Scheduling Prod.order

Hi Experts,
Can anybody please tell me.
SMK - 1 1 1
In house prod. time - 2 days ( MRP 2 views )
There is no maintain any set,teardown,processing time in Routing.
I created two prod.order. for quntity 1 & 200.Where I got following dates.
Basic finish date - 10.03.2009
Basic start date - 06.03.2009
Why dates are common for 1 & 200 quantity. It should have take more days for 200 quantity.

Dear,
SMK - 1 1 1 it is independent to the order quantity. In house production time from materail master is also lot size independent.
While create the production order system take the timing from the routing so machine time only get multiplied by order quantity as it is lot size dpendent on that basis system define the scheduling date.
House production time in MRP 2  use when we run the MRP on basic date scheduling. It is also consider for claculting the lead time.
If you want lot time dependent in house time then you need to schedule the routing and update the material master through CA96. Then you will get in house time in work scheduling view.
Hope clear to you.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Mar 3, 2009 1:00 PM

Similar Messages

  • Link between Prod Order and Sale Order schedule line

    Dear all,
    Ours is a MTO (81).
    In Scheduling Agreement / Sale Order , there are multiple schedule lines for a single item .
    Production Orders are generated for every schedule line of the Item.
    The client wants to know (for a custom developed report) , against which schedule line of the Sched Agreement/ Sale Order, the Production Order is generated ?
    This Information can be seen in MD04.But  I am not able to fetch from the tables .
    The schedule line field (KDEIN ) is not updated in AFPO table & the order no (AUFNR) is not updated in VBEP table .
    Say,
    Sale Doc No : 42000506
    Schedule line/Dely date            Order qty          Prod Order No
    06.10.09                                    500kg               100170
    15.10.09                                    300kg               100171
    Pls give your valuable inputs.
    Regards,
    Sheik

    Hi,
    Only Sales Order No & Sales Order Item No is updated in the table.
    Whereas , I want to know the Sales Order Schedule Line no.
    Regards,
    Sheiki

  • Prod Order's Scheduled finish time

    Hi PP Experts,
    Could you please advise where's Scheduled finish time (field GLUZS) in the production order coming from?
    Some prod order has 24:00 and other has 23:59.
    We want it as 23:59.
    I changed the work centre's capacity Finish time (ENDZT), but still didn't get it right.
    Many thanks in advance.
    Regards,
    Thomas

    Hi,
    2 Things:
    1. Are you sure you clicked on schedule order after changing values in WC?
    2. Control key ZT02 relevant for scheduling? Check in OP00
    At my end, i did a small test & it works, so do a re-test at your end.
    Regards,
    Vivek
    Added
    Also notice that active version is maintained as 1, so go intervals & shift in capacity details tab (shift + F12) & check the timings there.

  • RE: Prod order automatic scheduling at creation level

    Hi All,
             While creating Production order thru Backward scheduling, the system automatically scheduling but I need to schedule after creation manually. Any solutions to this issue.

    Hi,
    If you have maintain scheduling type as Backward then system will ask you to maintain the Basic Finsh Date.
    So my doubt is with your order type.Is it correct one for which you are creating the production order.
    Now if you don't want to do the automatic scheduling and do this one manually then try this.
    For that order type maintain scheduling type as only capacity requirements.After this system will not schedules the order automatically.All the dates you have to maintain manually.There is no scheduling at all.And if you want to schedules the order then change that scheduling type to backward in order itself (not in OPU3) and then press that scheduling tab.
    Regards,
    Dhaval

  • Converting SNP Planned Order /Purch Req to Prod.Order/Purch.Order

    Guys
    What is the standard process to Convert the SNP Planned Order /Purch Req. into a Prod.Order/Purch.Order ?
    Can the conversion indicator be set in APO for SNP Planned Order /Purch Req.and then transferred to R3 as Prod.Order/Purch.Order  or can the convesrion of Planned Order /Purch Req to Prod.Order/Purch.Order  can be done in R3 itself ?
    I am not clear on how exactly this works. Would appreicate if you could provide me with the standard process and any config involved in the same such as Number Ranges and how to set the conversion indicator automatically through SNP planning runs ?
    Thanks

    When you set this indicator for a planned order or a purchase
    requisition, the system automatically converts the order into a
    Production order or purchase order after the transfer to the
    connected SAP R/3 system.
    The converted orders are then retransferred to the SAP APO system with a
    different category; a purchase requisition with category BS-ANF becomes
    a purchase order delivery schedule line with category BS-EIN.
    Please check configuration setting in SPro for transfer setting to R/3.
    1. Configure Transfer to OLTP Systems(SNP)
    2.Maintain Global Parameters and Defaults(PPDS)
    Also on R/3 side you can see it in MD04/MD07 collectively for a product . or individually on
    MD13 : planned order
    MB51n: PR
    Manish

  • Different batch no in prod order at the time of creation of prod order

    Hi, we need different batch numbers in production order at the time of creation of production order. tried in system, i can able to create only one batch no at the time of creation of order. we need different batch no at the time of order creation and same no should be assigned at the time of GR from prod order. pls advise how to map this.

    Dear,
    Use the Exit EXIT_SAPLCOBT_001 under enhancement PPCO0001 where-in based on your requirement you can create batch for your order. You can use CALL FUNCTION 'VB_CREATE_BATCH' to create the batches as per your requirement.
    Also make sure the automatic batch creation setting in Prodn Scheduling profile has been turned-off so that the batch is created only through the user-exit.
    Refer this thread,
    Re: Batch creation
    Please try and revert back.
    Regards,
    R.Brahmankar

  • Prod Order Type Automatic selection

    Dear Sir,
    In MTO, after MRP run, during the conversion of planned order to production order, how system detect the production order type automatically if I have more that one production order type.
    Thanks and Regards,
    Chetan

    Dear Chetan,
    1.Check if the production scheduling profile/production scheduler has been assigned in the material master.
    2.If only production scheduler has been maintained means,then in OPJ9,check whether this prod.scheduler has been linked to
    prod scheduling profile(through which the default order type can be set),if only prod scheduling profile means then directly check
    in OPKP for this profile what is the order type.
    3.IF no prod.scheduler/prod scheduling profile has been maintained means check whether any MRP group has been assigned in
    MRP1 view which has the default production order type settings in OPPR.
    Check and revert back
    Regards
    Mangalraj.S
    Edited by: Mangalraj.S on Aug 22, 2011 12:37 PM

  • Material staging indicator not populating in prod order WM pick list item

    Hello,
    I have an issue with material staging in an prod order
    1) PP-WM interface is activated
    2) Control cycle for material is created
    3) Production storage location is created for material
    4) storage type is 100 for production
    5) There is one discontinued material and also the follow up material
    6) stock of discontinued material is zero and requirement are passed to follow up material
    When we confirm the order the stagging indicator for both follow up material as well as discontinued material automatically populates zero (Non relevence to pick list items) where as it should be one (1 - for pick list items).
    One more issue user has manually inserted discontinued material as well as follow up material in production order change mode.
    In the BOM of a main material both discontinued as well as follow up material is there with some quantity as a component.
    For the same work center, control cycle , production storage location the indicator is populating.
    These two material (discontinued as well as follow up) are appearing twice in the WM pick list screen where first two line items are OK and populating indicator "1". But in line item last and second last indicator is not there.
    My question is why the stagging indicator is not automatically populating in the production order WM pick list screen in front of components.

    Unfortunately, WM material staging via production orders is not possible
    from the pull list.  Please see the long text of message RMPU 311
    (WM material staging for production order reservation not possible):
    "You cannot carry out a WM material provision for pick parts from
    production order reservations in the pull list". The reasons for this
    are cleary explained in the SAP on-line documentation via the
    following path :
      Logistics -> Logistics Execution -> Warehouse Management Guide ->
      Goods Issue -> Goods Issue for Production Supply ->
      Material Staging for Repetitive Manufacturing
    See the following under the Selection heading :
    The choice of the selection type influences which types of WM material
    staging are supported in the pull list. However, the pick parts can be
    staged via RS headers/planned orders but not with the current BOM
    explosion. The release order parts, on the other hand, can also be
    staged if the current BOM is used for calculating the dependent
    requirements.
    WM material staging via production orders is not possible from the pull
    list.
    I think you may try in CO02 or COR2 for production order or process order.

  • Block creation of multiple prod. order against single sales order in CO08

    Hi All,
    We have a requirement of blocking the creation of multiple production order against single sales order in CO08 if the production order is already created for that item.
    How to achieve this?
    SmanS

    Hi,
    you need to check if any user exit is there which will check order haeder table for the said sales order if any Prod Order exist for the same and flag custome error whicle prod order save.
    Pls revert if you need any further information.

  • Settlement rule SDI in prod order

    Hi,
    I used strategy make to order in my client, when i create prod order the settlement rule is always MAT and want the settlement rule to be SDI to my sales order.
    What should i config to achieve this ? since i tried to change order type dependent parameter and it did not allow (only PP1 and PP2 allowed).
    Please kindly help
    Best regards,
    Freddy Ha

    Hi,
    i tried to change the requirement class for makte to order so the setlement become SD1 in setting for requirement type KE. In the OPJH i still used PP01. and now it work thanx for all off your input.
    Thankx once again.
    Good day,
    Freddy Ha

  • Require settlement rule when creating a Prod order

    Hello,
    Hello,
    one of our processes is to fabricate complex tools that will be capitalized and depreciated when completed.
    while the tools is being fabricated, we would like to settle regularly the production order to a capital order (AUC) and track the budget for the fabrication.
    in this production process we want to require the user to enter a capital internal order in the settlement rule of the production order master data..  this way when Prod order is settled we dont have issues.  can you make settlement rule entry as required during production order creation?
    any input is appreaciated on the issue. Thanks
    Andy

    Hi,
    There is no standart control for this, but I know a PP user exit which excatly meet you requirement.
    PPCO0007---User Exit for Checking or Changing Header Fields During Order
    You can first control if it is a production order ( ı think it is a special type to produce auc) that you want to control. Then you can select settlement rule and control and give error message settlement rule is mandotory you can not save. The exit sends a signal that it is not possible to save. For error message you can write code into the exit for the message.

  • Status of Prod Order not updated as delta - 2LIS_04_P_COMP

    Hi all,
    We are currently using 2LIS_04_P_COMP to update the data to BI. We have enhanced the DS to include the status of the prod order from table JEST. However it seems that this is not getting updated to BI server whenever prod order change its status. There is a delta queue when I see in tcode LBWQ and then I run the collective update in LBWE and then it will disappear from the queue which is correct. But when I see in RSA7, there is nothing and also I run the infopackage in BI server, it cannot get any data. Anybody has this issue before?
    Many thanks in advance.
    Regards,
    Janet

    The delta will only be captured if the Production Order actually changes. When a change is made to the status of an object in JEST, or JCDS, it doesn't register as a change on the object. Therefore, changes in Production Order status won't invoke a change on the source tables for Production Orders and therefore not get captured on the 2LIS_04_P_COMP or 0PRODORDER_ATTR DataSiources.
    If you need to capture the changes in status for Production Orders, you will have to create a generic DataSource that is sourced by the JEST table and join it with the Production Order in BW.
    Edited by: Dennis Scoville on Sep 17, 2009 8:16 PM

  • Problem: Scheduling Process Orders.

    Hi,
    I have a problem in PPPI with scheduling in Master recipe and with the process order in CM25. Can you help me?
    In Master Recipe:
    I create a capacity category 0025 to display for a resource the setup formula and Processing formula in the Scheduling Tab (as the capacity category 0001 - I also tried to let the capacity category 0001 be used in application C - Master recipe and didn´t work).
    In OP40, I created and assigned in applications to C Recipes
    Afterwards, I ordered the views in OP13.
    When im creating a resource, i prove the formula and i have no problem. But when I assigned it to the recipe and the recipe to the production version to make a process order, neither the master recipe or process order schedules the order.
    When I create a resource with a capacity category 0008 (standard) the scheduling works just fine in the process order.
    Scheduling in CM25:
    Also when Im trying to schedule the order in CM25, I see two lines of the same order (i guess are the 2 phases 0010 and 0020), is there anyway to just see the second to avoid misunderstanding?
    Thanks in advance!
    AM

    Dear,
    For FIFO you can use the Characteristic  LOBM_LFDAT for FIFO if is LOBM_VFDAT then in plant storage data 1 view maintain the SELD then assign these Characteristic to class in CL02 then assign this calss to material master.
    Then craete sort rule in CU70 withCharacteristic  LOBM_LFDAT or LOBM_VFDAT
    then assign it to serch strategy in MBC1 or COB1 with selction criatoria.
    In OPL8 assign this serch procedure.
    Then create the order and check the result.
    Regards,
    R.Brahmankar

  • Qty withdrawn is not updating in prod order.

    Hi gurus,
        Qty wihdrawn is not updating in prod order , when i issuing
    raw material through tcode mb1a 261 movement type.
        What could be the possible reasons.Pls suggest.
    Thanks in adv.
    Sudarshan

    Dear
    you are issuing the materials in MB1a w/o reference to the reservaton.
    You need to do as below
    In MB1a ---follow the menu path -Goos issue -->create w.referenec to order.
    Enter the order number. execute the report
    system will default matrerial no and qty/storage loc from order. Here you enter the qty requuired and post. This qty you posted in this way will refect/update the withdrawl qty in the production order.
    You are not entering the order the way I suggested, hence it is going as a unplanned issue...hence the problem.
    come back if required

  • Form for Gr against Prod order.

    Hi
    I need a form for Gr against Prod order.. the form be trigerred once the Prod oder is saved...
    Can you pl let me know the smartform for the same which can be used in this ...
    Thanks in advance

    This scenario is new
    Normally during production order creation Order Printing can triggered automatically through spro setting
    I don't think the GR related smartform
    K.Prabakaran