Settlement to cost center posted for statistical WBS element

We have the following scenario
Statistical WBS elements with assigned Cost center posted for actual postings
Network assigned to statistical WBSE and settlement rule on the same WBSE
On settlement run CJ88  the network costs are transferred from network to Cost Center posted in the WBSE.
Issue:
While analysing the active availability control the assigned value is doubled. This happens only of the networks are settled. System considers the Actual values from network + Statistical value from WBSE to caculate the assigned values.
Simulation details as under.
SP-SET-02-3  (wbs element)
    COSS 2011 11 0007101000     0001240704 KOAO D INR                 100.00  INR
    NWA 500000002408 0010
        COSS 2011 04 0007101000     0001240704 KOAO O INR                 100.00- INR   S  -- does not contribute to assigned value
        COSP 2011 04 0007101000     0001240704 COIN D INR                 100.00  INR
        COSP 2011 01 0007101000     0001240704 KPPP D INR                 100.00  INR   M   -- does not contribute to assigned value
Hence the assigned value gets doubled and eating up the budget.
Anyone encountered similar issues pls share the possible solutions.

Hi Mohit
It is against SCN's rules to post the same discussion thread twice. You have already posted a similar question in the below thread. Please refrain from doing this and close one of the threads.
Initial balance upload of revenue GL accounts with wbs
Regards
Sowmya

Similar Messages

  • No costs visible for statistical WBS element

    Hi,
    The followin steps are the setup:
    - Project with a statistical WBS element and a network below
    - Create a PO with Account category "Fixed Asset"
    - Fill in a fixed asset, but also a (statistical) WBS element (put field 'project' optional in customizing)
    - execute a MIGO to book costs
    Now when I run the cost report for this project using transaction CJI3 then I do NOT get the costs visible on this statistical WBS element.
    HOWEVER when I do the same steps, but instead of putting a statistical WBS element I put the network (next to the fixed asset) then I do get the costs visible.
    Is this normal or do I have to change something in order to get the costs visible for my statistical WBS element?
    kindest regards
    bert

    Is this necessary?
    Because in the end I want to book these costs as actual costs on my fixed asset...

  • Purchasing for statistical wbs element

    Hello SAP experts,
    Could you please advise if it is possible to create a purchase requisition with regard to a statistical WBS element? If so, please let me what the assignment category should be used, so both cost center & wbs element number could be used.
    Thanks!!!

    not possible
    statistical means not account assigned - no commitments (PR) can be raised against these

  • No costs visible statistical WBS element

    Hi,
    The followin steps are the setup:
    - Project with a statistical WBS element and a network below
    - Create a PO with Account category "Fixed Asset"
    - Fill in a fixed asset, but also a (statistical) WBS element (put fields 'project' and 'network' optional in customizing)
    - execute a MIGO to book costs
    Now when I run the cost report for this project using transaction CJI3 then I do NOT get the costs visible on this statistical WBS element.
    HOWEVER when I do the same steps, but instead of putting a statistical WBS element I put the network (next to the fixed asset) then I do get the costs visible.
    Is this normal or do I have to change something in order to get the costs visible for my statistical WBS element?
    kindest regards
    bert

    It is normal

  • Wbs settlement to cost center

    Hi Gurus,
    We have project sysyem, FI and cost and profit center accounting.
    We are booking cost and revenue on wbs and then we are settling it to cost center.
    Do we really need to settle to cost center what is the need and what is the correct process???
    Thank you

    Hi Mohit
    It is against SCN's rules to post the same discussion thread twice. You have already posted a similar question in the below thread. Please refrain from doing this and close one of the threads.
    Initial balance upload of revenue GL accounts with wbs
    Regards
    Sowmya

  • We want to post actual cost through statistical WBS elements.

    when we do the posting on Costcenter assigned to a Statistical WBS element (2nd level), I was in the opinion that, the actual cost posted on the Costcenter of statistical WBS (2nd level) will reflect to the top WBS element (which is non-statistical in 1st level).
    But, I cannot able to see the actual cost in the 1st level WBS which also a Billing element (with this, finally we want to  do the Resource Related Billing).
    So expalin me how to bring actual cost posted on the costcenter of a Statistical WBS, to top WBS element which is non-statistical.

    U can book the actual cost from Procurement Cycle or by direct Invoice posting using FI transaction.
    Procurement Cycle:
    When you create PR or PO user Account Assignment Q or P and maintain WBS element. When u do GR or service entry actual cost is captured on the Project (WBS element).
    Using FI Transaction:
    When there is no PO and to book the cost u can use  F-43  to post actual cost (via Invoice) and mention WBS element.
    U can check the Actual Cost using Line item report CJI3 or S_ALR_87013532.
    Venkat

  • Settlement receiver (cost center) for an PM order

    Hi Gurus,
    In which table I can find the settlement receiver (cost center) for an PM order??
    Thanks.

    Settlement distribution rules are stored in table COBRB.
    Regards
    Sreenivas

  • Cost Center mandatory for PO creation

    Dear Experts,
    When a PO is created and assigned to a WBS element, the cost center  should be mandatory  if the wbs element is statistical. Please let me know the suitable steps to achieve this ???
    Regards,
    Kenneth

    Dear all,
    Thanks for your replies, I'm quite aware of the solution, which most of you have replied.But by selecting the option 'cost center as mandatory' in the Account Assignment, we are more or less forcing the user to enter cost center irrespective of whether WBS has been checked Statistical or Not.
    But the actual requirement is, only if it is checked for Statistical, then Cost Center should be mandatory, else not necessary to make it mandatory.How do we do this check via Customising ??
    Kenneth.

  • Plant maintenance order settlement to cost center

    Hi,
    I have a requirement from the client that PM order costs should be settled to Cost center (real) and credit the order line with statistical cost center.
    1. Consumables GL is debited at the time of goods issue with refrence to PM order , cost center is not updating in this line item
    2. Settlement rule maintained as cost center receiver which is mentioned in the PM order and after settlement consumables GL is getting credited with Order and debit to cost center mentioned in settlement rule , statistical cost center is not updating in credit line
    My client requirement is
    Statistical cost center should update along with Maintenance order at the time of goods issue for consumables GL (Debit)
    Statistical cost center should update along with maintenance order at the time of settlement for PM order (Consumables GL credit with statistical cost center and maintenance order and the same GL debit with settlement receiver cost center (real)).
    If i provide cost center in account assignment at the time of Goods issue , system is updating the cost center along with order , however at the time of settlement both cost center and order are not updating in credt line item and the cost is lying in the order without settling.
    Please advise any configuration setting or user exit to meet the above requirement.
    Thanks,
    Sreedhar

    Hi Ravi,
    Thanks for the update.
    If i give the cost center in acct assignment in MB1A it is taking , is there is any option to default the cost center either from PM order or thru some other setting.
    I have tried both substitution and OKB9 , however system is not defaulting the cost center from this settings.
    Please let me know if there is any other option to default the cost center in MB1A.
    Thanks,
    Sreedhar P

  • Error in Cost center posting

    Dear All,
    We have created Autopumps Export A/c as a revenue element catagory 11.
    In cost element we had given cost center 100 as a default account assignment.
    We have not created any other cost object such as profit center or business segement.
    While releasing sales order accounting doqument has been generated but cost center report for 100 does not showing any revenue postings.
    what is the cause??
    please suggest

    As you may be well aware, revenue is normally posted to cost centers. If posted this is regarded as a statistical posting so you need to check the report you are running if it is displaying statistical posting.
    Also check that the cost center master control allows posting of revenue to it.
    Hope this helps
    Siva

  • Report: Statistical WBS elements with assets assigned to them - actual cost

    Hi all,
    I would like to run a report that gave me this info:
    WBS Element (all statistical)
    Assets assigned to each WBS
    Actual costs
    It would be perfect CJI3 but it doesn't show assets. In AM I haven't see either any report that shows WBS elements...
    any ideas???

    Hi
    There is not a standard report which can cater to your requirements. You need to develop one.
    You can take the refernece from CNS41 report for development. Some of the fields you need are PRPS-XSTAT for statistical WBS and will have to use tables ANLA and ANLC to fetch asset master data.
    Regards

  • Statistical WBS element posting - Asset

    Hi,
    From the SAP help on AS03 transcation field on Origin tab >Account Assignmnet for investment  - WBS element  , I see the following information.
    WBS element investment project
    Enter the WBS element here, if the system should automatically make statistical postings of the transactions on this asset to this WBS element.
    You can specify in the Customizing definition of the transaction types, whether statistical automatic posting should take place for certain transactions.
    But I am unable to find a setting in the transaction type which allows the statistical postings on the WBS element , when we are posting to the asset.
    We have a requirement to post statistical postings to WBS element when posting to the asset and we thought of using this funtionality but unable to find the setting which allows the statistical postings on the transaction type.
    If anyone knows how to make this setting , could you please share with me.
    Thanks
    Vara Prasad

    Hi Markus,
    Thanks for your response.
    Even with the OSS note I am unable to find how to change the asset accounting transaction types allowed for statistical postings to WBS elements.
    I am aware of other steps in the configuration except this setting, could you please let me know if you have any idea on this setting specifically.
    Regards
    Vara Prasad

  • Training & Event Management - Cost Center Posting  Error

    Dear Friends,
       I am stuck on the posting part in PE module as in when i run the T-Code PV1C - Cost Transfer Posting . I can run up to first level but after that i am unable to transfer the cost .
    Error
    E BK 031 Enter Controlling Area
    Note:- I have assigned the cost for the particular event but still i am unable to transfer.
    I have even tried in Cost Center Posting after running wizardbut finally i get a error saying their is no automatic transport active.
    After this error i have activated in HRIS node  in TEM automatic transport active. but still i get this eror
    suggest ASAP
    Thanks in Advance
    Magesh

    Hi,
    Hi,
    Have you assign controlling area and cost element to your cost item in the table T77Kb or T.code OOKB.
    E BK 031 Enter Controlling area. here
    E- Business event/course
    BK creterion
    031- is reltionship is required.
    so, maintain the relationship to your course using pp01 t.code.
    check properly.
    Good luck
    Devi

  • Sales order - cost center posting

    In a sales order, the field cost center (header rellated) appears only by entering an order reason.
    Are there other possibilities to open cost center field for entry?

    Hi,
    If the account in question is defined as cost element (KA03), then it requires an assignment to CO. Profit centre is not sufficient, as it's not a CO entity, but EC-PCA. If you want to set different cost centre depending on input paramteres (plant), you can define a substitution (OKC9). Otherwise, if you just want to set a default you could use OKB9 or KA02.
    Regards,
    Eli

  • Cost center planning for overhead calculation

    Gurus,
    I have a doubt regarding the cost center planning for overhead calculation.
    My scenario is:
    There is a service cost center from which a certain percentage I want to allocate to the products as overhead. Now while doing so I have created a cost center and a cost element of type 43 (internal activity allocation). This cost element is the base for overhead calculation. Also I have created one cost element of type 41 (overhead rates). I have defined the credit (of cost sheet) with the cost element of type 41 and the cost center as mentioned.
       Now I am facing a problem while planning the cost center with cost element type 43 through KP06.The system is throwing the error message: 'Cost element xxxx can only be used for activity input'. My understanding is we must carry out the planning for the cost center to allocate a certain percentage to the product cost estimate. If I am not allowed to use the cost element of type 43 to plan, what should I use for the planning?
    Request your suggestion.
    Thanks in advance!
    Snigdho.

    Hi
    Since you mentioned catg 43 cost element, I thought you are using Activuty Type
    To apply overhead on the product during CK11N, you need not plan any value on the cost center... The values planned in the cost center can not be used as a BASE in your costing sheet....
    It goes like this
    1. Your cost estimate has BOM + Routing
    2. So, the cost elements that you would see during CK11N, can be broadly classified into 3 types
    a. Primary cost ele - Material Consumption accounts for BOM components
    b. Secondary cost ele (Catg 43) - If you use any actvity type in the routing
    c. Secondary cost ele (Catg 41) - These cost elements are parasites... They need some basis to calculate the overhead value... That basis can be either the (a) or (b) above.....
    I think, what you are planning to do is Plan Primary cost ele in a cost center and trying to use the same as the Basis.. That wont work!
    What you need to do is
    a. PLan the values in the cost center, say, 100,000 USD
    b. Absorb it on the basis of 2.a or 2.b
    If 2.b is not applicable in your case, since you are not using activity types, then 2.a is the Only option left for you
    Hope it is clear....