Total Delivery Cost for partial Item delivery

Hi Guru,
I have a requirement wherein I have to apply the total delivery cost for partial Item delivery.
For example: Even if there is partial GR, delievery cost must be paid in full.
Say PO is for 100 PC and delivery cost is 100 EUR. Now at MIGO if the delivered quantity is 60, the freight vendor must still be paid 100 EUR.
Is this possible by configuration or do we need to make any changes at code level? If yes, Please guide me on how to do that....

Create a PO without tick GR-Bsd IV, suppose I have created PO with qty 20 and rate 1 INR and give freight 50 INR (Fixed Amount)..
Then I have done partial GR for qty 5. My freight amount booked as 12.5 INR (for partial GR)
Then I have gone for MIRO..
Here select Goos/Service item + Planned delivery cost.
Enter the PO, you can see two line items appear..
One for goods and one for freight...
Goods will come as qty 5 and amount 5 INR and Freight will come as qty 5 and amount 12.5 INR.
Just change the freight qty and amount as 20 and 50 INR.
Then post the MIRO, you can see your total freight will be booked to vendor..
Now again do GR for qty 2, at that time your freight amount will booked as 5 INR.
Then when you will go for MIRO, you can see only the GR item, Freight qty and amount will not come at the time MIRO..
(Note : I have told the scenario as per my previous screen shot)

Similar Messages

  • Total actual cost for a given PM Order

    hello all,
    how do i get total actual cost for a given PM order (in IW33 under cost tab we have total actual cost)..
    is stored in table or do i need to use any function module.....
    thanks in advance....

    Hi Vinay,
    You can use the following logic for extracting the Actual cost of a PM order.
    Pass the Order No (AUFNR) in Table AUFK and fetch the Object number (OBJNR).
    Pass OBJNR value in table COEP.
    You can get the actual cost of the order in COEP table.
    Please mark this as correct if it resolves your issue.
    Regards,
    Joydeep

  • About add cost for an item master

    Hi,
    I checked the DI about item master, I didn't find any way to add cost for a specific item or when I try to add a item master. Does anyone do this before?
    Thanks,
    Lan

    Hi Lan,
    You can add item price list only by that object. Item cost is controlled by system depending on your inventory valuation method.
    In another word, there is no option to add cost for an item master directly.
    Thanks,
    Gordon

  • What is the formula for calculating average cost for an item in inventory

    Hi,
    Can someone please share the formula to calculate average cost for an item in inventory which uses Average Costing?
    Thank you,
    Naren.

    HI
    When a transaction updates the average cost of an item, the new average cost is calculated as follows: 

  • Actual item cost for batched items

    Hi everyone,
    I'm not entirely sure if there is an easy solution to this, however we have a client where their stock consumption method does not match their stock costing method therefore they can never really get a true stock valuation from SAP. 
    They currently have their items set to FIFO however they don't always use the oldest stock as its not always feasible to do so.
    Due to this, they cannot really find out the age of the items in stock as SAP assumes they use the oldest stock first.  To get around this I've suggested using either serial numbers for big items and batch numbers for the smaller items which will allow them to track when it came in to stock and whether it has gone out or not.  This works well and allows the users to find out the age of the stock.  However, the cost calculated in the journals and posted to cost of sales is picking up the cost from the oldest open layer in the FIFO (OINM) table and not the cost from the layer from the associated batch. 
    Is there any way we can get the system to pick up the actual cost of the item being dispatched?
    If not, we may just have to create a report which looks at all open batches, get the incoming cost and get a stock valuation that way. 
    Has anybody faced similar issues?
    Regards,
    Adrian

    Hi Marcella,
    Many thanks for your reply.
    I have looked in to both Standard and Moving Average and ran through various scenarios but unfortunately neither is exactly what the client wants and neither allows them to get a true stock valuation by item.  The client would ideally like the actual cost to be posted, but I'm afraid its either the oldest layer, average cost or a standard cost posted.
    Some items could possibly be standard as the cost doesn't alter too much, however some item costs vary rapidly dependent upon things such as exchange rates and other market influences.
    I think this may have to be done via reports.
    Regards,
    Adrian

  • "Cost Rollup - No Report" not updating costs for some items.

    Hi ,
    We have an issue with "Cost Rollup - No Report" program. When it is run for all items in an Organization, some item costs were not getting updated.
    "Include in Cost Rollup" flag in Master Item form and in Item Costs form is enabled for these items. When we run the report for specific item , it is working fine, cost
    is getting updated. Only when we run the report for all items of an org, we are having this issue. Any suggestion or help in this regard is highly appreciated.
    Thanks in advance,
    Pavan.

    Hi,
    I mean B(Sub Assembly)
    Item Rollup Flag
    A No
    --B                       Yes
    ---B1 No
    ---B2 No
    ---B3 No
    --C                      Yes
    In this case when we run cost rollup by giving item A, Oracle will consider below structure.
    A
    --C
    Regards,
    Sarvottam.

  • Calculation of cost for subcontracting item of type N (non stock) as it calculating for type L(Stock)

    Hi Gurus,
    I have a Requirement for calculating the cost for Subcontracting  Non stock items N as it is getting calculated in standard functionality for subcontracting items of Type L.
    This will be done in CK11n ( used to calculate the standard cost estimate of the product) for header as well as component materials.
    please suggest the user exit or Badi where i can change.
    Please refer the below logic-
    BOM for the material 2000500 as Header and 1LPL0835298AB as a component and this component has an assembly with 7008508 as a component and this component is an Sub contracted item and this has an assembly with component 1LBA182151-3.
    Price calculation for the material 7008508 (Item Category as N). Since this is sub contracted item the price will picked from field EINE-NETPR.
    In EINA, pass the material (MATNR=7008508) to fetch the list of info records (INFNR) created for that material.
    Then it has to input those info records to EINE table along with Purchasing organization (EINE-EKORG=PT02).
    From the output of EINE table, it should compare the price (EINE-NETPR) of the PIR and should take the least price from those PIR`s.
    If the currency is other than PLN, then it should be converted to PLN based on conversion charges.
    For Material (MATNR=1LBA182151-3), it should pass the material number to table MBEW along with valuation area (BWKEY = WERKS).
    From the output, it should check the Price control (VPRSV) ‘V’ or ‘S’
    If ‘V’ the price will be picked from the field “VERPR”
    If ‘S’ the price will be picked from the field “STPRS”
    Also from the output, it should check the Price unit (PEINH) ‘1’ or other than ‘1’. If it is other than ‘1’ it should divide the VERPR or STPRS by PEINH. Then this is the price of the Material “1LBA182151-3”.
    The material (MATNR=1LBA182151-3) should be passed to table “MARA” and will take the Base unit of measure from that table “MEINS”.
    Br,
    Surya

    Hi Surya,
    Please put breakpoints in any of the below BADI's and check if any of them will trigger for your
    requirement:
    VALUATION_CK                            BAdI for Valuation in Product Costing
    CK_KALAMATCON2_CI                       BAdI for CI Fields for Table KALAMATCON2
    COSTINGRUN_CK                           Edit Costing Run
    COST_APPORTION_CK                       Maint Apportionment Structure Joint Production: Dist Rules
    CO_PROD_COSTING_CK                      Cost Management for Joint Products (Costing, Target Costs)
    DATA_EXTENSION_CK                       For Data Enrichment in Product Costing
    DYNPRO_EXTENSION_CK                     BAdI for Interface Enhancement in Costing
    ORDER_COSTING_CK                        Enables Header Data Changes in Preliminary Order Costing
    QUANTITY_STRUCT_CK                      Enables Quantity/Structure Changes in Costing
    SUR_STOCK_TRANSF_CK                     Overhead on Materials with Stock Transfer Between Plants
    Thanks
    Sri

  • Getting Total Order Cost for each order

    I have a fact table, order lines.
    There are two dimension tables, customer & Product.
    For each order i want to display on a pivot table:
    - the cost of the line.
    -the cost of the total order. 
    Is this possible? I have been playing with ALL & All except but have not found a solution yet. some metadata is below
    CustomerID CustomerName
    1 john
    2 mary
    3 jim
    4 kevin
    ProductID ProductName Price
    1 pen 5
    2 cup 4
    3 car 7
    4 phone 3
    OrderLineID CustomerID ProductID Quantity
    1 1 2 2
    1 1 3 2
    2 2 1 4
    3 1 2 5
    3 1 2 4
    3 4 4 6
    4 4 4 6

    Hi Winston,
    Could you kindly provide an example of the output you'd expect based on the above data? Also, I've noticed that there is no OrderID column in the order line table. How would you determine which OrderLineIDs belong to a single order?
    Regards,
    Michael Amadi
    Please use the 'Mark as answer' link to mark a post that answers your question. If you find a reply helpful, please remember to vote it as helpful :)
    Website: http://www.nimblelearn.com
    Blog: http://www.nimblelearn.com/blog
    Twitter: @nimblelearn

  • Updating Standard Cost for an Item in Item Master Data

    How do you change the Item Cost field under the Inventory Data tab in Item Master Data if Standard Cost is selected as Valuation Method.  This field is greyed out.

    Hi ,
    If you have an inventory in the warehouse , you cannot change the item price of the standard cost .
    So it is greyed out .Once you donot have inventory ,this field becomes active and you can enter the price .
    Second option is from Item Revaluation .
    Please test it in test environment
    Thank you
    Bishal

  • What is the total checkout cost for the iphone 5 16gb?

    I live in CA. i really need to know so I can put the right amount in my card.
    Plz help
    Cuz I am willing to purchase it right now.
    Thanks.

    Well, the answer has a few variables.
    Are you getting a "new contract" price with your carrier?  Does your carrier have an activation fee? Do your state, county, or community have sales taxes they charge?
    I can tell you that when I purchased my 64GB iPhone 5 near Indianapolis, IN, I paid $427.99 to teh AT&T store that I happened to find with one in stock that I could buy.  That was the $399.99 for the iPhone plus 7% ($28) sales taxes (state, county & local).

  • Item cost  conversion for buy item

    HI
    can you please tell me what are the validation  for Item Cost for BUy Item
    what are the fields that have to be check and validated .
    what is interface table and base table \
    What is master program
    Thanks in advances

    hai,
      U try this one
    SELECT T0.ItemCode, T0.ItemName, T0.AvgPrice, T1.WhsCode, T1.OnHand FROM OITM T0 INNER JOIN OITW T1 ON T0.ItemCode = T1.ItemCode WHERE T0.AvgPrice=0
    and T1.WhsCode = 'pinnacle' and T1.OnHand > 0
    Avgprice is numeric .so use 0.for varchar datatype only use is null.
    Regards,
    Ramya.

  • No cost on for stocked Item via return

    From time to time we stock in an Item to a Return Warehouse via a return and since there is no cost for that item it is stocked in with no associated cost.
    Are there others experience this problem?
    If so how do you do a work around?

    Check - Allow stock release without item cost is ticked in
    Administration -->System Intialization --> Company Details --> Basic Intiallization Tab,
    Simulate it in test database before doing it.
    If it is ticked, detick it
    Do Inventory Revaluation to a new price.
    Jeyakanthan

  • Excise capture in import po for free item

    Dear Friends
    I am having an issue.
    I have created an import po for free item.
    As the item is free of cost,system will hide the conditions tab item details tab.
    But we are paying the all the duties like CVD,Import Duty ,cess etc for the free item.
    The item detail tab is hidden, I cannot enter the planned delivery costs for the item
    Please advise me how can I capture Excise Invoice for the free itme in import PO
    Thnks

    The only way to do it is to assign a small notional value (like 0.01 USD) to the item, so that the conditions tab does not disappear.
    The only problem will be that the GR/IR clearing account will have an open entry, which can be cleared via MR11 with minimum accounting impact.
    Regards,
    Aroop

  • Calculation of sales tax for free item

    Dear SAP B1 Experts
    I have query regarding sales tax calculation for free item .
    For EG.  I have two item for sales (A = 1000,  B = 100)   Sales tax is VAT4%
    But when i am doing sales, i am selling B for free of cost with A for Rs 1000/- 
    here my tax calculation is (1000 *4%)  = 1040/-
    but as per the govt sales tax rule, we are liable to pay the tax for free item as well
    So I this case, In SAP B1 how we will calculate the tax 4% for free item  .
    Please help me.
    Thanks

    i have checked, its working okay, but
    in Invoice print out unit price and line total is showing for free item.  How i make the unite price 0 .
    Tax only calculation is based on the Line total and the line total is based on the unit price.
    in that case when i give the invoice to the customer.
    It should show like this
    Item A       100   * 10         1000
      "    B           0   * 1              00
                                             1000
    4% tax                               44
    Doc Total             =           1044
    thanks
    Regards

  • Sales order - show total plan costs (from production order) on sales order

    Hi all,
    I have the following question/scenario:
    We create prodction order to collect cost (hours) for a service. There exists also a material master for this service.
    The confirmed hours are posted on the production order and then setteld to the respective sales order (settlement rule SDI).
    What to I have to maintain/customize to show the total plan cost (for the service) on gthe sales order?
    If I check the sales order via VA03 --> environment --> cost report , I can see the planned sales revenue but no planned costs?
    (the actual value flows work so far, postings via settlement or billing document).
    I hope the topic is understandable. Any ideas?
    Thanks in advance.
    Edited by: Butch66 on Sep 27, 2010 7:07 PM
    Edited by: Butch66 on Sep 27, 2010 7:08 PM

    Hi
    Planned costs from prod order can not show on sale order.. Both are 2 separate entities in their own respects
    Unless you calculate sales order cost estimate on your sales order, you cant see planned costs on sale order...
    To calculate sale order cost estimate, make settings in your requirement class...
    1. Go to procurement tab of sale order
    2. See whats the requirement type
    3. Go to IMG > Controlling > Prod cost Contr > Cost Obj Contr > Prod Cost by Sales Order > Control of Requirements
    4. Here you can see mapping of req type to req class....
    5. If you want to have sales order costing and have sales order as CO object inorder to have sales order wise profitability, you should have following settings in Req class...
    >Acct Assignment Category should be E
    >Costing: Either Blank or X
    >Costing Id and Costing Method: As per your requirement
    Regards
    Ajay M