Selectively publish and/or approve certain tasks in Project Server 2013

hello forum members,
is there a way in Project Server to selectively publish and /or approve certain tasks?  for example - publish all tasks with new actual. Also, is there a way to auto-publish and not wait until project managers publish their updates?
tatiana
tatiana

It is in the approval center, you'll find the "manage rules" button.
If the replies above were helpful to you, please mark them as an answer so other users with the same concern can refer to it.
Hope this helps,
Guillaume Rouyre, MBA, MCP, MCTS |

Similar Messages

  • How to handle PSW approval task in project server 2013 through declarative workflow VS 2013

    Hello,
    Plz explain in detail handling PSW approval task in project server 2013 through declarative workflow VS 2013
    bcoz when using am posted on with this error when i try to approve the item
     "This list item  has not been created by the workflow.you cannot apply this content type"
    any help would be appreciated!!!!
    Thanks regards, Vignesh.

    I am also experiencing issues with this.  After the approval task is completed, the Workflow gets cancelled with the following message
    RequestorId: 60d96368-4cb4-b059-8086-604972a92e60. Details: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary. at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context)
    at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager
    bookmarkManager, Location resultLocation)
    All other desired workflow actions work as expected.  Emails are sent, project is moved from stage to stage, however as soon as the workflow approval task is completed, either Approved or Rejected, the Internal Status is changed to Canceled and the
    workflow fails.
    What is interesting is when the Approval task is completed, the approver will receive an email notification that the task was CANCELLED or DELETED....
    not COMPLETED, which is what would be expected.
    Has anyone seen this - any potential resolution?

  • Access permission to the Project server workflow tasks in project server 2013.

    Hi All,
    I am creating an OOB Project server workflow, where it contains few phases and each phases have some stages, there are few approval levels of the workflow. 
    Scenario - 1st stage - when project is submitted, a task is assigned to resource, when the resource click on the task link provided in mail, it redirects to the project server workflow task list.
    1) When users view the task list, for all user the delete Item and approve button is enabled even we have given permission as edit,view permission in sharepoint group for that user.
    2) Task list should be viewable by specific user but in my case even after giving the permission it can be apporved by any one who is not authorised also.
    3)  then i tried below things
    1. deleted the user in pwa
    2. deleted the user in sharepoint site.
    even after doing the above, the user able to do all activity in the stie content page, have access to the sharepoint portal. how this is possible?
    When checked with not existing user permission there are few defalut permission set for that user after AD sync. because of this he as access, even if he is not in pwa or in sharepoint site. how to retrict this?
    Can anyone faced the same issue?
    How to fix this permission issue?
    Thanks in advance.
    Sunitha

    Hello Treb Gatte,
    I ma creating Data Connection from SSRS Report, and then creating Data Set for "Project
    Server Workflow Tasks".
    And then when I pull data from the database, it is returning empty. For any other sharepoint list this
    is working absolutely fine. I am facing issue only wrt "Project Server Workflow Tasks" list.
    Thanks,
    Shanky

  • When attempting to edit a project in the PWA I receive the error: 'An error occurred while opening your project. Give us a few minutes and try again...' Project Server 2013

    Hello,
    I am hoping someone can assist with the error we are encountering when trying to edit a project from the PWA in Project Server 2013.  I can click on the project name and go to the detail page and I can
    click and see the schedule.  However, if I click on a task in the schedule and attempt to edit it, I receive the following error:
    'An error occurred while opening your project. Give us a few minutes and try again. If this happens again, contact your administrator.'
    At this point I must click cancel twice to get rid of the error pop-up message.  At this point, I am no longer able to look
    at the schedule of the project either.  Can someone assist with this issue?
    Thanks

    Hi antonio,
    In addition to Phani's advice, which version of IE are you using?
    Can you reproduce the issue on another mahcine and with another browser?
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Create template for a task in Project Server 2013

    Hi everyone,
    I've got a little question, yes, again :-)
    Some user of Project Server haven't scheduled tasks, so they need to create their tasks by the "My Tasks" page, "Add a row" then "Add a new task".
    Unfortunatly, these users create a lot of little tasks but which are the same excepted for an information (like number of the bug ticket) and my bosses want to create a template of a task for create this kind of tasks very quickly but I do not find a way to
    do that.
    Is it possible with Project Server to do something like this ?
    Thanks to you,
    Patmol

    Patmol6 --
    There is no default functionality in Project Server 2013 that would allow a team member to create a new task from some kind of custom template.  It MIGHT be possible through custom software development, however.  Hope this helps.
    Dale A. Howard [MVP]

  • Allow collaboration on un-published / checked-in project on Project Server 2013 and Project Online

    Hi All,
    Before a project is officially published specific resources in the project team need to be able to "collaborate" i.e. create tasks, change dates, etc. before the project is published. The complication is that we need this collaboration to happen
    on un-published / checked-in versions of the schedule. For example, the primary Project Manager adds tasks and makes changes to a published version of the schedule, saves and checks-in the project (doesn't publish), tells a secondary PM to go in and review
    the changes, the secondary PM should be able to see the changes the primary PM made, even though the schedule changes weren't published, be able to check-out the schedule, review what the primary PM did, make some more changes, save and check-in the schedule
    (again, without publishing it), and tell the primary PM to review. Then the primary PM could go, check-out the schedule, review it, save it, publish it, and check it in.
    Can Project Server 2013 or Project Online allow to do this? I looked into permissions and Server settings but I couldn't find anything that would indicate it is possible.
    Any help will be greatly appreciated!
    George

    Hi George,
    If you perform some tests, you'll see that even from PWA, the schedule can only be edited from the draft table. When you access the schedule in read only (as a team member for example), you see the published version, but as soon as you edit it (after clicking
    on the edit button assuming you have the appropriate permission), you'll open and update the draft version of the project.
    As far as I can remember (I don't have it in front of me now), you have a "line" in the schedule PDP (don't know how to call it in english) that will tell you if you are accessing either the draft or the publish version.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Need to create a TASKS page with a filter default in PWA Project Server 2013 (Online)

    Never done this so, I am wondering How to go about or what I would need to create a simple PWA page like "Tasks" in Project Server 2013 online where it default to a filter that is set to not equal to the user that is logged on?
    \Spiro Theopoulos PMP, MCITP. Montreal, QC (Canada)

    Hi Spiro,
    The "my tasks" page or "my timesheet" are automatically filtered on the user currently connected. Unless you are using workarounds such as status manager or delegation, I see no way to bypass this.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project Server 2013 - Approved Tasks not applied to Project Schedule

    Environment Details: Microsoft Project Server 2013 SP1
    When an Resource completes a tasks within the Task or Timesheet page at the end of each day, the tasks is routed to the Project Owner for approval. The Project Owner (Project Manager) approves the task. During this process no errors are displayed.
    When the Project Owner (Project Manager) goes into the Project Professional 2013 client to view how the project is progressing, and update the project completion date, the updates is not applied to the project. 
    This worked for some time, but has recently stopped working with no changes made to the environment. Any help would be great, as our project manager's are manually updating the tasks prior to approving them so they can report back on the project each week. 

    Hello ProjMgrMatt
    Sounds pretty serious, but I think something is missing somewhere.
    Make sure that the Status Manager field is the same as the Project Owner. 
    Check to queue to be sure that nothing is stuck and waiting.
    Create a new project, publish, submit, approve, etc and see if it still happens.
    Cheers!.
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

  • Task custom field and formula custom field don't correspond Project Server 2013

    Hi people, I have an interesting case in Project Server 2013 SP1 CU Apr:
    I have a custom task number field called AM. This field get's filled by a PSI action with actual material costs from an external system.
    I also have a custom task cost formula field that is called AM*. This field is a formula field that has the formula [AM]. And summary tasks use the formula field as well.
    As soon as I create a project, assign costs in the external system and let PSI fill the values within AM I get correct values in AM. But nothing is calculated on AM*. If I edit the project in the browser and publish, check in and revisit the project
    AM* still isn't filled.
    If I open the project in MS Project Pro the calculation comes through nicely, however I do not want to use MS project Pro to see correct data in browser.
    Some tests I have already done:
    I have noticed that when I create a new calculated task field AM2*, this get's calculated correctly on the already existing task.
    I have also noticed that opening the custom field in server settings and just saving the field creates correct values on AM*.
    What is going on? I don't want to save the custom formula field every day... There are 11 custom formula fields in the environment at the moment.

    Hi Gary,
    Thank you for the quick response. Please note that the fieldnames are [AM] and [AM*]. There is a difference in field name due to the astrix. However I did think about the situation and changing one of the field names all together didn't do anything for the
    situation at hand.
    It looks like some kind of refresh thing, because without changing anything in the custom field just saving the field in server settings will turn op good values. However, values already turned up good in Project Professional 2013. And that suggest
    that there is a calculation error on the PWA side wouldn't you say?
    Anyway, thank you for taking time to look into this matter.
    Erik

  • Project Server 2013 Tasks differ in project site and plan

    I have an Project Server 2013 enterprise plan that I created with an associated project site. The plan has tasks added to the timeline. The project site has a timeline webpart but the problem is the tasks added to the timeline differ.
    Does anyone have any ideas what could be the problem here? I checked the timeline webpart and it's correct.
    Thanks!
    [Images below].
    The following image is taken from the schedule PDP.
    This image taken from the project site depicts what is out of sync.

    Hi Guillaume,
    Yes, I've checked the queue while publishing the project. It's successful without any errors. I don't remember if I checked the ULS logs, but what I suspect is that it will say something along the lines of orphaned tasks in the project site.
    Anyways I've tried a number of things and I think the only 2 options I have are:
    Re-create the project site then sync the plan to it
    Ask MSFT for a script to resolve the orphaned tasks
    For the same of time, I'm going to assess how long it would take to re-create the project site.
    Thanks,
    Roland

  • Project Server 2013 Workflow Task Permissions Breaking Inheritance and Causing Workflow to Cancel

    I have an on-premise instance of Project Server 2013 with a workflow that includes an
    Assigned Task to assign users to Approve or Reject a WF phase. The workflow successfully assigns the task and notifies the user of the task. However, after (or possibly just prior) the user Approves the task, the workflow is automatically
    cancelled. 
    By default, the WF Task List is set to inherit permissions. After Approving an item, it appears that the list permissions automatically breaks inheritance, causing the workflow to cancel. This occurs somewhat regularly after resetting permissions to inherit
    from the parent site. Although there are stretches where the issue doesn't occur. I'm not sure what's causing the list permissions to change. 
    This issue occurs in both our Dev and Prod environments. Has anyone experienced this issue with permissions breaking inheritance automatically?

    Hi Vic,
    According to your description, my understanding is that the workflow was cancled when you created a workflow with Impersonation Step to break inheritance permissions.
    After breaking inheritance permissions, make sure the workflow initiator (the creator) still has least edit permission on the list.
    In addition, please check the workflow history list to find more information about this issue.
    I hope this helps.
    Thanks,
    Wendy
    Forum Support
    Please remember to mark the replies as answers if they help and unmark them if they provide no help. If you have feedback for TechNet Subscriber Support, contact
    [email protected]
    Wendy Li
    TechNet Community Support

  • Notification to Manager if task/Time sheet not approved in Project Server 2013

    is there any option if any user(Resource) updated his/her task & sent to his/her Manager for approval
    and Manager is not approved ( say in said timeline or days) then some notification should go to one step up (as Reporting Manager of that Manager who not approved task update & time sheet) in Project Server 2013?

    A solution could be to create email subscriptions on an SSRS report containing the non-approved task updates by manager.
    See reference here:
    http://bhushan.extreme-advice.com/email-subscriptions-for-ssrs-reports/
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, MCP |

  • Project server 2013 csom save and publish

    Hi,
    In Project server 2013 PWA when you edit project custom fields and save the queue job execute the following jobs: 
    - "Project Update from PSI"
    - "Project Publish Summary"
    - "Reporting (Project Publish Summary)"
    In my code (CSOM)  i can only use : " QueueJob Job = projChechedOut.Publish(true);"
    which is creating all these jobs:
    Project Update from PSI
    Project Publish Notifications
    Project Publish
    Project Checkin
    Prepare Project Web App Permission Synchronization For Projects
    Reporting (Project Publish)
    Project Workflow Check-in
    Synchronize Project Web App Permissions to Project Web App
    Synchronize Project Web App Permissions to Project Site
    Reporting (Project Sync)
    Is there way to "simulate" the save from PWA instead of fully publishing the project using CSOM,  because it is a lighter solution since my code is supposed to only set custom field value (if i only update, not publish it is written to the
    Draft) and secondly performance (less jobs) is better ?
    Thx in advance !!

    Hi,
    as an update to my post:
    - In PSI the method is project.queuepublishsummary(guid jobid, guid projuid)
    http://msdn.microsoft.com/en-us/library/office/gg200290.aspx
    the description says: Publishes the stage summaries of the specified project, in a partial publish operation.
    I am wondering if the equivalent method exists in CSOM. There is this method: PublishedProject.UpdateVisibilityCustomFields() but it seems doing exactly the same thing as publishing a DraftProject.
    Any ideas ?
    Thx

  • Project Server 2013 timesheets not showing up for approval

    We're using Project Server 2013 and entering timesheets. I'm a team manager who is set up as the timesheet approver for a few people, including Nicole.
    Nicole opens her timesheet and fills it in for the week.  She applies time to four Administrative tasks and two project tasks.
    Nicole submits her final timesheet for approval.  (We have also tried having her save it first, then to the final submission, with the same results.)
    I go to my approval screen and see the four Administrative tasks listed as separate lines.  I do not see the project tasks.
    I select the four Administrative tasks and approve them.  They disappear when the screen is submitted.
    In previous weeks, and with some other employees, I would immediately see a single line item that said "My Timesheet" for Nicole which I could then approve.  But recently this stopped, and I do not see her timesheet.
    If Nicole checks the status of the timesheet it says it's submitted to me.
    On my Approval page if I go to History, Timesheets this timesheet is not listed under "approved by me" nor is it under "my resources unsubmitted timesheets."  It's in limbo.
    The only fix is for Nicole to recall the timesheet and resubmit it.  Then it shows up on my Approval page.
    Any suggestions?
    -- Paul

    We resolved this. The solution was as follows:
    Go to PWA Settings, and under Security choose Manage Groups.
    Click the Team Members group.
    Scroll to the Categories section, and in the Selected Categories area highlight (select)
    My Tasks.
    Click the box to allow the permission called Adjust Timesheet which is under the grouping for Resource.
    Now don't ask me how or why that works.  It's not a setting that intuitively matches what's going on.  But it fixed it for us.
    By the way, we had a number of other timesheet issues (view failures, etc.) that were all cleared up when we installed the April 2014 Cumulative Update for Project Server 2013, as well as SharePoint 2013 SP1.  I highly recommend both.
    -- Paul
    Paul LoSacco, Web Presence Team, Omnicare

  • Workflow in Project server 2013 online not going particular stage after Approval

    Hi All,
    i have created workflow using sharepoint designer 2013 for project server 2013 online. and i have also set the approver after the first stage. when i create a project using this workflow, project is created successfully and the approval task also go for
    a approval to specific user. and i have set the property that after approval it has to go on specific stage. but the problem is when user approve the task it shows approved but my stage in workflow is remain same. it is not going to any stage. 
    i don't know why this type of problem is occur. 
    FYI, i have created same workflow for Project server 2013 on premise(Which is installed in my server) and
    it is working fine but when i want to deploy this workflow in
    project server 2013 online its giving error.
    so please help me to solve this type of issue.
    Thanks

    I am also experiencing issues with this.  After the approval task is completed, the Workflow gets cancelled with the following message
    RequestorId: 60d96368-4cb4-b059-8086-604972a92e60. Details: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary. at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context)
    at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager
    bookmarkManager, Location resultLocation)
    All other desired workflow actions work as expected.  Emails are sent, project is moved from stage to stage, however as soon as the workflow approval task is completed, either Approved or Rejected, the Internal Status is changed to Canceled and the
    workflow fails.
    What is interesting is when the Approval task is completed, the approver will receive an email notification that the task was CANCELLED or DELETED....
    not COMPLETED, which is what would be expected.
    Has anyone seen this - any potential resolution?