM Expert,
Good Day , i am PP/QM/PM user but i am new to PM and now my boss ask me to implement PM with QM. So i would like to know equipment calibration process.
I do have the process as below but can any one help to tell me entire flow in sequence.
Thank you.
Inspection Characteristics
QS21-Create Master Inspection Characteristic
PM Order for calibration
IA06-Assign MIC to task list
IE02-Euipment (PRT) status
IW28-Create PM order with Notification List
Result Recording
QE17-Record Result for Inspection lot
QA11-Record Usage Decision for Inspection lot

Hi Kent999
Process :
Equipment Calibration will be planned as a single cycle plan and scheduling will be done using Scheduling Parameters.
Calibration order will be created through dead line monitoring functionality and system will generate Inspection lot. Based on the master inspection characteristic parameters and sampling procedure inspection lot will be processed. Results of the testing will be recorded and valuated. System will provide an indication whether the parameters are with in the acceptable limits and usage decision can be taken for acceptance / rejection of the calibration.
Maintenance order can be confirmed, technically completed.
Steps :
u2022     Create task list with Inspection points & MIC
u2022     Create Single Cycle Plan for Test Equipment -- If applicable
u2022     Assign the Task list with Master Inspection Characteristic
u2022     Schedule the plan using the scheduling parameters -- If applicable
u2022     Using Dead line Monitoring function Schedule the Plan -- If applicable
u2022     Release the Calibration Order Generated by the system and Check the Inspection Lot.
u2022     Process the Inspection Lot and Record the results
u2022     Confirm the operations of the calibration order.
u2022     Valuate the results and take Usage decision, automatic technically completion of order.
T codes
IA01      Create Equipment Task List
IP41             Create Single Cycle Plan
IP10             Schedule Single Cycle Plan
IW32     Release Maintenance Order
QA02 / QA03     Change / display Inspection lot
QE17     Results Recording of Equipment and valuate
IW41     Confirm the Operation
QA11     Record Usage Decision
QGA2     Display Inspection Results
QGA3     Print Inspection Lot Results
KO88     Settlement of  order
Hope this will help you.
Riyaj

Similar Messages

  • SAP Equipment Calibration Status Table

    Hi,
    Can someone point me to the Equipment Calibration Status table ? I want to locate the current calibration status of individual pieces of equipment such as (out of use, calibrated etc. )
    Thanks,
    Emmett

    Hi Emmitt,
    Would you please identify which BAPIs they are?
    Thanks,
    Mike

  • Requirement in equipment calibration

    Dear All,
    I have some requirement in the equipement calibration as given below.
    1)  Next call date should be less than 1 day for the next call . Means if my cycle time is 1 month, and start of cycle is on 15th then next plan date should be 1 day before, next call should be on 14 of next month and further moving ahead it should be on 13 on the next month and so on. Is it possible in standard SAP or any custom development.
    2) Next call date should be based upon the UD date. Means if my cycle time is 1 month, and start of cycle is on 15th. Now in this case if i completed inspection lot processing on 20th then next call should be calculated based upon the UD date and it should be 20th of next month.
    How these two scenerio can be handled.
    Regards
    Amit

    Hi Jogeswara,
    Thanks for the updates.
    Just want to ask you another query that, in case of fixed date scheduling
    system will generate the call on fixed date of each month. e. g every 15th day
    of each month in case of monthly schedule. But if I started the schedule on
    31st then system will generate the next call on 30 of next month and it will
    call on 28 in case of Feb month and then it will continue to generate calls on
    28th date only. But my business requires to generate call in the
    last day of the month.
    In this scenario how to handle the situation.
    Regards
    Amit

  • Error QE503- in QE11 transaction (results acquisition) for Equipment calibration

    Hi Gurus
    I'm working on QM-PM environment to set-up a Equipment Calibration process.
    I've defined a  routing for Equipment, and I've linked few Quantitative Inspection characteristics to the PM Order Operation.
    When I run IP10 to schedule the Maintenance plan defined for the equipment, the system create fine a Lot Inspection.
    When I try to set the inspection result using QA32/QA11 the system isssue the Error  "QE503-Enter a valuation for this qualitative characteristic"
    rather Inspection charactristics are defined QUANTITATIVE !!
    Where is the error ??
    Thanks in advance for your help.
    Claudio

    Hello ,
    Whenever you are working in QM/PM environment , your using inspection point as well as define sampling procedure in task list so that inspection lot created w.r.t equipment. Now because you are using inspection point w.r.t equipment i.e. 300 then definitely you check and if not maintained then maintain the inspection point valuation in QM customizing in plant level settings.
    Before UD it is required to put the valuation against the inspection point and then post the UD.
    goto QM---> Basic setting---> Plant level---> Define inspection point valuation.
    Now, as you said this is related to MIC, please provide the screen shot of Error message. If any assignment is there then system will provide you the MIC number for which it is required.
    Another, check whether you selected the correct task list or not. i.e. same Grp but different grp counter. it may possible that mistakenly you selected the another grp counter.
    Check all master data first, and then go to customizing part for correction.
    Regards

  • Equipment calibration configuration and settings

    Hi Gurus
    I would like to know the steps involved  or the process flow for equipment calibration in PM.  Please guide me with documents, or any website.
    Thanks
    Vidhyadharan K.P

    hi vidhyadharan,
    Follow this steps given below.
            Equipment must be a test equipment u2013 IE01
           Task list to be created for equipment u2013 IA01
         Plan for this task list with respect to the equipment u2013 IP41
         Scheduling of maintenance plan u2013 IP10
         Checking of call object u2013 IP24 / IW39
         See that inspection lot in maintenance order u2013 IW32
         Result recording u2013 QE51N
         Completion of order u2013 IW41
         Usage decision u2013 QA11
         Technical completion of order u2013 IW32
    Regards
    G.Sathish

  • Equipment  Calibration

    Dear All,
    I am implementing equipment calibration in one of our client .
    I have one issue. In case of equipment calibration suppose sheduling start date is 17/06/2009 and calibration frequency( cycle time ) is 10 days. Now when i will shedule the maintenace plan today i.e 17/06/2009 for this equipment system is creating maintenace order hence inspection lot today only .
    The system is showing shedule date in sheduling overview  correctly as 26/06/2009 and inspection date in inspection lot as 26/06/2009.
    But
    My requirement is that the system should  generate order and inspection lot on its due date only that is on 26/06/06 because  If i sheduled the background job today for these equipment the system will generate inspection lots today only .
    Thanks
    Amol

    Hi
    Your stsrt of cycle is 17/06/2009
    Cycle is 10 days
    so Lot is cretated for 26/06/2009 as pe cycle.
    My requirement is that the system should generate order and inspection lot on its due date only that is on 26/06/06 because If i sheduled the background job today for these equipment the system will generate inspection lots today only .
    as this was the first lot which you have created after start of cycle it is showing future date.
    But when you through IP30/SM37 then it will only create the lots of due date..Provided that in IP30 you maintain Interval call object 1 day 
    This will solve your Problem
    Regards
    Sujit

  • Equipment calibration process

    Hi experts,
    in  equipment  calibration  process we have created a plan and scheduled.
    maintenance order with inspection lot created.Calibration completed and closed.
    But for the next calibration due date again we have to save the schedule (IP10)
    in order  to create maintenace order with inspection lot automatically by the system.
    is there any solution for this problem so that we don't have to save the schedule again and again to create maintenance order automatically ? Plz answer.

    When you create a maintenance plans for calibration in the third tab you will find sort field, define one sort field specific to calibration in configuration and attach it with your all calibration plans. Now after completing the calibration work don't forget to run the dead line monitoring program. Simple select the sort field and execute it will not take more than a min and all your next planned dates will be adjusted automatically
    Regards,
    EJ

  • Tset equipment calibration

    Dear All,
    How to carry out test equipment calibration without integration of PM module. Its my client's requirement but they don't have PM module implemented. Is there any way to resolve in QM module itself.
    Regards,
    Manoj

    calibration without PM will be very much customized approach as I know
    1.You have to define the plant maint order type like PM01 to PM05
    2.In the customization you have to assign the origin 14 to the PM05.
    3.Also master data like work center ,maint plan or Equipment master.
    Also you have to define the basic settings like serial number & number range for this order type.
    Then only lot will be created.& RR can be done.
    Otherwise you have to customize whole module as Z development as per requirement.

  • SAP-ISU - Equipment number from installation

    Hi All,
    Regarding SAP - ISU.
    How to fine Equipment number from installation. Is there any table or function module. Please let me know.
    Please mail to *msrinuvas@gmail. com
                           [email protected] *
    Thanks in Advance !
    Regards,
    Srinivas

    Dear,
    You need to archive the equipment, through SARA Object is  PM_EQUI
    Please refer this link,
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/8d/3e623f462a11d189000000e8323d3a/frameset.htm
    Regards,
    R.Brahmankar

  • SAP PM - Equipment BOM

    Hi,
    is there a function (perhaps in the customizing) to prevent the user to input a material twice in the same equipment bom? SAP should warn the user by doing this.
    regards

    I think this can be acheived using an User exit which checks for duplication of materials in BOM while saving the BOM.
    The User Exit should get activated or triggered while saving the Equipment BOM and check for duplication of entries, should warn the user and pop to save or exit.
    Hope this helps you.

  • Interface between Legacy and SAP for Equipment Master

    Hello
    I got a requirement where I need to develop a interface between legacy system and R/3 system for Equipment Master Data update in R/3. I am thinking of getting a Idoc file from Legacy and then update the changes or any new creation of Equipments in R/3. I found a standard BAPI for this BAPI_EQUIPMENT_CREATE/CHANGE. This BAPI use a strcture BAPI_ITOB for data record of IDoc. But I got more data from legacy except what we have in BAPI_ITOB. I got Partner Data, Classification data also for Equipments. I am thinking of copying the BAPI to a Z function module and modify the Idoc structure , message type and all to capture all the data and then do a update in same way as standard transaction IE01(Equipment Create) is doing in Batch Input. Do you think if there is any better way of doing this? I am not used to transaction BAPI . just wondering if we Can use that in someway to include our modification?
    Thanks
    Harkamal

    20,000 is on quite higher side for IDOC.
    IBIP help doc says it needs 2 Kbyte for each record, i.e. 40 Mb for 20,000 rec. that should be ok. Since it has structures for Partner & classification data , I don't think u need to modify the BAPI.
    Transaction IE01 - Create equipment
    Transaction IE02 - Change equipment
    Structure - IBIPEQUI Equipment record
                     |->    IBIPNSTA     New status profile if necessary
                     |->>   IBIPSTAT     User status records
                     |->>   IBIPDOCU     Doc. from Doc. management system
                     |->>   IBIPPART     Partner details (comment below)
                     |-->>  IBIPTEXT     (see comment below)
                              for long text:          TEXT_MARK = " " empty
                              for internal comment:   TEXT_MARK = "1"
                     |-->>  IBIPCLAS    Classification record (eqpmt class)
                         |-->> IBIPFEAT     Classification characteristics,
                                               ie. features for the class
                     |-->>  IBIPBDCD     see below (from screen 102)

  • Inspection lot for equipment calibration

    We created a equipment with category P, Created task list with insp points 300, maintance package and insp characterstics were assigned thru ia01. Maintenance plan created and pm order has been created. But in qa32, could not find inspection lot. Please advise where need to be checked.

    HI
    Assign inspection type 14 to the order
      Use the control key QM01 in tasklist
    Assign inspection points to the task list 
    Alagesan

  • ISU Serial number = SAP Equipment number

    Hi experts
    We are thinking to synchronize the ISU device/serial number to SAP's equipment number when creating using IQ01.  This is done by setting the SerLev indicator to "1" on Material Master plant data/stor 2 tab.
    We are doing this to reduce confusion of the 2 fields, e.g. SAP maintenance plan uses equipment number and we want to use it for scheduled meter testing.
    My question is has anyone done it this way before if so what are the implications if any.
    Thanks.

    Hi,
    This is ideal way. However, please note while building logic for meter read interface etc.
    In this case,
    EQUNR = SERNR
    MATNR = Material in MM = Caategory
    Also, you have to build a logic based on LOGIKZW which is unique for register.
    Please let me know if something doesn't answer your question..
    Thanks
    Vinod

  • To get SAP Equipment Details Screen  TCODE IE03 in CRM

    Hi experts,
    We have a requirement to navigate from CRM equipment details view to SAP ECC equipment Details.
    Below are the few steps were approach the euipment view.
    GO to Service Pro Profile in WEBUI CRM 7.0 -> click on Accounts&Products Work Center->Object.
    From the above step we get search view where i am entering serial number as input. Getting few records in Search Result view and after picking one record we get the Equipment and Ibase details.Go to Equipment View and we find a button on that view.
    Now our requirement is when we press the button on that equipment view ,we need to see the screen of ECC corresponding to that equipment number.
    Pleae help how i can make it worked.

    Hi Emanuel,
    Thanks for looking into this issue.
    I have performed the following steps as suggested by you, still it doesn't seem to work and gives the same error.
    Below are the changes done on the ECC Side.
    1) Copied the standard equipment class /SYCLO_CL_PM_EQUIPMENT1_DO to custom class ZSYCLO_CL_PM_EQUIPMENT1_DO. Changes made in the GET Method to get custom equipment related data
    2) Modified the standard equipment structure /SYCLO/PM_EQUI_STR by adding one custom field
    3) Configured this custom class as the object handler in the equipment mobile data object
    4) Configured this custom class as the object handler for the equipment complex table
    5) We are still using the standard BAPI Wrapper itself for getting the equipment data and the added field is reflected in the BAPI Wrapper table parameter
    Is there something we are missing?

  • Compliance Calibrator 5.2 RTA for Non-SAP Apps

    Hi all,
    Can SoD rules be written for analyzing a Users access to SAP and NON-SAP applications across the enterprise?
    If yes will CC RTA need to be installed on the NON-SAP application?
    If yes are there any requirements that need to be met by NON-SAP application and is there a list of NON-SAP applications (other than-Peoplesoft, Oracle, Hyperion, JD Edwards) that CC has an RTA for?
    Is there any documentation specific to aplications that can support CC RTAs and installation on these?
    -Cheers

    Hi,
    Yes SoD rules can be written for analyzing user accesses to SAP and non-SAP applications.
    Basically there is no other application for which an RTA exists, but there is a documentation discussing the technical requirements for file generation from the non-SAP systems for integration of non-SAP Systems with SAP Compliance Calibrator.
    This documentation is available in <a href="http://service.sap.com/rkt-grc">http://service.sap.com/rkt-grc</a>
    under SAP GRC Access Control 5.2 -> SAP GRC Compliance Calibrator 5.2 -> Step2: Prepare for your project -> Cross Application Material
    You'll need your OSS user-id to access that page; in case you cannot access it, please post a message in the OSS.
    Rgds,
    Karim

Maybe you are looking for

  • No signal or weak signal samsung

    I have my appletv hooked up via hdmi to my samsung dlp hlr5667w tv and I keep getting a "no signal or weak signal" message.  Why can't my tv find the Apple TV signal?   I do not have any other splitters or devices hooked up and I have the same issue

  • Acrobat Help | Scan documents to PDF

    This question was posted in response to the following article: http://helpx.adobe.com/acrobat/using/scan-documents-pdf.html

  • Comment "dé"concat​énner des chaîne?

    Bonjour à tous, je cherche a déconcaténer une chaîne qui est envoyé via un port série rs232 comment faire ??

  • Bugreport: Long Plugin-Name raises exception when used in item

    Hi, i created an item-type plugin with a rather long name which saves and "compiles" successfully. Name: Resizeable Textarea (remember Size) Internal Name: PLUGIN_INFO.ORACLEAPEX.RESIZABLETEXTAREAREMEMBERSIZE But when i try to use this plugin for an

  • Adobe Premier Pro CS5

    When I am finished working on a project using Adobe Premier Pro CS5 I save the file. Then when I go to close out Adobe Premier Pro CS5 I get a message that says " Adobe Premier Pro CS5 has stopped working. A problem caused the program to stop working