SAP R/3 4.7 Enterprise Project System(PS)

Hi,
        I have to do achieve following four tasks for four integration scenarios :
      1. Create a Project in Project System.
      2. Create a Network in Project System.
      3. Create an Activity in Project System.
      4. Update an Activity on Project System.
I want to know the following :
     1. Which BAPIs to use?
     2. How to import these BAPIs in my integration repository.?
Thanks in advance.

Go to transaction BAPI in R/3
<i>1. Create a Project in Project System.</i>
Project System -> Project Definition -> CreateFromData ->  FM: BAPI_PROJECTDEF_CREATE
<i>2. Create a Network in Project System.</i>
Project System -> Network -> Maintain -> FM: BAPI_NETWORK_MAINTAIN
<i>3. Create an Activity in Project System.</i>
Project System -> Network -> Maintain -> FM: BAPI_NETWORK_MAINTAIN, this has activity create
<i>4. Update an Activity on Project System.</i>
Project System -> Network -> Maintain -> FM: BAPI_NETWORK_MAINTAIN, this has activity update
<i>I want to know the following :</i>
<i>1. Which BAPIs to use?</i>
mentioned above.
<i>2. How to import these BAPIs in my integration repository.?</i>
Double click on your SWCV, click the radio button <b>import RFC and IDoc interfaces from SAP Systems permitted</b>, then enter your R/3 System ID and client number. Save and activate. Then you will see new item under the SWCV
Imported Objects
  RFC
  IDoc
Right click on Imported Objects and in the pop up mention R/3 system host, system number, userid and password.
regards
SKM
Message was edited by: SKM

Similar Messages

  • Difference between SAP cProjects and SAP Project System

    Hi,
    SAP already has a solution PS ( Project System ) for managing the projects in an Organization.
    When there is a solution already existing then why did SAP come up with a new solution cProjects ?
    Can any help me in understanding the main differences and advantages between cProjects and PS ?
    Thanks and Best Regards,
    Priyatham

    Hi.
    I have copied an SAP text below which sets PS, cProjects, (x)RPM and PPM into context.
    In the ninties, the Project System was developed within SAP R/3 to provide a powerful application with full integration into logistics and financials.
    Target groups were industries such as engineering and construction, automotive, high tech or utilities with focus on project manufacturing or large maintenance projects.
    Later on, the need for more flexible and easy-to-use tools supporting the new process methodologies, phased-based approaches, quality gates, and so on, emerged. SAP developed Collaboration Projects and Collaboration Folders (cProjects Suite), which takes these new requirements into account and provides extensive features to collaborate with internal and external partners using a HTML-like interface and Web Application Server technology.
    Thus, cProjects was able to address to a broader range of industries, such as service providers, offering a high degree of visibility and flexibility to support various scenarios from product development to consulting projects. Nevertheless, cProjects is seen as a complementary product to Project System, not as ist successor!
    It always depends on the scenario that a customer wants to cover, which application is the best choice.
    As another matter of fact, combinations of both are also possible.
    In addition to this, the new generation of composite applications was born and SAP xApp for Resource and Portfolio Management provides excellent capabilities to align operational project management with strategic portfolio management.
    The latest developments bring all these three applications tighter together and offers a comprehensive solution for project and portfolio management by covering logistical, financial and human resource aspects and addressing the needs of all stakeholders throughout the entire organisation.
    However, xRPM capabilities are not only restricted to project portfolios but can be leveraged to control all kind of portfolio items.
    Regards / Anders

  • SAP Enterprise Project Connection 2.0 in SAP ECC 6.0 EHP6

    Hello experts,
    Before describing any think let me tell u that i am very new to this field.
    We are configuring SAP Enterprise Project Connection 2.0 in our SAP ECC 6.0 EHP6 .I have already installed ABAP add on for EPC in ECC system.
    I have also installed trial version of primavera6 in another system.So now how can i connect my ECC system to Primavera6 through Enterprise Project Connection(EPC). I have gone through the installation guide for SAP Enterprise Project Connection 2.0 SP2.But i could not get any clear idea.
    Any reply is helpful for me..
    Thanks
    Debasis

    Hello Debasis,
    Post EPC installation,you need to perform configuration of EPC through portal.You can see it listed under configuration--> configuration scenarios-->EPC.
    During configuration you will be asked to define path of you primavera installation and a user on that system with sufficient permissions. This user is called APS user.
    Try to do a mock configuration run on sandbox/dev system and then you can follow the guide.
    Regards,
    Hetal

  • Creating Project Profile in SAP R/3 Project System

    Hi All
    While creating a project definition in Project System in SAP R/3, it is the mandatory to select a Project Profile from a pick list. How can I create a new project profile for myself?
    Thanks
    Sheenam

    It is mandatory to select a Project Profile while creating a Project Definition. Project Profile can be created using OPSA transaction.
    regards
    Shravan

  • Interface between Microsoft Project and SAP Project Systems

    Hi,
    When we update SAP Project systems from Microsoft Project, our users want to swap values between project nodes id and description. Is this possible? Which BAPIs are used by OpenPs? I am trying to find a user-exit where I can swap these values.
    Thanks in advance.
    Regards
    Jitendra Pongurlekar

    Refer Note 579761. This can provide you some hint.
    Regards
    Sreenivas

  • Project System SAP and MS Project

    Hi,
    Someone know a software for integration between Project System SAP, and MS project, in addition to the "OpenPS".
    Best Regards,
    Helena Granja

    Hi
    Please check this
    http://www.pipelinesoftware.com/psi/news.jsp?page=20080105
    And from Impress
    http://www.impress.com/stuff/contentmgr/files/7e364d6f079722b5d13bb004e69649c2/misc/impress_for_epm_web_1007.pdf
    Regards

  • Where does Plan Version field store in SAP project system table?

    Hi,
    I would like to know where where does Plan Version field store in SAP project system table.
    The plan version that I m refering is the Plan Version 1 in the menupath u201COn the Project Info System: Progress Analysis: Initial Screen, Choose Settings > Value display > Plan versionsu201D.
    T-Code: CNE5
    Thanks.

    hi,
    try table TKA09
    regards

  • SAP Enterprise project connection and Primavera

    Hi, has anyone worked on interfacing SAP ECC and Primavera P6 using SAP EPC Add on. Need some guide on how to!!

    Hi,
    Instguide for epc 2.0 sp 04
    https://websmp106.sap-ag.de/~form/sapnet?_SHORTKEY=01200252310000094598&_SCENARIO=01100035870000000202&
    Rin Note:
    1993495 -
    RIN für SAP Enterprise Project Connection 2.0 mit Patch 04 für SP02
    PAM:
    https://websmp102.sap-ag.de/~sapidb/011000358700000103362012E
    br
    Julius

  • Do we have a separate forum for SAP Project Systems?

    hi
    do we have a separate forum for SAP Project Systems?
    regards
    kish

    hi all
    i got the answer
    its the PLM forum ie. product life cycle management
    Expert Forums  » SAP Solutions  » Product Lifecycle Management (PLM)
    cheers
    kish

  • Integration between SAP HR and PS (Project System)

    Hi Guys,
    Is there any integration between Project System and HR in SAP. My client is service oriented company.
    Every month New customers will join and each customer they call it as one project & maintain in PS. Now my client requirement is, through PS recruitment requisition should have to come to HR (For ex XYZ customer requires 2 Supervisors, 1 Manager), so that HR will recruit employees for the project.
    So is there any integration between PS & HR
    Regards
    Prasad

    Hi Vikram Patil,
    In my client place we are not implementing SAP Payroll, hence if any new project is created in PS, I need only man power requirement from PS, how can I proceed now
    If is there any documents on PS and HR integration please forward to my mail ID
    [email protected]
    Regards
    Prasad

  • IS-AFS and SAP Project Systems

    Hello All,
    Can we use SAP Project system in IS-AFS system?
    IS-AFS (Industry Solution - Apparel and Footwear Solution)
    Regards,
    Kumar Rayudu

    Hi
    Normally the project system is used for industries like construction, oil , gas.
    If you are manufacturing
    In your case i suggest you to go with PP(Production planning) module, basically Apparel and Footwear Solution you can with manufacturing process.
    can you please explain your business scenario?
    Thanks
    S.Murali

  • Regarding SAP Enterprise Project Connection

    Hi Experts,
    I understand there is a connector available in the name of SAP Enterprise Project Connection to interface SAP PS/PM with Primavera. We are planning to use this. Have anyone came across this product ? How is the performance of this product and how much it costs ?
    Thanks in advance.
    Regards.
    Bala

    Hi,
    We are getting below error when we are providing "Oracle Primavera 6 Client API JAR File" location..
    Validation error:Invalid jar file pathThe user name or password is incorrect
    Regards,
    Sudarshan

  • Problem regarding SAP Project System & Material Management

    Hello Experts,
    please check our process as below:
    Order confirms than sales order and project will create
    material of BOM is assigned to any activity in project so these material (RM) will be procured and consumed
    assign activity for all work done on material to produce FG or SFG.
    confirm activity whenever any work done like fabrication done so confirm and its cost comes to WBS.
    than we have to subcontracting process so dispach SFG from this and receive after activity done by third party.
    than more work is done and confirm these activity. than after all work done we get FG in stock. than delivery from project.
    We are facing issue in above business process of our client as below:
    1. process of subcontracting using project system as we are not using production planning. how we get any SFG for subcontracting process.
    2. if we confirm all activities and consume all Raw Materials than how we will get finished good in our project stock for delivery.
    3. after delivery from project how sales order affects with regards to completeness of this sales document.
    Please help for this.
    Note: Remember we are not using PP cos customer require detailed report of these process and capacity planning etc.
    Thanks
    Sunil

    Hi Sunil,
    Assume this is my project structure & attached components. I will procure this components externally. After GRN, This components will be issued to network with 581 Q movement type.
    Now we need to assemble this raw material to produce our FG, As these SFG are in our project stock. What we need to do for assembly process through PS.
    Also throw some light over benefit of using PS-BOM interface ( CN33 ) for attaching material components.
    Project
    WBS
    Network
    Activity A
    Gears
    Qty - 1
    Activity B
    Blades
    Qty - 2
    Activity C
    Stand
    Qty - 1
    Activity D
    Connectors
    Qty - 1
    Regards
    Gaurav Ahuja    

  • Regarding the process flow of project system

    Dear Sapgurus,
    I am working new ps project in our client place . The process which i mentioned for a ps flow is sales enquiry,
    design approval, procurement, production, deliveryetc apart from this anything i mention so i request anybody to suggest the business process while starting a customer project and new project development.
    regards,
    muralidhar.t

    Dear Murali,
    Welcome to PS World.
    See link which is given by Venkat Sir.(It shows process)
    Its very tough to explain whole process.
    Plz refer this link.
    Deffntly it will help you.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/80/ea89395eb58c4f9d0c3e837cf0909d/frameset.htm
    PS cycle
    Re: Enterprise structure for PS
    Re: Why we use Project system?
    Regards
    Chandra

  • Enterprise Project Connection 2.0 - Architecture

    Hi,
    We are implementing EPC 2.0 to link between Oracle Primavera & SAP PM for turnaround scheduling. We have 1 ECC instance that used by different users from our offices around the globe. I couldn't find here SAP Enterprise Project Connection 2.0 – SAP Help Portal Page information about the architecture recommendation. For example, which is better :
    Having 1 single EPC instance close to the ECC that is connected to 1 Primavera DB and the Primavera clients in all the regions access this DB that is colocated with ECC & EPC ? or
    Having 3 EPCs, 3 Primavera DBs (in each region) and all these are connected to the single ECC instance.
    Performance wise which is better ? is the 2nd option valid  (many EPCs to 1 ECC) ?
    We couldn't find answers to this.
    Any help is appreciated.
    Regards,

    Hello Debasis,
    Post EPC installation,you need to perform configuration of EPC through portal.You can see it listed under configuration--> configuration scenarios-->EPC.
    During configuration you will be asked to define path of you primavera installation and a user on that system with sufficient permissions. This user is called APS user.
    Try to do a mock configuration run on sandbox/dev system and then you can follow the guide.
    Regards,
    Hetal

Maybe you are looking for

  • Current state of photoshop plug-ins for Intel?

    The good news (I guess) is that CS3 is now Universal. A reason to send a large chunk of money to Adobe. Bad news seems to be that every plug-in I've looked at so far is not available for Intel OS-X. (Admittedly I've only looked at a few like FocusMag

  • Parameters in Excel Output

    I am outputting some financial information into an Excel spreadsheet from BIP. Part of the reoprt is to select the data based on the current fiscal period. When I create the template using the Excel Analyzer these parameters appear in the template, a

  • Vanishing MobileMe Galleries

    So last time I used iPhoto it alerted me that MobileMe albums X,Y, and Z were being deleted. I still had the originals in the main library so I wasn't really worried about it. I just clicked OK and continued on my way, confused but not overly concern

  • How to assign an xpath query result to a variable

    I have a problem that I'm having trouble solving. I need to conditionally run a query based on the results of another query. Both are XPATH queries using extract. I can't seem to get it work as an IF...THEN; so I tried to assign a variable to the val

  • Discovrer Summery folder rebuilt error ORA-30353: expression not suppor

    Hi While i edit summery folder in discoverer 10g. I got follwing error. ORA-30353: expression not supported for query rewrite I checked this error with oracle but i m not ok with that. As per their solution disable the REWRITE option on the materiali