Source System conversion for several production SAP
Hello all,
What kind of customizing in table RSLOGSYSMAP i have to do ?
We have 1 DEV and 9 production system P01, P02, .... P09.
In the table i must insert 9 lines, one for each production system ?
DEV -> P01
DEV -> P02
DEV -> P09
Or i insert only one line
DEV -> P0X
and i change the table before each of the nine transport ???
I have to transport the same order 9 times ?
Thanks for your precious help.
Christophe
Cristophe,
I think this must be done on the target system where you will mention the source and target fields .
You do not have to manually enter the values into the table - you can find this under source system conversion defined in the transport connection .
I think the source system just gives it current logical systems and then the target system will do the conversion and hence it will not be 9 entries in your DEV environment but 1 entry each in your productive environment.
Also you cannot have two entries for the same logical source system in this table.
Arun
Similar Messages
-
Source System Conversion in Remote Process Chain
Hi all!
I' working with BI7 SP12 and facing the following problem:
<b>There is no source system conversion for Remote Process Chains, when transporting Process Chains with Remote Process Chains from DEV to QA.</b>
First the following warning appears:
DEV-Destination of Remote Process Chain does not exist on QA-System.
==> The is correct because the DEV-Destination should have been converted to QA-Destination.
Then the following error appears:
Process Chain with the Remote Process Chain was not succesfully checked.
<b>All source system conversion tables are maintained correctly!</b>
The source system conversion works for example for InfoPackages correctly.
But for Remote Process Chain there is neither source system conversion for the Destination nor for Callback Destination. Both should be converted.
Do I have to do it manually??
Or do I have to create the DEV-Destination in SM59 on the QA-System??
==> We want to avoid this...
Thanks for any ideas...
kjPlease note:
When I create the DEV-Destination in SM59 on the QA-System,
the transport gets no warnings and no errors...
But there is still no conversion of the source systems for the Destination and the Callback Destination of the Remote Process Chain to QA-Destinations...
So, i think:
There is no automatic source system conversion of Remote Process Chains and I have to adjust it manually in the QA-System... -
Creating DataSources for File Source Systems in csv format in sap bw 7.0
Hi,
Please explain how to Create DataSources for File Source Systems in csv format in sap bw 7.0. WITH SCREENSHOTS
Thanks
JINI
Edited by: Jini Jayan on Jun 11, 2008 11:36 AMStep 1. Select Source systems under Modelling in the left panel. In the right panel, right-click Source systems and select Createu2026.
Step 2. Select the FileSystem, manual meta data, data using file inte option, and then click to continue.
Step 3. Enter a name and a description for the source system, and then click to create the source system.
Now create an application component
Step 1. Select InfoSources under Modelling in the left panel. In the right panel, right-click InfoSources and select Create application componentu2026.
Step 2. Enter a name and a description for the application component, and then click to continue. (BW automatically adds a prefix of "Z" to the technical names of application components, unlike the naming system used for other BW objects.If u give the name as AC_DEMO it will be saved as ZAC_DEMO in the system.
Now create infosource
Step 1.Select InfoSources under Modelling in the left panel. Right-click the newly created Application Component , and then select Create InfoSourceu2026.
Step 2. Select the option Master data/texts/hierarchies, and then click to continue.
Step 3. Enter your infoobject name, and then click to continue.
Now you will be asked
Infosource(name) assigned to Appln component(name)?
Click continue
Now go back to workbench and see the Infoobject listed under the Application component name (under Infosource)
Right click the infoobject name and select Assign Datasource
Enter the Infoobject name as Infosource name and the source system name and continue
Now you ll get datasource assignment confirmations for Infosource_ATTR and Infosource_TEXT for master data and text.
Click yes and continue
Now you ll be taken to the Infosource(master data) change screen
Source system name will be given
Below that u need to give the datasource name u2026.._ATTR
Click Activate.
Now Click the tab transfer rules
Copy the communication str infoobject names to an excel sheet
For ex if your infoobj are IO_MATNUM and IO_MATNAME (material number and material name) copy and paste as
IO_MATNUM IO_MATNAME
MAT001 TEA
MAT002 COFFEE
MAT003 SUGAR
GIVE YOUR DATA IN THE EXCEL. AND CLICK File Save As CSV(comma delimited) and save to ur system. Give file name as something like infosourcename_ATTR.csv
Now back to the Infosourcechange screen
Source system name will be given
Below that u need to give the datasource name u2026.._TEXT
And activate
Now Click the tab transfer rules
Copy the communication str infoobject names to an excel sheet
GIVE YOUR DATA IN THE EXCEL. AND CLICK File Save As CSV(comma delimited) and save to ur system. Give file name as something like infosourcename_TEXT.csv
Now create Infoobject to load data
Go to Infosourceu2014Appln Componentu2014InfoObju2014SourceSystemu2014rightclick->create Infopackage
Step 2. Select the DataSource Material number (Master data), enter a description for the InfoPackage, and then click to continue.
Give infopackage description as Infopackage:InfoObj_ATTR
Now take care to select the first item in datasource and click continue
In the next screen click external data tab
Click client workstation
Datafileu2026.file name (browse to give the file u saved in ur system)
There will be an option to remove header data from file.remove 1 row.
File typeu2014csv file
Now click schedule tabu2014start dataload immediatelyu2014start.
In the same way
Go to Infosourceu2014Appln Componentu2014InfoObju2014SourceSystemu2014rightclick->create Infopackage
Step 2. Select the DataSource Material number (text)enter a description for the InfoPackage, and then click to continue.
Give infopackage description as Infopackage:InfoObj_TEXT
Now take care to select the second item in datasource and click continue
In the next screen click external data tab
Click client workstation
Datafileu2026.file name (browse to give the file u saved in ur system)
There will be an option to remove header data from file.remove 1 row.
File typeu2014csv file
Now click schedule tabu2014start dataload immediatelyu2014start.
Click the icon below admn workbench to go to monitor and check the load
Or you go back to Infosourceu2014Appln Componentu2014InfoObju2014right clickmaintain master data
Click execute
You can see the data load
Hope this helps!!! -
What is the ideal settings for source system conversion in the following scenario.
1. Source Systems - CRM, ECC6 (ignore flat file)
2. Landscape - Dev Qual Prod
3. System Names
CRM -- CRD, CRQ, CRP
ECC -- ECD, ECQ, ECP
BI -- BID, BIQ, BIP
4. All clients are 100
5. Source System Conversion in BID
Source Target
CRD100 - BID100
ECD100 - BID100
Question: I need the conversion also from the CRM and ECC systems is that correct?
6. Source System Conversion in BIQ
Source Target
CRQ100 - BIQ100
ECQ100 - BIQ100
BID100 - BIQ100
Question: I need the conversion also from the CRM and ECC systems is that correct?
7. Source System Conversion in BIQ
Source Target
CRP100 - BIP100
ECP100 - BIP100
BIQ100 - BIP100
Question: I need the conversion also from the CRM and ECC systems is that correct?
If there are thoughts and/or suggestions otherwise would be appreciated. ThanksHi Niten,
I am not sure about you requirement for these source system mappings.
My guess is, when you transport BI objects from dev to quality or dev to production , you want your BI object to adopt to the source system in the target systems landscape.
example - If you transport a BI datasource which has the source system name in it, or an infopackage, the in BW dev it would point to R/3 dev and after transport it should point to appropriate source system, that is R/3 qa or prod.
If this is the requirement, then you need to maintain the settings in RSA1 in Tools--->Conversion of logical system names.
Log on to QA system and in the 'Conversion of source system names after transport' maintain the source system as dev and target system as QA system. Here you have to maintain the logical names of the systems.
Do the same in production. PN you need dev to prod in this case not QA to Prod. Consult with your basis to confirm the transport route.
In BW -> In SPRO ->SAP Netweaver->Business Intelligence->Transport settings--->Changin Source system name after transport
Click on the page symbol next to it, to read more on this.
Hope it helps,
Regards,
Sunmit. -
Creating source system PC Files on productive system
Hi,
I have a problem, i need to create source system PC Files on productive system.
I tried to do it in RSA1 - source systems.
I could not create any source system - error message :
"No entry for BW_USER in table RSADMIN available"
Where should be problem?
Thanks for help
RadkaHi Radka,
You have two options to do that:
1. Write an ABAP program or use an Infohub to download the data on to your Prod Application server.
2. Download the data to your PC and then FTP to your Prod App server. You can speak to your BASIS on this.
Bye
Dinesh -
Transport of Source System assignment for a Virtual Cube
Built a transport with the datasources, transfer rules, cubes etc..
After transport to my Q system - in the Q system I am not seeing any source system assignment for my remote cube
OBviously it exists in Dev
Everythign else is fine - datasource, infosource trasnfer rules but nothing underneath the infocube where the source system normally is
transport before and after in the transport conenctor picks up nothing to be transported
Logical system mapping table in Q is fine (naturally - because the datasouces got there) - replicate all done
Any ideas?hi Simon,
check sap help
http://help.sap.com/saphelp_nw04/helpdata/en/3b/63c620e18411d4b2d90050da4c74dc/frameset.htm
The source system assignments are local to the system and are not transported.
hope this helps. -
I cant update or remove itunes without receiving the message: the install source (itunes.msi) for this product is not available. verify that the source exist and that you can access it. Has anyone had this problem? Thanks
(1) Download the Windows Installer CleanUp utility installer file (msicuu2.exe) from the following Major Geeks page (use one of the links under the "DOWNLOAD LOCATIONS" thingy on the Major Geeks page):
http://majorgeeks.com/download.php?det=4459
(2) Doubleclick the msicuu2.exe file and follow the prompts to install the Windows Installer CleanUp utility. (If you're on a Windows Vista or Windows 7 system and you get a Code 800A0046 error message when doubleclicking the msicuu2.exe file, try instead right-clicking on the msicuu2.exe file and selecting "Run as administrator".)
(3) In your Start menu click All Programs and then click Windows Install Clean Up. The Windows Installer CleanUp utility window appears, listing software that is currently installed on your computer.
(4) In the list of programs that appears in CleanUp, select any iTunes entries and click "Remove", as per the following screenshot:
(5) Quit out of CleanUp, restart the PC and try another iTunes install. Does it go through properly this time? -
Delete Source System Assignment for a DataMart Infosource in BW3.0B
Hello Experts:
Can one of you assist me with how to delete source system assignment for a system generated infosource(ie., Infosource existing under data Mart). i noticed that in case of an Info Cube, system provides an option to delete the source system assignment but not for an ODS.
I am trying to delete the system data source 8* that has been assigned to the data mart info source 8* and reassign the data source to my custom info source.
Any ideas would be highly appreciated.
BTW, we are on BW3.0B
Thanks,
RagavanHi,
Go into the infosource with change mode. Open the transfer Rule/transfer structure and hit the delete button. It'll ask for delete datasource assignment. That would delete the source system assignment.
Cheers,
Kedar -
Source system connection for DB connect.
hi experts
presently the data is available in sql server(legacy system).so we have to extract data from sql server to bw server through DBconnect.tell me the procedure for how to connect sql server to BW server through DB connect.hi Suresh,
there is pdf 'Transferring Data with DB Connect' https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/2f0fea94-0501-0010-829c-d6b5c2ae5e40
and bear in mind ...
1. You have to create a special login for the extraction.
You should add this login to the db_ddladmin database role in the corresponding database. This generates a similar DB user at database level. The user you use must have the 'CREATE VIEW' authorization at least. This is contained in the mentioned role.
2. For the extraction, you should only use DB views that were created under this DB user. (See also type conversion, naming convention, and so on).
3. The selected user should be granted the required authorizations (SELECT at least) on the source tables, or on the columns of these tables.
4. The especially created login is to be used in the logon information when you are setting up the DB source system in BW.
hope this helps. -
Source system conversion doesn't work after transport
Just transported a query to BW Production and found that the source system is still the same as in DEV.
The conversion is there (QAS-->PRD). But the conversion doesn't seem working in the transport.
Can anyone tell me how to troubleshoot this issue?Hi,
Please check the following:----
1. RSA1->Source Systems --> Select the source system -->Check. It should take you to the correct source system with a Remote logon.
2. Check the logical system mappings in RSLOGSYSMAP table.
3. http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/70a7b233-8be5-2c10-4190-aed723af5373
Regards,
Suman -
Same logical system name for two productive systems - BW, PI issues
Dear all,
we have a productive system which serves two companies (different company codes). This system is connected both to BW and PI for both companies.
There is a requirement that these two companies must use their own system, so the whole landscape (dev,qa,prd) will be copied to different systems (different server with different system id).
As a result of the above procedure we wll have two different productive systems, as required, but we wll have the same logical system name for the two productive systems, which must be both connect to bw and PI.
However as far as I know:
- we cannot connect systems with same logical system name to BW,PI
- we cannot convert logical system name of the one of the two productive systems as they are productive and so this is not supported.
How can we overcome the problem?
Please advice.> However as far as I know:
> - we cannot connect systems with same logical system name to BW,PI
> - we cannot convert logical system name of the one of the two productive systems as they are productive and so this is not supported.
Right.
> How can we overcome the problem?
Since you split up systems (or plan to) I highly recommend booking an SLO service (http://service.sap.com/slo). Those people have to the tools and the knowlege to help you. I would not do this on my own.
Markus -
Source system in Development & Quality & Production
Dear Experts,
Normally we do developments in Development server,so we create source system connection to R3 Development server (say 120) and create DataSources, DTP and process chains based on the Source system 120.
Now my Doubt is when we transport the developments to QAS, how will i get the data from R3 Quality Server 500 (because my developments -DataSources, DTP,Infopackages and process chains are connected to R3 dev 120).
how should i do this?
Please give me your valuable inputs.
Regards
BI LearnerHi Friend,
In general this connections done by Basis people.
So in your case automatically mapped quality r/3 to bw quality, but first replicate changes from r/3 quality to bw quality before moving changes from bw dev to bw quality.
this scenerio is normal wherever you go either in production perspective also.
SAP BW(Dev)---->SAP BW(Quality) and simaltaneously mapped SAP R/3(120)--->SAP BW(Dev),SAP R/3(500)---->SAP BW(Quality)
llly mapped production also, this is general landscape.
I try to give scenerio and hope it should helps out.
Thanks-RK -
Source system icons changes when connecting SAP BW to mySAP ERP 2004
Hi,
Just an Interesting observation in relation to the creation of source systems in SAP BW to SAP Web AS 6.40 based systems (mySAP ERP 2004, mySAP SRM, etc).
I thought it would be interesting to share!
The behavior is logical but can be a surprise for a BW administrator who is not aware of the new internal SAP BW systems within mySAP ERP 2004.
Scenario:
The customer was connecting a stand-alone BW system to two new systems with latest and greatest mySAP ERP 2004 (ECC 5.00) and mySAP SRM.
Observation:
In the past the SAP R/3 source system would be created with a "SAP R/3 icon" indicating a SAP Source system.
<b>As of mySAP ERP 2004, the source systems will be created in the SAP BW standalone system with the "SAP BW System icon".</b>
Note: This is also the same behavior for new releases of mySAP SRM, and other SAP applications that are <u>based on SAP Web AS 6.40 or greater</u>
Why?:
The standalone SAP BW system is connecting to a system that contains an internal SAP BW system. The standalone SAP BW system determines that it is possible to extract <u>both</u> from the internal BW System <b>and</b> from the Plug-in extractors. It simply denotes that this source system is a SAP BW system and uses the BW Source system icon. (Remember SAP BW is client independent*!).
Note: This behavior will still occur even if you do not use the internal SAP BW system within mySAP ERP! It is there whether you use it or not.
Second Note: You can still use the ERP Content extractors from the mySAP ERP Source System as you did in prior releases.
Another related observation:
I would expect that this case will probably be true even if you only use the internal SAP BW.
Scenario: You use the internal SAP BW in another client in the mySAP ERP system than your ERP processing.
Result: The connection between the BW client and the ERP client source system(s) (i.e. client 001 for ERP, client 100 for BW), both the 'myself' and ERP client source systems, will show up as BW source systems!
Source system 001 and source system 100 will be displayed as SAP BW icons because SAP BW is client independent*
user master and authorizations are client dependent
I hope this was interesting.
Cheers,
Mike.Hello,
I used my user id to login. I recieved a message :
User already exists in source system I continue:
Anothre window pops up : "Check RFC connection" and it asks
'RFC connection already exists in source system . Do you want to check, use or cancel source system connection'
Here I select Use - but i get an error : Error in source system'.
how can i track down this error.
Kindly inform.
Regards,
Nikekab -
Source system Connection for DB2
Hi All,
I need to create a source system for DB2 in SAP BI 7.0.
I have some information about the DB2 database but not sure if that info is sufficient to create a source system for this server.
The info I have for DB2 server SERVER1 :
FOR SERVER1:
1) Username: User01
2) DB Password: XXXXX
3) Conn. Info : BCDT
I could get the info that database name is entered with the parameter u201CDB2_DB_NAME=u201D (is that right ?)
I believe that there needs to be more info for "Conn Info" other than just what is provided.
Regards
Shalabh JainHi Jain,
Hope this will help you....
ETL PROCESS WITH DB2
Thanks,
Vijay. -
Source System Error for 0Material_Attr
Hi Gurus,
I have New BI System, when i m loading 0Material_Attr, the whole data is coming but with the status Red. May b the error is with source system. I checked in PSA maintenance and the error detail in source system is mentioned below.
"Value 'A3000014500L ' for characteristic 0MATERIAL is in external format"
"0MATERIAL : Data record 1 ('A3000014500L '): Version 'A3000014500L ' is not valid RSDMD 194".
for detail error check the link below
https://docs.google.com/document/d/1v4uHeg6Ci29zv0qJ21dOH7gttuQyg_VZsLM2IMfZEuM/edit?hl=en&authkey=CLnd8P4H
can anybody help in this regard.
Thanks in advance.
Regards
Manna DasHello Manna Das,
0Material has conversion Exit MANT1 which converts the Material in the external format to internal format of the system.
Can you please check if the Converison exit is there?
Thanks,
Sarat
Maybe you are looking for
-
.gif not working with gallery
.GIF animation image works on internet browser but when saving it and view it in gallery it does not play. On Samsung galaxy tab 10.1, .GIF animation pictures works in gallery so how come it does not work on my Sony tablet s when its using the same a
-
Hi! I have this situation: Document class: private var controller:MyController = new MyController() addChild(controller) in MyController Class: later in the code... stage.addEventListener(MouseEvent.MOUSE_MOVE, mouseMoveListener); MyController class
-
Installation error, can you run a 32 bit database on 64bit Linux?
I have Oracle Linux 64bit but downloaded the 32 bit version of 11g as the 64 bit required 4gig of Ram (which would max me out) I have followed the pre install instructions but when I ./runInstaller I get: ./runInstaller: /home/michael/database/instal
-
Creation of document in CProjects which is sent to DMS system
Hi all, I am trying to create a document in CProjects which would be linked to the DMS system. When I try to create a document with reference to another the document number is coming blank. I even tried transfering the doucment after save. Actually I
-
New feature: quick settings?
Hi Xperia people! I was just wondering... as I see in the changelog for the new update 4.4.4 – Quick settings – customise your settings to access what you need quickest What is the difference now? I can't seem to find where is the "new thing". Any he