Scheduled Delivery Date

Hi Guys
I have an issue with the scheduled delivery date being determined incorrectly.
If an order is created with the required delivery date of saturday or sunday, the system is confirming the schedule lines for that day/date. The factory calendar has been setup with working days (Mon, Tue, Wed, Thur and Fri), plant and shipping point have been assigned the same factory calendar. Based on the calendar the system should not confirm it for the weekends.
Also if i create the order for the current week with the delivery date of weekend(saturday/sunday) then the system pushes it out to to monday but if i create it for the next weekend or following month weekend then the system confirms it.
Can someone suggest the possible solution??
Thanks

Dear Comes,
    Kindly check whether the factory calender maintained for your plant and shipping point is maintained for your Sales organisation and i think you can also assign it for storage location. So make sure all the factory calender are same.
regards,
Sudhir

Similar Messages

  • In GATP would like to push schedule delivery date+1 day

    Hi Experts:-
    We have below requirement  in GATP:-
    Can we maintain a condition record for pick /pack time  = 1 day against Shipping Point in particular Location.? In other word we would like to push schedule delivery date+1 day.
    In APO we can see control data :- Plan (LEAD), load (LOAD), pick/pack (PICK), transport (TRAN), unload (UNLD)
    In APO We have maintained  value = 24:00 for location XXXX ( as per below steps)
    1.     In the SAP Easy Access screen choose Master Data ® Master Data for Transportation and Shipment Scheduling ® Create Scheduling Step.
    2.     Select a condition type.
    3.     Enter concrete values for the key combination.
    4.     Enter a duration (external display: hhhhhhh:mm).
    While checking order, When the process branches into APO ATP, can see time 24:00 This seems to indicate that Pick/Pack record has now been found, but the scheduled delivery date is not being pushed out by one extra day.
    Looking at the condition log in APO shows the following;;
    Lead Plan:304 Access for Access sequence LEAD missing(Usage U)
    Pick Pick : 208 Condition record has been found
    Load Load: 304 Access for Access sequence LOAD missing(Usage U)
    TRAN Transport: 009 Condition record is missing
    UNLD Unload :  002 Access not made ( Initialized field)
    Can you suggest.

    Hi DB,
    Thanks, Very helpful links.
    I did some testing on various sets of data change in APO for PICK and TRAN :-
    Parameters :-     
    Order creation date     2-Nov
    Route YR0004= 4 days     
    Calendar :-Sat and Sun holidays  & 11th Nov bank holiday     
    Test 1 with 0 Day pick time, No TRAN maintained :-
    Delivery date     8-Nov
    Gi Date     7-Nov
    Loading date     7-Nov
    MAD     7-Nov
    Transportation planning date     7-Nov
    Test 2 with 1 day pick time, No TRAN maintained :-
    Delivery date     8-Nov
    Gi Date     7-Nov
    Loading date     7-Nov
    MAD     4-Nov
    Transportation planning date     7-Nov
    Test 3 with 3 day pick time, No TRAN maintained :-
    Delivery date     8-Nov
    Gi Date     7-Nov
    Loading date     7-Nov
    MAD     2-Nov
    Transportation planning date     7-Nov
    Test 3 with 5 day pick time, No TRAN maintained :-
    Delivery date     9-Nov
    Gi Date     9-Nov
    Loading date     9-Nov
    MAD     2-Nov
    Transportation planning date     9-Nov
    Now next scenario only TRAN without PICK
    Test1 with 1 day TRAN time
    Delivery date     8-Nov
    Gi Date     4-Nov
    Loading date     4-Nov
    MAD     4-Nov
    Transportation planning date     4-Nov
    *with 2 day and 3 day result is same as test1
    Test2 with 4 day TRAN time
    Delivery date     8-Nov
    Gi Date     3-Nov
    Loading date     3-Nov
    MAD     3-Nov
    Trasnportation planning date     3-Nov
    Test3 with 7 day TRAN time
    Can see Delivery Date moving ahead one day.
    Delivery date     9-Nov
    Gi Date     2-Nov
    Loading date     2-Nov
    MAD     2-Nov
    Trasnportation planning date     2-Nov
    Now next scenario  is to maintain data in both PICK and TRAN
    Test 1 with 1 days pick time+ 1 day Tran
    Delivery date     8-Nov
    Gi Date     4-Nov
    Loading date     4-Nov
    MAD     3-Nov
    Transportation planning date     4-Nov
    Test 2 with 1 days pick time+ 6 day Tran
    Delivery date     9-Nov
    Gi Date     3-Nov
    Loading date     3-Nov
    MAD     2-Nov
    Trasnportation planning date     3-Nov
    Would like to know is this the correct standard behaviour or something wrong with our system config.
    regards
    Samir
    Edited by: Samir Ali on Nov 3, 2011 4:07 PM

  • WIP or CoS if scheduled delivery date not fulfilled

    Hello,
    SD-order.
    The checkbox "Fixed date and quantity" within the Schedule lines table has following effect on costs:
    - if the checkbox is marked and there is no confirmed quantity to the delivery date, all costs are settled from WIP to the CO-PA - I have heard that this has background in law, because if the delivery date is not fulfilled the customer is not obliged to accept the delivery.
    Please, confirm if this is true.
    What would happen if the mentioned checkbox is marked, the quantity is confirmed, but the SCHEDULE DELIVERY DATE IS PAST AND NOT RE-SCHEDULED?
    I would expect similar behaviour like in the first case, but I have tested it and the costs are still in WIP.
    Thanks
    Regards
    P

    Dear Comes,
        Kindly check whether the factory calender maintained for your plant and shipping point is maintained for your Sales organisation and i think you can also assign it for storage location. So make sure all the factory calender are same.
    regards,
    Sudhir

  • Schedule Delivery Date in Sale Order

    Dear All,
    I have an order on 03.11.2009 (today) and its last delivery date is 15.11.2009. It means that I have to deliver the complete order on or before 15.11.2009.
    So where can I put this date in Sales Order?
    Regards,
    Vishal

    Hi Vishal,
    Your Last Delivery Date can be entered in the "Requested Delivery Date" field in the sales order.
    By doing so, the system will give us a confirmation that whether the delivery can be made possible on the Requested Delivery Date or NOT (The status can be seen by going in to the Schedule Line Level of your line item).
    The system also gives us the NEXT POSSIBLE DELIVERY DATE with the confirmed  Quantity as a Second Line item in the Schedule line level.
    The System considers mainly the Material Available Date to come to a conclusion on the Delivery Date of the goods. Also, there are other activities (Loading Time, Transporation Planning Time etc) for which some time will take and that also need to be considered (The same can be seen by going in to the Schedule Line Level of your line item and then click the Shipping button).
    Your Scenario: In your case, the delivery can happen ON OR BEFORE the Last Delivery Date.
    So for that follow the steps:
    Step 1: Put the Last Deliv Date in to the "Requested Deliv Date" field in Sales Order.
    Step 2: After enetering the other necessary details in the sales order then Save it. Now go the Schedule Line level of your line item and look for the Confirmation of the Delivery Quantity on the Requested Delivery Date.
    If Yes: Then its your wish that you can Prepond the Delivery Date by giving the required Delivery date during your delivery document creation.
    If No:
    Then you have look for the Next Possible date. OR Make sure that you can manage all your other activities like Loading, Transporation Planning etc. in 10 - 12 days time and make your material Availabilty today and do the delivery.
    Reagrds

  • Schedule Delivery Date in Sales Order

    Hi All,
    Does anyone have any idea, how can I determine the date on which a line item material can be delivered, if I know the Material Availability date. After a material is available, it takes some more time for Loading, Pick-Pack, Transportation... which may take a couple of days.
    Please share if anyone have any fair knowledge to determine the Delivery date for the Material. I need to do a forward scheduling with that information.
    Thanks
    Ipsita

    Hi Ipsita,
    Delivery date arrive based on Material available date, Transportation date, GI date, Loading date and if you have material available for inventory you can create delivery and pack and hold in WH.
    <REMOVED BY MODERATOR>
    Regards
    JACK
    Edited by: Alvaro Tejada Galindo on Feb 20, 2008 9:38 AM

  • Scheduled delivery date according to customer calendar

    hi all,
    i maintained a customer calendar with only friday as work day, and assigned it to customer in uploading point in customer master data.
    when creating sales order, the system checks the customer calendar with the date proposal from sales order type, and display message "No goods accepted on 2008.11.19. The next possible date is: 2008.11.21". that means customer calendar works, but the system didn't change the date proposal to 1121, and further, it didn't change the schedule line delivery date accordingly. it give and just give a message out.
    i need the system calculate delivery date or schedule line date under the restriction from customer calendar, not just give some message.
    i once make it out that the system automatically changed the schedule line into two line, say, the first line is 0 pc on 1119, and the second line is 10 pc on 1121. but afterwards, i can no longer reproduce the result.
    can anybody give me some help on it? thanks a lot.
    daniel

    Daniel,
    I'm not sure but you may want to try it out. Deselect the Propose Delivery Date option in the Sales Document type and then try. Maybe the system in proposing the date because of this configuration and is not changing as per customer calendar
    Regards
    Nadarajah Pratheb

  • Delivery schedules delivery date in future-GR

    Hi all,
    For the Me38 Maintain delivery schedules, we will maintain delivery date and schedule details.
    We can make GR for the current and past date through MIGO. But when we try for future delivery date, it will show no selectable items in MIGO with reference to the scheduling agreement. I guess this is std behavior. So they have the option for changing the schedule to the current date and then post MIGO again. The user feels it to be time consuming. So want to have a message just a warning while Migo and then proceed GR.
    Is it possible to meet?
    Rgds

    it is the nature of a delivery schedule to have accurate timing.
    However for all that do not like that .........you can achieve what you want with an user exit.
    For details see OSS  Note 741385 - Goods receipts up to current date for scheduling agreements

  • Sales Order- scheduling delivery date for Procurment type F

    Hi Expert,
    In material Master , in MRP 2 View mailtained data as  1. Procurment type- F, Plant Storage Loc- 1140, In-House Production- 21 days, GR - Processing time-1 days. But while creating sales order for this material it shows only one day difference in sheduling delivery date.
                         Thanks in advance.
    Manoj

    Hello
    Procurement type F is for external production indicator
    If you want to see a change in schedule accordingly, then maintain Planned Deliv. Time.
    As per SAP, Planned Delivery Time in Days is Number of calendar days needed to obtain the material or service if it is procured externally. If you have different vendors for a material, you must specify an average value. The same applies if you order the material from a fixed vendor that has varying delivery times.
    Or in sales doc type, maintain Lead time in days, this specify the number of days after the current date that the proposal for the requested delivery date in the sales document should be.
    FYI - GR Processing Time, Goods Receipt Processing Time in Days is number of workdays required after receiving the material for inspection and placement into storage.
    Thanks & Regards
    JP

  • Delivery Date needs to be changed on Schedule lines

    Hi All-
    I am using BAPI_SALESORDER_CHANGE, to update the delivery date on the schedule lines...If I have 2 lines of schedule, needs to be updated the second one ETENR '0002'...
    Bapi returns message that successfully processed, when I go back and look at Sales order, I don't se any changes on schedule line..
    I am pssing into BAPI, sales doc and schedule line with the delivery date and the flag 'U'..and also I am using BAPI commit...
    But, let me know if I am missing something and also let me know is it possible to change schedule delivery date or not?
    Thanks,
    Sony

    Hi
    Please follow this process.
    Only specify fields that should be changed
    Select these fields by entering an X in the checkboxes
    Enter a U in the UPDATEFLAG field
    Always specify key fields when changing the data, including in the checkboxes
    The configuration is an exception here. If this needs to be changed, you need to complete it again fully.
    Maintain quantities and dates in the schedule line data.
    1. Minimum entry:
    You must enter the order number in the SALESDOCUMENT structure.
    You must always enter key fields for changes.
    You must always specify the update indicator in the ORDER_HEADER_INX.
    2. Commit control:
    The BAPI does not run a database Commit, which means that the application must trigger the Commit so that the changes are read to the database. To do this, use the BAPI_TRANSACTION_COMMIT BAPI.

  • Best Buy moved delivery date by 20 days only 18 hours before originally scheduled delivery

    I purchased a Samsung gas range/convection oven on December 3, 2014.  Delivery was scheduled for December 30, 2014.  On December 29th, at 12:05 p.m. CST, a mere 18 hours before scheduled delivery, Best Buy emailed me to alert me that the delivery had been unilaterally rescheduled until January 19th.
    Unfortunately, do to the late nature of the notice of rescheduling, I had already sold/gotten rid of my old oven.  In response to this issue, I contacted Best Buy customer service and, after speaking with 6 different people of the course of 2.5 hours, was provided the following options: 1) Cancel your order; 2) Wait until the order is filled; or 3) Contact your local stores to check for availability.
    When asked if Best Buy would consider providing a partial discount on the oven purchase to cover the potential costs associated with renting an interim stove, the customer service representative told me that she was unable to help me in that regard and to ask my local store.
    Has anyone had experience getting a similar situation effectively resolved?  Has anyone ever spoken to a customer service representative with Best Buy that was actually able to resolve an issue?

    Dear rtjamison,
    When receiving a scheduled delivery date like this, I can understand your foresight around creating the space for your new oven by getting rid of the old one beforehand, and I respect that. It pains me to hear that this responsible act will now affect you negatively due to the untimely rescheduling of your order. I am very sorry for any inconvenience this has already caused you.
    On occasion, orders can be rescheduled because of sudden inventory constraints. Other times, scheduling issues can occur if a store is the one fulfilling the delivery and are absent an available delivery driver due to sickness; although, you would typically be provided with an explanation around this. Without being able to look up your order, I am not sure what the reason was in your case specifically. The options you were provided by the phone agent are all viable choices; however, I would like to work with my support team to see if there are any other options available to us at this time.
    As I was unable to pull up your purchase history using your email address you provided here on the forums, I will be reaching out to you via private message to obtain your purchase information so I may investigate further. To check your private messages, click on the envelope in the upper right-hand corner while you are logged into the forums.
    Sincerely,
    JD|Social Media Specialist | Best Buy® Corporate
     Private Message

  • How to show delivery date in Bex Analyzer

    Hi Gurus!
    I have to create a report in logistic scenario and my client wants that the report shows a column with the "Scheduled delivery date". I don't know how to show it in a column because in my KF structure, I can't put just this time characteristic.
    Does anybody know how can I solve it?
    Many thanks!

    Hi,
    Create a Formula Variable on Scheduled  DeliveryDate with processing as replacement path, replace variable with InfoObject, replace with Key and use it in the new formula in the columns.
    in this way query designer will accept you to use the char as in column,
    hope it helps you.
    Regards
    Reddy A

  • Load a sales order with delivery date in the past

    Hi,
    We want to load in the system a sales order with delivery date in the past, and maintain the schedule delivery date in the past. To do that, in the customizing Sales And Distribution / Basic Functions / Delivery Scheduling and Transportation Scheduling / Define Scheduling By Sales Document Type, I selected the flag Blackwards. But the problem is that the rest of the dates in the scredule line: goods issue date, loading date, material avail.date and transportation Plan Date, are in blank and you cannot enter any data because the system deletes it.
    How can I have these dates informed with dates in the past?
    Thanks in advance,

    You can control this using the "Message Control" in the SAP IMG.
    Supplier Relationship Management>SRM Server>Cross-Application Basic Settings>Message Control>Influence Message Control
    Using this you convert Error to Warning or even swith off this message.
    Please refer this thread for complete steps:
    Re: How to change an error message to a warning message in SRM
    Note: you need to suppress the messages relevant to your case here.
    Regards
    Kathirvel

  • Program to update Delivery dates of STO based on Material availability

    Hi,
    We have requireement in which, we need to material availability check for the materials on daily basis. This is only for Stock Trasnfer orders.
    Suppose there is STO ( Stock Transfer Order) 1 that has been created for material M1 for qty 20. The scheduled delivery date for the material is tomorrow. Now I create another STO 2 today for the same material and same quantity. The scheduled delivery date that was proposed was 7 days from today.
    Some one deletes the STO 1. Now Material M1 with qty 20 is avaiable to use. I then go in the system, open STO 2 in change mode. Select the line item and click on Material availability check. When I do this, the new delivery dates are proposed.
    This is standard sap functionality.
    We have required to do this programmatically. Is there any standard SAP program which will check all the STO's by there creation date and do the material avaibility check automatically and re-set STO dates.
    Regards,
    Shahu

    Instead of all that, you could just use stock transport scheduling agreements.  MRP can update those automatically during its processing.

  • Purchase Order Delivery date Expiry

    Hi Friends,
    My Client wants, Puchase Order should be blocked if the GRN is not done at the scheduled Delivery Date.
    Please tell me if it is possible
    Regards
    Prashant Atri

    Hi,
    In Purchase Order ( ME22N) , enter Latest GR Date in Delivery TAB in the  item details which allow latest acceptable date for goods receipt and if date is after this date, you will receive a message .
    Regards,
    Biju K

  • Delivery tolerance (based on the delivery date)

    Dear All
    How to maintain delivery tolerance (based on the delivery date) in Purchasing Order
    Would you help me, please
    thanks
    imron

    YOu can try with
    u2022     ST: Date variance (value x days)
    The system calculates for each item the product of amount * (scheduled delivery date - date invoice entered) and compares this product with the absolute upper limit defined. This allows relatively high schedule variances for invoice items for small amounts, but only small schedule variances for invoice items for large amounts.
    IN transaction code OMR6 for a company code.
    IN SPRO - Materials Management -- LIV -- Incoming  Invoice -- Invoice Block.

Maybe you are looking for