HI
I need to create multiple production order for a single item sales order. Is it possible ?
for Eg. i have received order for qty -- 100 & i want to create 10 different production order of qty 10 each. IS it possible ?
I need this to be done automatically.
Please susggest.
regards
Rupesh
Edited by: Rupesh Shah on Sep 2, 2008 11:08 AM
Hi Rupesh,
If you maintain max lot size system always create the planned orders in the same multiples which we mentioned in the material master to satisfy the requirement and if at all any left over qty is there (less than the multiple qty),system will create separate planned order for that qty.
In customization for lot size t code OMI4 FX open the details screen of the lot size which u are using
in the details screen there is a indicator LAST LOT EXACT now if u tick this indicator then the system will create thelot exact
Ex:
order qty 100 pcs,
as per ur reqment the system will create 4 lots of 25 pc each Run MRP Try this if u get the solution,.
Please note Strategy group 82 or 83
With this strategy , When creating a sales order, you can Create a production order directly.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Sep 5, 2008 1:02 PM
Similar Messages
-
Hi Gurus,
I am facing a problem that sap system generates in one sales order multiple production order in mto cases,now from table i want to find out the multiple production order against one sales order pl tellme the selelection criteria.Dear ,
The best way to address this issue to check the report
1.MD4C-Give Sales Order , it will display all the Planned Order , Production Order etc
2.COOIS-Order Header -Stantdar Profile -Enter Plant Code /Order Type , Sales Order Number and Execute , It will diplay all the Sales order with respected line itme .
Please make sure that all the sales order have credit realsed (VKM3-Sales Order ) .
4.You can also check thriough COHV/CO46 etc .
Try and revert
Regards
JH -
Multiple production orders for sales order line item
hello Guru's
In our case Requirements are created in 2 ways
Case 1:
1) Sales Orders are created at Plant level with schedule line category CP
2) Sales Orders are created at Depot level
In the above mentioned 2 cases the requirements are taken as inputs and the process is carried at plant level
Step 1: Automated MDO3.
Sales Orders are created if there is short fall of the Quantity at the Depot and Plant Sales Orders are raised against the plant for which the requirements are generated and MRP run is carried out at Single Item single level.
Step 2:
For the results of the step1 are then transferred and Production orders are created for the planned Orders.
The issues is whenever there is change in confirmed quantity or change in confirmed date the requirements are considered again as inputs and the multiple production orders are getting generated for the single requirement
Actually we dont want this to have multiple production orders
regardsHi,
Can you let us know the strategy group used for this material ? If i understood the query correctly, each time there is a change in the sales order (i.e. increase in qty), there is a triggering of new planned orders to meet that demand.
Regards,
Vivek -
Delevery(Sales invoice) against Production Order
Dear All
In COOIS report can we check the Sales according to Production order.
Within a month can we check the booked sales of that particular order. (Not 1 by 1)
It should be commulative.
Rgds
Pankaj AgarwalPankaj,
You cannot see these informations in one report
i.e. sales order qty/delivered qty/production order target qty/GR qty/WIP qty. input being sales order creation date.
You need to refer to sales order VA05 to get sales order for a perticular month.
take this sales orders ifrom this report(click on the column and CONTROL C)
goto COOIS
in the sales order field, click multiple selection icon click on the green button(import from text file)
you will get import from local file screen, you click on "upload from clip board" icon...you will get the sasles orders and then you can get the details of thoses production orders for the saales order in that month. -
Planned order to multiple Production Orders
Dear Gurus,
I would like to split planned order qty and convert into multiple production orders in CO41, is there any user exits or BADI which makes it possible?
Many Thanks!
//Sreenivastry the following function module
CO_AB_CONVERT_PLANNED_ORDERS
CO_SD_PLANNED_ORDER_CONVERT -
Release of Multiple Production Orders
Hi All,
Does anyone know of a process that would enable the release and close multiple production orders?
Best regards
EarlHi Gordon,
I was sure that was the case. However, I thought I would put it question out there hoping that someone may have devised a solution. SDK it is.
Best regards
Earl -
Gneration of multiple Production Order from multi level BOM
Hi Experts,
My customer has multi level BOM. meaning child item also has its own BOM - 4 Level.
FG-Pack - Make
FG - Make
SFG - Make
RM - Buy
Their process is once they create Production Order for final Finished Good, System should also create Production order for child which it self are of make type and has own BOM defined in system.
They wish that once the create Production order for FG-Pack, system should automatic generate production order for FG and SFG as both of these has BOM defined and are of procurement type Make.
So first they will close the chile production order and receives qty. in ware house, they will issue this child qty. against main production order, and then completes the main production order.
So they remains informed about the child item stock.
My question is SAP Business One supports creation of multiple Production Order?
BR
Samir GandhiHi Samir Gandhi,
There is no build-in function for this task. You need add-on or SDK for the job.
If the sub level BOM items are phantom, you can create a big production order including all sub BOM components. That is system supported.
Thanks,
Gordon -
Need transaction similar to KKBC_ORD but for multiple production orders
HI all,
Have been scouring the system looking for a report which displays production order variance information for multiple production orders.
The best way to describe what we need is KKBC_ORD but with the option to select multiple production orders or a range.
This transaction gives us exactly the results we want, but we have a long list of orders to analyse and to be able to get a list of them all rather than have to go into each individually would be fantastic.
Do you think we're looking at a custom development here ?
Regards
Helen SmithIN these situations, I have sometimes written a "wrapper" program, with a Z version of the transaction....Get the list of documents via user input to your selection options, then loop at that pick list and do a call transaction for each document.
-
Any stanard BAPI have both sales order and production order
hi Experts,
i need to Identify any standard BAPI have both sales order and production order. If such BAPI is not available, create 'Z' BAPI to do the same.it's my require ment?plz give me suggestion it's useful for my project. i will give good points.
thanks and regards,
bbmhi eswar,
can you give me how to do? and what i can use import,export,table and sourcecode bcz i am new in BAPI side even now i am working in SAP XMII project.
so plz guide me.
thanks and regards,
bbm -
Assign batch number from sale order to production order automatic
Dear all, I have a question for all. Please help me in this case
My scenario is make to order
I have a sale order, when i create sale order, i have assigned batch number at each line item.
When i run MRP for sale order (MD50), the system generate a planned order for it and I've converted to production order.
So when I view production order, I think that batch number what I've assigned to sale order will be assign to production order but that is not happen.
So, can you help me solve this problem. I think that sap can assign batch number from sale order to production order automatic but i don't know how to configure that
Thanks allHi,
To the best of my knowledge, when system is generating planned order / production order from sales order system doesnt copy batch number from sales order.
In fact , you are following wrong practice for generating batch no.
Follow procedure like this :
Create sales order without any batch assigning there. Run MRP with MD50 and then convert planned order to Production Order.
While creation / releasing of Production order, you have option to generate batch automatically by following way :
Go to OPKP (Production Scheduling Profile) -> Take your plant & give suitable name to Production scheduling profile-> Batch Management tab -
> Automatic Batch creation in the order maintain this field as
1 Automatic batch creation at order creation
or
2 Autom. batch creation at order release
This will generate batch number automatically at the time of creation or release of order.
Then follow same process i.e. Goods Issue, Confirmation & GR for production order.
So you will get sales order stock in the form of batch managed.
Check & revert if any issue in above flow.
Regards,
Tejas -
How to Park the single invoice for multiple purchase orders
Hi,
How to Park the single invoice for multiple purchase orders?brother this is possible to enter one Invoice fro multiple purchase order.
call transaction MIR7, select " purchase order/Scheduling Agreement" from the PO refernce Tab. then click on arrow. give your purchase orders here.
Thanks -
Sales order and Production order status
Hi Colleagues,
We need to use sales order status functionality, so that when sales manager set status , for example, "dont produce" a production order can not be released.
Has any one dealt with that?
Thank you.Dear,
You can give the reason for cancellation of Sales Order item & block the sales order. When the sales order will get block it will get disappear from MD04 so in next MRP run if there is any planned order it will get deleted. But suppose by that time you had converted the Planned order in Production Order you will get Exception message no. 20 in MD04 list. So this means that there is no requirement & order should be cancel.
Still you want to have restriction of checking the Sales order is open or not, then i hope you are working in MTO scenario & every production order is created w.r.t SO. You can use following Exit in such case.
PPCO0021 Enhancement for Order Release
Exit - EXIT_SAPLCOZR_003. -
Rescheduling Sales Order vs Production Order (Components)
Hi gurus,
Transaction V_RA rescheduling sales order with different filters.
We need a transaction similar to V_RA that rescheduling sales order and production order (for availability check of components). Does it exist??
I will reward points to all answers!
Thank you!Daniel,
It all depends on the business policy of each client. In our case, it was decided that in case Production orders and Sales orders compete for the same material, we will give priority to sales orders. Hence, we changed the timings of the nightly jobs. The backorder job was run first, so that stock was committed there first. Balance if any could go to Prod orders.
But again, that depends on the strategy of your company.
Ashutosh -
Relation between Sales order and Production order
Hi,
In Make to stock scenario how the relation between Sales order and production order are related.In which table we will get the related fields (expect AUFK,VBAK,AUFO).
warm regards,
Surendar reddy.The relation between sales order and prodution order is as follows.
Pass AUFNR to AFKO/AFPO Get AUFPL.
Pass AUFPL to AFVC Get BANFN.
Pass BANFn to EBAN Get EBELN.
Hope this works .
Cheers,
Lakshmi Prasanna Gandham -
Copy from Sales Order to Production Order
Hi all,
Is there a way to copy direct a Sales Order to Production Order (probably for item with BOM).I am using SAP B1 2005
Thanks in AdvanceHello,
Currently you can choose relevant Sales Order from Production Order but only for information purpose.
I think you can try to use SDK to implement it.
Hope this helps.
Regards,
Maggie An
SAP Business One Forums Team
Maybe you are looking for
-
Settlement Posted to future period
Hi All, User has execute the settlement in CJ88 to an asset by giving future period 12/2010. Value of settlement was Zero and no accounting document got generated. Only CO and Asset line items with Zero values. Now when he tries to reverse the settle
-
Finally copying iTunes from my PC to Mac. It was suggested by Apple that I do this via homesharing. Why is it that 1) PC itunes has 2196 songs 2) Mac itunes sees 2192 but only copying xxx of 2093. Why am I missing 100 songs and no, not a purchased
-
I am running Firefox 3.6.13 under windows/xp. All of a sudden, when opening a new tab the "about:tabs" message comes up all the time. I checked the box labeled "do not show this message again" but the "close" box seems to be inactive. Pressing it has
-
Can I exceed the license count on a 5508 series WLAN controller?
Scenario: 5508 WLC licensed for 100 APs. Currently have 78 APs on the controller. Two buildings coming online this week, but there was a snafu with purchasing and license upgrade still in progress. 92 APs total between them. I looked at the license
-
Circuit for auto tuning of pid controller in lab view