Hi All,
Can any 1 tell me that is there any report that shows Released Budget versus Actuals
Hi,
Use this tcode to compare actuals vs budget.
S_ALR_87013557 - Budget/Actual/Variance
Muzamil
Similar Messages
-
Standard report showing Permitted Payees linked to vendor
Hello,
Does anyone know if there is a standard SAP report that shows the permitted payees linked to a vendor without having to go to table LFZA?
For example, I have a vendor 112222 ABC company and on the payment transactions global screen, I have defined three permitted payees in field EMPFK:
5555 ABC East
6666 ABC West
7777 ABC South
I am looking for a report that shows me:
Vendor Permitted Payee
112222 ABC Company 5555 ABC East
6666 ABC West
7777 ABC South
Does anyone know if this exists as a standard report?
Thanks,
LindaLinda
I am unaware of a standard report like this.
The only standard reports are the Vendor list (S_ALR_87012086), Address List (S_ALR_87012087) and Display changes to vendors (S_ALR_87012089/90).
The only way to do this is write a quickviewer/SAP Query report. -
Copied standard report shows error.
i just copied the standard report RM07DOCS TO YRM07DOCS
AND EXECUTED.
IT SAYS LAYOUT /GR VKP DOES NOT EXIST FOR YRM07DOCS.
and if i execute without giving any layout , it shows only few fields of output
PLEASE tell ME TO SOLVE THE PROBLEM to get the layout , and complete output..
Edited by: Dastagiri on Dec 7, 2011 4:30 AMDastagiri wrote:
i just copied the standard report RM07DOCS TO YRM07DOCS
> AND EXECUTED.
> IT SAYS LAYOUT /GR VKP DOES NOT EXIST FOR YRM07DOCS.
> and if i execute without giving any layout , it shows only few fields of output
>
> PLEASE tell ME TO SOLVE THE PROBLEM to get the layout , and complete output..
>
> Edited by: Dastagiri on Dec 7, 2011 4:30 AM
Hi,
How did you copy your report? Check if there are includes in program RM07DOCS and it is copied in you Z report.
Also, check if your selection is made thru Screen-painter?
Reetesh
Edited by: Reetesh on Dec 7, 2011 5:40 AM -
Standard report show the confirmed quantity in sales order
Hello
i'd like to know t-code for report show the confirmed quantity and the remaining quantity of sales order
For example : i create sales order with quantity (1000) and the quantity of material in storage location 600 , so i want report display the confirmed quantity ( 600) and the remaining quantity (400)
ThanksSearch the forum before posting. Check in VA05
G. Lakshmipathi -
Cost center budgets report showing double budget amount
Hi,
I entered $5000 as the cost center budget in t.code KPZ2 however in the cost center budget report S_ALR_87013648 its shown as $10,000 which is double of what i entered.
May i know why is this?No answers yet
-
WBS Standard report and customized reports
Hi Frnds
we have one SAP standard reports for WBS elements ( plan/actual/variance) and one whichis customized project management report in Projects systems but both the reports are showing different balance.
is there any particular reason for showing different balance for both actual and budget colum?
plz reply asap
thanks
manishHi,
Thanks for reply...
If u have any idea regarding other reports, please let me know...
Thanks.. -
Report for released purchase order
Hai guru's
this is second time but i did't get any good replay please consider this, i want any standard report for released purchase order,means(i released two backdated po today next day i verify the report ME2n,those po are not display, the system take only document date not released date, now i am using CDHDR through this i got the report. but it is big process, so once check this and send your valuable solution.
PrasadHi Krishna,
You could use Me2N with the dynamic selection coupled with normal selection screen.
In Dynamic selection(3rd icon in screen).....you can select for which company code, release indicator as released....and save it as default variant.
hope this should solve your query
Sk. -
Standard report on Installation facts inconsistencies
Hello
Is there any standard report showing inconsistent installation facts details? Any help would be greatly appreciated.
Thanks
RajatHi,
S_KK4_82000014 gives you a list of Operands based your your specified parameters, but to check for consistency, you would probably need to do a mass overall check (EAMACH).
Regards,
Ivor Martin -
Report showing Contract, sales order and invoices created
Hii All,
Is there any standard report showing the sales contract, sales orders created with reference to contract and the invoices with some relevant details such as customer, material, invoice value etc.
If i go to VF05 and then select the a line and see the document flow, i get the contract number, sales order number.Hi,
You need to create a report of this requirement only through development.
Rgds,
Sivarajesh. J -
Standard report to see open delivery quantity
Hi,
Is there any standard report to check the open delivery qty?I mean,if I am having a sales order of 100 qty and I have issued 25 materials then the remaining 75 qts report needs to be viewed.Is there any standard report showing--
SO No Delivered qty Open qty
regards
somnathHi somanath,
just go for VL10H transaction code i think you will get what items and how many quantity pending for shipping
it may solve your problem
regards
bvdv -
Report showing sum of Budget/actual cost of WBS elements from diff proj
Hi,
i need to display consolidated budget/cost report for separate projects. (example PROJ 1 and PROJ 2)
in both projects, they have similar structure of WBS (same descriptions etc..)
in reports i can run both project but the values are summarized for the entire projects.. (results = Total of PROJ 1 + total of PROJ 2).
but i need report showing subtotals of WBS 1.1 of PROJ 1 + WBS 1.1 of PROJ 2 and so on...
i thought i could do it using CJI8 but i cannot filter it by description and do subtotals since it does not have a description column.
is my requirement possible with standard or need to customize a report?
thanks in advancehi
please try to use Co Object Name field with sub total -
Standard report for budget allocated, actual consumed, amount capitalize
Hi,
I need report for following condition: Is there any standard report for the same?
Once the project is capitalized, the system should provide in one report
the budget allocated, amount incurred, amount capitalized,
Date of capitalization and remaining expenses in desired WBS as on desired date.
Please suggest me, if any standard reports are available?
Regards
BipinDear Bipin,
1) S_ALR_87013558 - This report will give you information about Budget, Actual, Commitment, Assigned, Budget Avail.
2) S_ALR_87011990 - Asset History Sheet or S_ALR_87012050 - Direct Capitalization ( Asset Acquistion )
Hope this will meet you requirement.
If found useful reward the points.
Regard's
Sandeep N.Theurkar -
Budget Vs Actual report for FM
Hi SAP FM Gurus
We had implemented BCS in ECC 6.0. We are able to get the availability control for the commitment item & fund centre through the release procedure for specific periods.
In the above said situtaion, we are facing the following issues.
1. The Budget is released for 2nd period of a fiscal year. But when we make the PO for 3rd period, the system is not checking whether the budget is released for that period & the system is checking only the released budget for the whole year.
Solution Required : If we release the budget for a specific period, the actuals should be postable against that period only and not for the other period.
2. We want to know about the standard report to know about the Budget Vs Actual for a given fund centre / Commitment Item for a given period & not for the whole year.
Through some light on the abovesaid issue.
Regards
R.KarthigayanHI
THE AVC ACTIVATED FOR ANNUAL BASIS.IT IS NOT ON PERIOD BASIS.
YOU CAN RESTRICT THIS THROUGH THE RELEASE COMPONENT OF SPECIFIC PERIOD.
NORMALLY IN ANY ORGNISATION THERE WONT BE ANY FUTURE TRANSACTION POSTINGS.
FOR THE PAST PERIODS YOU CAN DO IT BY ASSIGNING THE BUDGET IN SPECIFIED PERIOD.
YOU CAN USE THE FOLLOWING REPORTS.
FOR BCS CONTROLL
FMRP_RW_BUDGET - Budget Overview
FMRP_RW_BUDVER - Comparison of Budget Versions
FMRP_RW_BUDCON - Overview of Budget Usage
FMRP_RW_EFFYEAR - Budget Overview After Year of Cash Effectivity
FMRP_RW_COVRGRP - Budget Usage of Cover Groups
FMEDDW - Display Budget Entry Documents
FMLIDW - Display Change Documents
FMRP_RFFMEP1OX - Commitments and Funds Transfers
FMRP_RFFMEP1FX - FI Postings
FMRP_RFFMEP1CX - CO Postings
FMRP_RFFMEP1AX - All Postings
FOR FORMER BUDGETING.
FMRP_RFFMTO30X - Totals Records
FMRP_RFFMEP30X - Line Items
REGARDS
MALA K REDDY -
Cost element and Line item reports show different actual costs
Hi PS experts,
My client has an issue pertaining to actual cost reports. The cost element report shows actual costs $42,000 for one WBS and when I double click to see details the value it shows is $2100. Even when I checked line item report for this WBS the value is $2100. What could be the reason for getting different values? If some one throw some light on this it would be great helpful to me
Regards,
LaxminarsimhaLaxminarsimha
The values in CJI3 should be correct and will include all postings (e.g. Settlement values) and possibly Actual Revenues unless a filter is in place - so take this as being your correct figure to start with.
Your drilldown will show the same value as CJI3 because it is CJI3
Any cost element report you are using is probably correct for what you are asking - is this a Standard Cost Element Report you are using or is it bespoke
One thing to be careful of when you drilldown on Cost Element Reports is that you do not always get the a make up of the value you have drilled down
e.g.
Cost Element Report was run for Period 1 to 6 2008 and shows £100.00
You drilldown and sometimes the drilldown automatically shows ALL line items e.g £500.00 (not just the values for periods 1 to 6 of 2008 which you may expect £100.00)
In the past I've removed the drilldown capability from bespoke cost element reports to prevent drilldown to the line item report (which is CJI3) because of this problem.
Usually where values for a a number of periods only (not total costs) was required
Other factors to consider
Revenues/Settlements may be excluded from Cost Element Report but will not be excluded from CJI3 unless you specifically restrict
You need to identify which types are postings are missing from the Cost Element Report (what is common...cost element, dr/cr indicator, business transaction)
I've also hit the mistake in the past where I've asked for periods 1 2007 to period 3 2008 and instead of giving me just over a years worth of actual it gave me actuals for periods 1 to 3 for 2007 and 1 to 3 for 2008.
Hope this helps
Steve -
A report showing all release refused purchase orders
Dear SAP Gurus
Please assist, I need to run a report showing a list of release refused purchase orders.
CNHi,
I dont think there is a standard report for that.. you can have the details from table EKKO with release indicator as 1 (EKKO_FRGKE)
Regards
Merwyn
Maybe you are looking for
-
Execute planning function in Web template for selected item in anylisys ite
Hello all. I have been trying several different solution for this issue I have, but could not ,make it work. Hopefully, any of you can give me some ideas. Initially the scenario seems to be easy. I have a Web template were I show a query analysis ite
-
Hi Gurus, how to monitor idoc and how many IDOC s come to in XI /PI ? Regards sreeni
-
Internal MBP HD up as external - cant see Admin user
Woke up to my Macbook Pro a couple weeks ago sitting in a puddle of water. Fried. Went to Apple Store and had them take out internal hard drive and bought an external case for it. They said the HD looked ok and was worth a shot. Today I finally found
-
I have been unable to uninstall google notifier following their instructions for my MacBook Pro. Any ideas what else to do? There is no icon in applications. I have an icon in activity moniter but I cannot delete it.
-
I am a Gentoo user. In portage kde packages are splited out. For example: I can install "ksnapshot" or "kpdf" without pulling whole kdegraphics package with a lot of other tools for graphics. In Arch Linux i have to install whole kdegraphics package