Selection of technical objects by work center and plant

Hi there,
I want to select functional locations and equipments that are diretly linked to a workcenter which you can see in the location tab in the standard-transactions.
How can I select this data the way from work center (and plant) to the technical objects? Which tables I have to use??
Kind regards
Jens

Try using Function Module ITOB_FUNCLOC_READ_SINGLE.

Similar Messages

  • BAPI_FUNCLOC_CREATE : Main work center and plant associated

    Hi,
      I'm trying to create Functional locations using BAPI BAPI_FUNCLOC_CREATE. I got almost all the fields except 'MAIN WORK CENTER' and 'PLANT  Associated with main work center'. Please advise me the relevant fields in the importing parameters of this BAPI so that I can upload the same.
    Thanks:
    Gaurav

    Hi,
      Thanks for your response. Actually after doing further R&D, I saw that work_ctr requires the object key of the work center. I fetched the OBJECTKEY from CRHD & passed. It automatically updated both work center & plant associated.
        Awarding you points for your help.
    Thanks buddy!!!

  • Could U Please Tell me the Link B/W  Work Center and Plant ?

    Urgent Issue ...

    Hi,
    The org structure is as follows-
    1 st - Company code
    2 nd - Plant
    3 rd - Work center
    First co code is created (by FICO) then Plant is created (by MM) then come s the creation of work center.
    When we create a Work center it will ask about the plant in which the WC is to be created. The work center is directly linked to the plant.
    Please revert with further details of your question if this answer is not satisfactory.
    Award points if satisfied.
    Thanks,
    Hemant

  • Network Activity - Timesheet: Work Center in plant does not exists

    Hi All,
    While doing Timesheet entry against Network and Activity in CAT2 transaction Code, I come across one scenario in which If I use copy function then one error message appears as " Work center XXXXXXX in Plant XXXX does not exists"
    But same combination gets worked if I put manually and do not use copy function.
    I think system checks copied entry plant with new entry Plant.
    Is this system inconsistency ? If so what may be the probable solution ? OSS Note ? Exit ?
    Please suggets to rectify this wrong validation message.
    Many thanks in advance.
    Swapnil Kharul

    Hi Swapnil,
    You can check following points once again.
    1.Check your Network Actvity details:
    Work Center/Plant : 1000/1300
    Work 10 (hrs)
    Activity Type :11000
    DistKeyCapRqlnt:SAP020
    Also Status of activity :whether it is in PCNF or CNF.
    and in Network Header: check Capacity Requirements.
    2.In CR02, check whether the work Center and Plant Combination.
    Plant:1300
    Work Center:1000
    Goto Costing Tab: Note the following:
    Cost Center: 4295
    Actvity Type Int Proc(Bottom Field):11000
    Formulae:SAP008
    3.Check in KP26/27, whether Cost center has been
    assigned to Activity Type for the period (or else entire Fiscal year).
    Version:0
    From Period:6
    ToPeriod:6
    Fiscal Year:2010
    Cost Center:4295
    Activity Type:11000
    with this combination whther rate has defined or not.
    Plan Actvity/Fixed Price/Variable Price
    4.And also CAC2, don't hide any field in all screen Groups of your data entry  profile.
    Now Pl. let us know the results.(all values considered here are for your understanding)
    Vemula

  • Cost Center, Work Center and Profit Center

    Hi ALL,
    Can any one please explain me the concept of Cost Center, Work Center and Profit Center.
    And where and when do I assign the cost center???
    Amit

    Hi Check the following "
    Cost centers represent areas of responsibility where costs are incurred or where responsibility for costs may be assigned.  They represent the smallest unit of responsibility within the organizational structure of an enterprise.
    A cost center can be pictured as a ‘cost bucket’ such as a department, product line, production stage or geographical area. 
    An unlimited number of cost centers may be created.
    All cost centers within on controlling area have to be assigned to a cost center hierarchy (standard hierarchy).
    Costs originally posted to one cost center may be distributed and assessed to one or more other cost centers using allocations.
    How are costs assigned/posted to a cost center?
    External financial accounting documents created in FI, AM or MM that post to a G/L expense account can be configured to require a cost center assignment be entered at the time of transaction entry.  The system automatically creates a parallel CO document that posts to the indicated cost center.
    Cost elements master records can be configured to be posted to a certain cost center (automatic account assignment).
    In addition, other non-financial activity (i.e., direct labor hours) may be posted directly to cost centers from within CO or via other modules such as PP  or HR
    chandra

  • How to change the main work center and  work center of each operation when generating work order by maintenance plan

    Dear experts,
    I face a problem that system get main work center from equipment master data as a default main work center in maintenance plan when creating maintenance plan. however, if main work center in equipment is changed later, the change will not synchronize to related maintenance plan. if work order is generated from maintenance plan, main work order in order is defaulted from maintenance plan instead of updated work center in equipment.
    another problem is that, for those orders generated by maintenance plan, the work centers in  operations is defaulted from task list in maintenance plan. in most case, work center in task list is dummy. Actually the work is done by work center in equipment master data.
    My expectation is how to auto replace the main work center and work center of operations in work order with the one in equipment master data if order is generated by maintenance plan? is there any standard configuration or enhancement/BADi that can help with this requirement?
    thanks!
    Wesley

    Wesley,
    Sorry - development is the only way.
    Another option is to create a batch program that runs before your IP30 run(s) and updates any maintenance items and task lists with the correct work centres.
    PeteA

  • Control Key in Work Center and Routing

    Hi Gurus,
    Can anybody tell me what is the difference between Control Key we are providing in second tab of work center and the control key we input in routing.
    can i use same control keys at both the places.
    Regards,
    Anand.

    Hello,
    Control Key in Defaut value keys screen is mainly for defining how the work center will be used in routings.
    Almost in all the PP we define same Control key to the work center as well in the routing.
    For example in work center control Key PP01 is used to define Routings/Internal proc. activities. When we go to the routing screen even if we do not see our components, work centers or control key we have to manually enter these details ans here control Key will remain the same as it was in Work center.
    No. of individual capacity defines how many machines are there of the same type in the work center. E.g if I have 5 CNC machines then I will make One work center and in capacity screen I will put 5 as No. of individual Capacity.
    Regards,
    Piyush

  • Link between work center and G/L Account

    Hi All,
    I need to link work center to the G/L account in PM Module . I know the link between work center and cost center . But would like to know how MO cost hits which cost element/ G/l account and there assignment
    Thanks and Regards,
    Vivek

    Hi check the below definitions
    Cost centre : Organizational unit within a controlling area that represents a defined
    location of cost incurrence.
    Profit Centre: Organizational unit in Accounting that reflects a management-oriented
    structure of the organization for the purpose of internal control.
    Work Centre: An organizational unit that defines where and when an operation should
    be carried out.
    Regards
    Sreeni

  • How to write a validaton rule for Cost Center and plant in PO

    Hi,
    I need to write a Validation Rule for Cost center and Plant in Purchase Order to get the error message if the Plant and cost center combination didnot match.
    But i am not sure in which transaction code do we need to write this validation. Kindly help me by giving T.Code or path to do validation at PO level.
    Thanks
    Sunil

    >
    Sunil Pal Raj wrote:
    > Hi,
    >
    > I need to write a Validation Rule for Cost center and Plant in Purchase Order to get the error message if the Plant and cost center combination didnot match.
    >
    > But i am not sure in which transaction code do we need to write this validation. Kindly help me by giving T.Code or path to do validation at PO level.
    >
    > Thanks
    > Sunil
    Check OKC7
    Regards,
    Indranil

  • Cost center and plant in asset master creation compulsory entry config

    where we configure that cost center and plant entry is complusory while creation of asset master.
    is it   asset accounting
                   master data
                           Define screen layout for asset master
                                     Define Screen Layout for Asset Master Data
    as in our system in config    cost center and plant is optional        but while creation of asset master it becomes compulsory field

    Hi,
    Yes, it's defined in the layouts for assets master data.
    Regards,
    Eli

  • Cost Center and Plant

    Hi Guys,
    Is there any R/3 table that gives relations between Cost Center and Plants?
    Thanks

    The plant is an <b>operating area or branch</b> within a company and  is assigned to a single company code. A company code can have several plants.
    The plant plays an important role in the following areas: <b>a) Material valuation
    b) Inventory management c) MRP d) Production  e) Costing (material prices valuation)</b>
    A <b>Cost center</b> is an organizational unit within a <b>Controlling area</b> that represents a defined location to identify where a cost is being incurred. or an area of Responsibility for costs
    If you happen to run transaction KSB1 for a cost center, where plant field is not blank, you may find some material transaction. These are trasnactions which could involve both plant and a cost center.

  • When I select a single object in a layer and try to move it with the mouse, everything goes with...

    I've been having this problem where I can't use the move tool with the mouse properly. I'll go and select a single item on a layer and then try to move it with the mouse (move tool). I've done this before and still do it all the time on Photoshop on my other machines. However, on my laptop it won't work. I grab the single object I want to move and the second I move it, it defaults to moving every single layer in my file. The only way to get around it is to use the arrows, but that's becoming laborious and frustrating.
    Any ideas?

    I know what you mean! This happened to me as well!
    And one thing that I found useful is, if you want to directly select a layer without selecting from the layers pallete and without having autoselect enabled, just hold Ctrl and click on in directly in the image. This saved me a lot of time!

  • IW51-52 - Updating fields Main work center and Maintenance plant

    Hello Experts.
    I Have a task which includes recieving a file and using the data to create new notifications. I need to update the fields above (Data elements GEWRK & SWERK ) but i can't find the right BAPI or Function which will do this work for me.
    Thanks for your help.
    Motty Gal.

    Hi,
      Thanks for your response. Actually after doing further R&D, I saw that work_ctr requires the object key of the work center. I fetched the OBJECTKEY from CRHD & passed. It automatically updated both work center & plant associated.
        Awarding you points for your help.
    Thanks buddy!!!

  • Work center and material

    Hi Gurus,
    is there a table that will give me work center, material that is being run at that work center, quantity and date ?
    Thanks
    Anusha

    Hi,
    You can use this FM 'COIS_SELECT_ORDER_DATA_READ':
    CALL FUNCTION 'COIS_SELECT_ORDER_DATA_READ'
          EXPORTING
            iv_prod_order_sel       = lv_prod_order_sel
            iv_proc_order_sel       = lv_proc_order_sel
            iv_planned_order_sel    = lv_planned_order_sel
            iv_rem_objects_only_sel = lv_rem_objects_only_sel
            is_objects_to_read      = ls_objects_to_read
            it_parameter            = lt_parameter
            it_status_hdr           = lt_status_hdr
            it_status_opr           = lt_status_opr
            it_status_cmp           = lt_status_cmp
          TABLES
            ct_ioheader             = lt_ioheader
            ct_ioitem               = lt_ioitem
            ct_iodocl               = lt_iodocl
            ct_ioopdocl             = lt_ioopdocl
            ct_iomamo               = lt_iomamo
            ct_ioconf               = lt_ioconf
            ct_ioopconf             = lt_ioopconf
            ct_iosoconf             = lt_iosoconf
            ct_iogomo               = lt_iogomo
            ct_ioopgomo             = lt_ioopgomo
            ct_iosogomo             = lt_iosogomo
            ct_iogmer               = lt_iogmer
            ct_ioopgmer             = lt_ioopgmer
            ct_iosogmer             = lt_iosogmer
            ct_iosequen             = lt_iosequen
            ct_iooper               = lt_iooper
            ct_iosoper              = lt_iosoper
            ct_ioopcomp             = lt_ioopcomp
            ct_iooppreq             = lt_iooppreq
            ct_iosopreq             = lt_iosopreq
            ct_iooppord             = lt_iooppord
            ct_iosopord             = lt_iosopord
            ct_ioopmst              = lt_ioopmst
            ct_ioopprt              = lt_ioopprt
            ct_ioopcap              = lt_ioopcap
            ct_ioopscap             = lt_ioopscap
            ct_iosocap              = lt_iosocap
            ct_iososcap             = lt_iososcap
            ct_ioopsccf             = lt_ioopsccf
            ct_iososccf             = lt_iososccf
            ct_ioprodlist           = lt_ioprodlist
            ct_iomatver             = lt_iomatver.
    Give the selection for workcenter. Check the transactipon COOIS and fill up the lt_parameter table with the workcenter detail. It will give the detail.
    Thanks and regards,
    Pradip
    Edited by: Pradip Ray on Aug 26, 2009 10:34 AM

  • System monitoring work center and CEN system

    Hi everybody.
    I'm setting up the central monitoring, using SSM as monitoring system. I'm also having a look at the work center for system monitoring; but I don't find how to link the central monitoring capabilities with this dashboard.
    I mean, it looks the central monitoring does not provide any advantage to work with this work center, am I right? Anyone has experienced this?
    Thanks for your answers!!
    Fermí

    Hi!
    I've done finished this issue!
    Please follow steps below:
    1. Create activity type in T-Code: KL01
    2. Go to KP26 to create the realtionship between Cost Center and Activity.
    Now you can see new activity in Costing tab.
    Regards!
    Woody.

Maybe you are looking for

  • How do I know if my iPad is using wifi or cellular?

    I've just got a sim card for my iPad. How do I know if my iPad is using 3G or Wi-Fi?

  • Sending HTML email with SO_DOCUMENT_SEND_API1

    Hi all, I have implemented a function module to send HTML emails with SO_DOCUMENT_SEND_API1. It works fine, but in every email I have at the end a CRLF which looks not very nice in MS Outlook. It seems that this will be added to every email in additi

  • Error launching jdev9i on solaris

    I installed jdev9034 version on solaris. After changing the jdk in .conf in jdev/bin , I get the following error launching jdev. The error is Unrecognized option: -XX:MaxPermSize=64M Could not create the JVM Thanks, Sunil

  • Adobe reader won't install

    I have downloaded the install program on my MAC. I run the program.  It keeps freezing at 40% I have confirmed that java flash in enabled.  I have tried with both a safari and a chrome download.  I have researched and discovered that I should be prom

  • How to Create the new Field ( Table - Row) in SAP B1

    I have a scenario in which the Purchase calculation is based on LR, so for that we have to add new field in Purchase  Document. that filed is not available in form setting.  kindly let me know how to Create a new field in Purchase document. Thanks