Hi
Tds used to be deduted at the time of payment or invoicing which one is ealier. Based on the contractor you have deducted accoring to the section (194-C).
Down Payment :-
Vendor A       950
TDS                50
Bank                  1000
Purchases :-
Purchases      3000
To TDS                   100
To Vendor A           2900
Final payment to Vendor :-
Vendor A    1950
TDS              50
Bank              2000
Warm Regards,
Sivakumar Sathiyamoorthy

Similar Messages

  • SAP TDS Advance process

    Hi All,
    My client doesn't want to use the standard process for Advance TDS Process like F-48, F-54 and F-44 Etc., Can any one worked on the this kind of scenario. If yes can you please provide me the solution. I know if we deviating from standard will be the implications in TDS Process. Can you please let me know if we follow the below options.
    Option 1
    1. Client want to use FB01 for advance posting for TDS Transactions.Manually entering the TDS Amount using posting key combination with Advance TDS Tax code. Is there any impact on the quarterly returns/challan printing???
    Option 2
    1.  For advances also TDS Tax code want to create as Invoice tax code. If it is the case where will be implications while generating the TDS Challana and quarterly return form26q ??
    1. FB01
    Dr) Prepaid Expense (GL account) 5000
    Cr) AP (w/ Vendor code) 4500
    Cr) TDS payable 500   TDS code 1 (Advance TDS Code)
    2. Vendor payment - FB05
    Dr) AP (w/ Vendor code)    4500
    Cr) Bank                         4500
    3. Expense - FB60
    Dr) Expense 8000
    Cr) AP (w/ Vendor code) 7200 TDS code 2 (Invoice TDS Code)
    Cr) TDS payable 800
    4. Reverse of first transaction (FB01/FB08)
    Dr) AP (w/ Vendor code) 4500 TDS code 1
    Dr) TDS payable 500
    Cr) Prepaid Expense (GL account) 5000
    5. Final payment
    Dr) AP (w/ Vendor code)    2700
    Cr) Bank                         2700
    6. Remittance challan - J1INCHLN
    Dr) TDS payable                 800
    Cr) Bank                          800
    Operational wise the above process complicate, but client doesn't want use the standard process. Please let me know the what will be the implications if we follow the above options in case of quarterly return filling and reports. Is the quarterly returns will contain the TDS Advance amount information as well?
    Thanks,
    jagadeesh.
    Thanks in Advance,
    Regards,
    Jagadeesh.

    Hi,
    As you know that TDS GL account automatically trigger at the time of invoice posting from the TDS customization.
    As per your process system won’t find the TDS manual postings in J1INCHLN, the same scenario I have worked for one of my previous clients. Only the automatic TDS GL postings will appear in the J1INCHLN.
    If your client don’t want the TDS certificate printings then go for your process, if your client wants the J1INCHLN clearing and TDS certificate then you have to follow the standard process.
    Please let me know if you need any further help.
    Regards,
    Ravi

  • TDS advance adjustement effect in invoice

    hai,
    Regarding WHT, while doing advance payment to vendor for Rs.50000.00, system will calculate TDS for Rs.50000.00. Then we received the bill from vendor for Rs.100000.00, then the system will calculate TDS for Rs.100000.00. But system want to dedcut TDS only for Rs.50000.00. How it is possible?
    I know one option, while entering invoice, select Withholding tab and system will display the keys and base amount. In that base amount if we enter the balance of Rs.50000.00 means, sytem will automatically calculate only for Rs.50000.00. But i don't want to enter every time. System want to calculate automatically.
    Can anyone give me an idea about this.
    govind.

    Hi,
    While making an advance for Rs.50000, system will deduct tax on Rs.50000. Then when Invoice is received for Rs.100000, then the system will calculate TDS on Rs.100000 only. Then when you do the clearing between the down payment and the Invoice using T.Code - F-54, the system will reverse the excess TDS deducted (ie) it will reverse the TDS deducted during down payment.
    Try this.
    Cheers
    V.Krishnan
    (Assign Points if useful)

  • TDS issue_ urgent

    HI,
    I have done migo, when we are doing  miro TDS not deducted in that doccument. where TDS exemption has been updated in Vendor master for one vendor but while booking TDS is not deducted as per specified exemption %.
    please Guide me
    Regards,
    Venkat
    Edited by: KVenki on Dec 29, 2011 4:59 AM

    HI Anil,
    I have checked as per ur mail, Here when my user Selceting Bus.place xxx1 it will calculated TDS, when selceting Bus.place xxx2 its not calculated, is there any raisen in the same PO line item they have selected diff bus.places pls clarif.
    thenks
    regards
    Edited by: KVenki on Dec 29, 2011 5:54 AM

  • Wrong TDS percentage is showing in TDS Certificate for partial payment

    The TDS percentage is not showing correctly in the TDS certificate for partly bill payment. While adjusting the advance payment with partly bill TDS amount is adjusted with the payment correctly but while calculating the percentage system is not calculating the advance part of the TDS and printing the wrong percentage in the TDS certificate. For example –
    The Total Bill amount is 10000/-
    Advance payment amount is 1000/-
    Assume TDS percentage is 10%
    Partial payment amount is 2000/-
    Description     Base Amount     TDS     Percentage
    Total Bill          10,000          1000     10%
    Advance          1,000          100     10%
    1st part Payment 2,000     190       9% (Wrong)
    Rs. 10 is adjusted with the TDS advance. So the TDS percentage should be 10%.
    In TDS cerficate the TDS percentage is printing wrongly. ERP Version we have 4.6C and CIN veriosn 40A.

    Hi
    check OSS Note No 1286144 my be it's helpful to you.
    satish

  • ORA-29278: SMTP transient error:421 Service not available error?-V.Urgent

    Hi All,
    I am trying to use utl_smtp for sending mails.
    1. I am not able to set SMTP_OUT_SERVER for scope =Both,i can use only SPFILE, Why?
    alter system set smtp_out_server = '<ip-address:port' scope=Both;
    my server ip address 172.16.1.10 and port-25
    2. I am using oracle 10g Rel1 database.
    3. I am using UTL_MAIL.SEND_ATTACH_RAW procedure for sending mail with attachment.
    Please help me as i tried so many things but no luck.
    This is very urgent.
    Thanks in Advance.

    Urgent is it?
    What makes you believe that your request for help is more important than someone else who has requested help? It's very rude to assume you are more important than somebody else, and I'm sure they would like an answer to their issue as soon as they can get one too, but they've generally been polite and not demanded that it is urgent.
    Also, you assume that people giving answers are all sitting here just waiting to answer your question for you. That's not so. We're all volunteers with our own jobs to do. How dare you presume to demand our attention with urgency.
    If you want help and you want it answering quickly you simply just put your issue forward and provide as much valuable information as possible.
    You will find if you post on here demanding your post is urgent then most people will just ignore it, some will tell you to get lost, and some will explain to you why you shouldn't post "urgent" requests. Occasionally you may find somebody who's got nothing better to do who will actually provide you with an answer, but you really are limiting your options by not asking properly.
    Looking at your question:
    1. I am not able to set SMTP_OUT_SERVER for scope =Both,i can use only SPFILE, Why?Why indeed? What problem are you actually having? Is it giving you an error? If so, what is the error?

  • Mir7 bill amount tds

    Hi
    Good morning to all
    I am making one smartforms in which i am not able to find table-field name
    Transaction use   mir7 .
    bill amount
    tds
    passed amount
    passed amount  =  bill amount  -  tds
    its urgent . point will be awarded  .
    Regards
    Rakesh singh

    HI Rakesh ,
    i think u need to get the document amt of the TDS g/l account.
    u need to find out more info from ur Functional ppls.
    regards
    Prabhu

  • CHANGEOVER FROM TAXINJ TO TAXINN

    HI all,
    TAXINJ and TAXINN cannot co exist in the same system.
    If you are talking about technical Upgrade, then I don't think this would be feasible since old Txn would have got posted with TAXINJ procedure with rates as defined in Tax codes and now after migration to TAXINN in same box, the system would pick value from Condition records.
    Just check this basic point of feasibility before we go ahead and look for changes.
    In SuX the change is for existing implementation, here at present they have R/3 4.7, and  are now in the process of technical upgrade to ECC 6.00; TAXINN is required to be implemented in the upgraded version.
    At present they are using around 129 pricing procedures, 25 sales org,220 tax codes in TAXINJ. Suzlon has 21 company codes, 219 plants and 1300 end users the whole nature of group activities results in use of all possible types of indirect taxes in India like VAT, CST, Excise, Service Tax etc...
    i have tried to search on sap help, service market place and others but could not come across any document for the change over. However i will try again.
    what are the things i need to take care before any implications busisneww point of view, what will be the status of  open sales order and purchase orders, and  splitting delivery docs. which are under process, what will be the cutoverstrategy.
    WHAT WILL BE THE IMPACT AT DB LEVEL AND BUSINESSLEVEL.
    RELEASE NOTES OR OSSNOTES, ANY DOCUMENT STEP BY STEP IS REQUIRED asap.
    tahanks in advance.urgent
    need ur help and guidance, thanks in advance.
    sri_cnu

    Hi Ravi
    Thanx again. It was helpful.  I really want to know the answers for these three questions.
    1. Is it possible to migrate from TAXINJ to TAXINN during the middle of the year, or is there any restriction, that it has to be done only during the start of the fiscal year.
    2. Is it possible to see the data, once we have migrated from TAXINJ to TAXINN (i.e. data in TAXINJ)
    3. what are the difficulties that would be there while migrating from TAXINJ to TAXINN.
    Please let me know
    Regards
    Rajaram

  • How to update weblogic.properties in order to support English & Chinese

    <URGENT PROBLEM>
    hi,
    how to update weblogic.properties in order to support English & Chinese
    version in a sing weblogic server?
    Thanks in advance
    <URGENT PROBLEM>

    If you are using JSP as your mechanism for content display, you should use
    the contentType parameter to specify the character and coding of the JSP
    page any character encoding of the resulting stream. So far, we have not
    done a good job of documenting how to produce localized content in JSP. I
    have filed an issue for the documentation folks to work on it. For now,
    take a look at section 2.7.4 of the JSP specification version 1.1.
    Thanks,
    Michael
    Michael Girdley
    Product Manager, WebLogic Server & Express
    BEA Systems Inc
    fxy <[email protected]> wrote in message
    news:8ffr11$59d$[email protected]..
    <URGENT PROBLEM>
    hi,
    how to update weblogic.properties in order to support English & Chinese
    version in a sing weblogic server?
    Thanks in advance
    <URGENT PROBLEM>

  • ChaRM in solution manager

    Dear experts,
    We had implemented the SM3.2 (change request management ,EWA and Support desk) in 3-tier landscape, my question is whether we can implement the Change Request Management in 2 tier landscape .
    The scenario which we have is 2-systems -
    Production with 700 & 900 client and Development with 200 , 300 , 400 .
    200---Development client
    300---Customizing client
    400---Testing client
    700---Pre production client
    900---Production client
    Usually by normal transport system we use to take the request from 200 & 300 to 400, after that we again test it in 700 then take it to 900 production client.
    Now please suggest that how we can configure change request in this scenario, if not possible can clients within the system be configure as different system.
    can we configure the ChaRM as 200>400>900 where 200 & 400 are the clients of same server or 200>700>900 .
    Thanks in advance|| urgent
    Chirag Kohli

    Dear cherry , prakash and tom..
    See i think i am still not able to clear the scenerio.....
    1. Dev box is having 200 300 400 clients
    2. Prd is having 700 900 client ..now i want to take the request by both of following routes -->
    1. 200--> 900....as the 200 is workbench client so testing not required
    in this case i got stuck after releasing the request frm dev server .........now no option in change document for importing it directly to production is there .
    2. 300-->400 for testing in dev customzing scenerio.
         then 300--> 700 for testing in PRD customzing scenerio.
         then from 300 --->900.
    no idea how to do this.
    i hav done all the customizing required alongwith CTC=1 extended tr. control as i have already had configured CHARM in 3-system landscape
    simply i want to ask that what should be the TMS route structure for such kind of scenerio.
    Also u have mentioned that it can b done through transport gr.........is it transport gr or transport target group u are talking abt.
    it will be very grate full if u can forward me the e-mail id at [email protected]
    chirag

  • QUES ON INTERCOMPANY SALES

    i have two ques
    1) while creating a  sales order , how we can find out it is an intercompany sales or
    2) methods of deleting a sales order
    3) table name - delivery item categories
    4) which invoice will go to profit centre in intercompany
    thank you in advance
    urgent replies will be highly rewarded
    regards
    kishore

    Hi Kishore,
    Go thr the below links:
    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b911d43ad11d189410000e829fbbd/content.htm
    REWARD IF IT HELPS
    regards
    Srini

  • Clarification sought on 'Qualifiers'-segment in ALE

    Hi friends,
    Could anyone plz explain me about the qualifiers which comes under segment in ALE.Thanks in advance.Urgent.

    Ok, so the login process APEX creates when you create a new application handles the post login stuff. Now if this is an automatic feature then perhaps the Post-Authentication Process Help should be changed to reflect this. Now to work on the Logout URL

  • TDS at the time of advance payment(urgent)

    Dear all,
    I have done the configuration of  TDS at the time of invoice and payment. i checked. it is woking well both at the time of invoice and payment.
    The issue is when i do the advance payment and when i click the withholding tax tab, it is not going into that tab and because of that tds at the time of downpayment is not getting deducted.
    Since we have short time for golive i want to solve this issue urgently.
    please guide me.
    Will award full points.
    Thanks & Regards,
    A.Anandarajan.

    Dear Friend,
    First create the down payment request in F-47, then make the payment of this down payment request in F-53 or F-58 ( with special GL indicaator F)
    That should resolve the issue.
    Assign points if useful
    regards
    Venkatesh

  • TDS not calculating at the time of advance payment to vendor

    hello gurus,
    need urgent help ,
    TDS not calculating for advance payment made to vendor, checked configuration in detail. payment WT type is marked as central invoicing prop.all other config is o.k.
    regards,
    Anand

    Hi Anand,
    Mark the WT type as No central invoicing. U can still deduct TDS. Central Invoicing concept is mandatory only in Argentina.
    what u have to do is, configure the WHT code and the WHT type for "Define Withholding Tax Type for Payment Posting".
    Then include the same in the vendor master in FK02 under "withholding Tax accounting" tab. mark it as liable.
    these settings in the master are enough.
    then when u run the f-48 for downpayment, after entering the details in the first screen and u press enter, the system will give a msg that the vendor is liable for WHT.
    this is how u can do it.
    award points if helpful.
    Regards,
    CA. Karthik Narayan N S
    SAP-FICO Consultant

  • Screen shot help for withholding tds on advance?

    can someone please help urgently
    When the withholding tax type is mapped to vendor master record it gives an error saying that entries in table T0 59Z not existent.I need to develop screen shots for " advance to Vendor& TDS on advance"

    HEllo,
    Firstly please check in your customizing that you activated the
    extended withholding tax functionality by following this path in
    the IMG:
    financial accounting global settings
      -> Comapny code
        -> Activate the extended withholding tax
    Also, there is an additional field "W/H tax catagory" which should be
    optional in your account group settings. Please check this by using
      Transaction: OBD3
        -> Clicking the relevant account group
          -> Company code data
            -> W/H tax data.
    Please note that when you create/change vendor master data, if you
    navigate to the withholding tax screen, you have to FIRST enter the
    withholding TYPE. Additionally, you may enter a withholding tax CODE
    (defined for this withholding type), which is going to be proposed when
    posting an invoice for this vendor. If you first enter the withholding
    code without having entered the withholding TYPE, the foreign key check
    leads to the message 00058 you described in the problem.
    Have you check if the tax type exist in T059Z?