Total Man Hours worked
Hi All,
I need to find out the total man hours worked in a timeline in Plant Maintenance. Can some one please let me know as to how we can do this?
Thanks in advance for your help,
Kanthi.
Greetings Kanthi,
IW47 will give you the hours of actual work that have been Confirmed against PM orders
Or if you have a process where you don't confirm hours manually, try Planned hours for Operations in IW37N
Also http://forums.sdn.sap.com/thread.jspa?threadID=2014538&tstart=0
Similar Messages
-
How to view man hours in MS Project 2013
I have created a sample project plan in MS Project 2013 with 3 resources. Some tasks are running in parallel while others are one after another. I am using standard calendar which is 8 hours a days, 40 hour a week.
How do I know man hours of my project plan? Is there some view available looking at which I can know the man hours of my project?Hi,
assuming default settings, you should do two things:
Add column Work to your view
Display Project Summary task: tab Format, enable check box "Project Summary Task".
This will give you total of hours (Work) for your project in line 0.
Does that help?
Barbara -
Total operation hours in routing
Dear Experts,
Please suggest me what is the way to tackle the following scenario :
We are having 3 Work Centers say WC1, WC2, WC3 to carry out the different operations. Each work center requires 6 hours. It means if I use the standard sequence then total required hours will be 18 hr to produce 1000 pcs of FG X. But My client is producing 1000 pcs of FG X in 8 hours as second operation at WC2 begins when 1st operation on WC1 is being carried out on some quantity say 100 pcs. 7 same for the WC3.
How to control this situation as I am using the lead time scheduling in MRP run,this data gets coppied to planned order giving wrong finished date.
Thanks in advance.
Regards,
SagarDear,
In Routing work center is maintain for an operation and each operation has different base quantity or production rate.
Work center Operation detail Production rate
W1 Operation 1 200 Each/Hour
W2 Operation 2 100 Each/Hour
W3 Operation 3 90 Each /Hour
Now select first two operations and go to operation detail, In detail find a radio button Overlapping required and mark as required.
For first operation
Now maintain Minimum overlap time 30 Min
and send ahead quantity 100 Each.
For 2nd operation
Now maintain Minimum overlap time 30 Min
and send ahead quantity 50 Each.
I hope this will solve your issue.
Thanks
Muhammad Ashfaq -
Hi there,
I am using Microsoft Project Standard 2010.
Within some elements of my schedule I would like to weight by man-hours, within some by material and within some others again by cost.
Also I would like to manually adjust the the weighting on the highest level of my schedule manually. E.g. WBS 01 20%, WBS 02 30% and so on.
By now I have only found out about how to weight by "Work"; putting in man-hours and then using the weighted %Work Complete.
But how about the other above mentioned weightings?
Thanks in advance!hkd66,
For work type resources the Work field is essentially man-hours and it sounds like you figured that out. For material resources, the metric is defined by the material label and the standard rate per the material label (e.g. "bricks" at $1.00/brick). Weighting
by cost is something you must "back" into via the quantity. Cost type resources are of course direct cost entries. Is that what you mean by "some others"?
Now the question comes, what exactly is your intent with regard to adjusting the weight at the highest level? Are you trying to set up the initial plan to achieve a certain man-hour and cost budget, or are you trying to achieve something else?
Although it may appear that you can "weight" your schedule's man-hours by entering a value in the % Work Complete field at summary level, that is not the intent of that field, nor the best use for it. You will not be able to do a similar thing with the cost
field. Summary lines are intended for summarizing the data of the subtasks under them, not for rolling data down to subtasks.
We need to better understand what you are trying to accomplish (i.e. you end goal), before we can give you much guidance.
John -
Calculate the performance of an activity according to the hours worked
Hi for all,
I need to calculate the performance of an activity according to the hours worked by anyone. Someone could tell me how can I do this?
timetable of staff
ID HR1 HR2 HR3 HR4 DAY
1 492 720 780 1080 Monday
1 612 720 780 1200 Tuesday
1 492 720 780 1080 Wednesday
1 612 720 780 1200 Thursday
1 492 720 780 1080 Friday
2 492 720 780 1080 Monday
3 492 720 780 1080 Saturday
SQL> Select to_date(to_char(trunc(sysdate) + 492/1440,'dd/mm/yyyy HH24:MI:SS' ), 'dd/mm/yyyy HH24:MI:SS') from dual;
TO_DATE(TO_CHAR(TRUNC(SYSDATE)
20/01/2011 08:12:00
Table Holidays
ID DATE_HOLIDAY HOLIDAY
1 01/01/2011 Holiday X
1 03/15/2011 Holiday Y
1 07/04/2011 Holiday Z
2 01/01/2011 Holiday X
Input Values
Start Date : 17/01/2011
Qtd Days : 0
Qtd Hours : 11
Qtd Minutes: 0
Result
18/01/2011 13:24Regards,Okay here is my second attempt.
With schedule_of_work As
Select 1 ID, 492 HR1, 720 HR2, 780 HR3, 1080 HR4, 'Monday' Day_of_week from dual union all
Select 1 ID, 612 HR1, 720 HR2, 780 HR3, 1200 HR4, 'Tuesday' Day_of_week from dual union all
Select 1 ID, 492 HR1, 720 HR2, 780 HR3, 1080 HR4, 'Wednesday' Day_of_week from dual union all
Select 1 ID, 612 HR1, 720 HR2, 780 HR3, 1200 HR4, 'Thursday' Day_of_week from dual union all
Select 1 ID, 492 HR1, 720 HR2, 780 HR3, 1080 HR4, 'Friday' Day_of_week from dual
), parameters AS
/* Creating a single row of input values that can be used multiple times */
SELECT TO_DATE(:job_start_date,'MM/DD/YYYY HH24:MI') AS job_start_date
, TRUNC(TO_DATE(:job_start_date,'MM/DD/YYYY HH24:MI'),'IW') AS beginning_of_week
, NVL(:days,0)
+ NVL(:hours,0)/24
+ NVL(:minutes,0)/(60*24) AS job_length
FROM dual
), holidays AS
SELECT TO_DATE('01/01/2011','MM/DD/YYYY') AS dt FROM DUAL
), date_range AS
/* Trying to generate a date range that should encompass the maximum date it would take
* to complete the task. Rough estimate is number of 8 hour work days plus a padding of 10 days.
* You may want to adjust this to something more suitable for your business or set it to an artificially
* high value. Be aware of possible performance implicications the higher you set it.
SELECT TRUNC(job_start_date) + (ROWNUM - 1) AS dts
FROM parameters
CONNECT BY ROWNUM <= TRUNC(job_length*24/8) + 10
), schedule_as_dates AS
SELECT sowo.id
, sowo.day_of_week
, dara.dts
, holi.dt
, CASE
/* Only perform the effective hours when the day is not a holiday
* and it matches a date in the date range. Otherwise set effective hours to midnight
* making the running sum below zero.
WHEN sowo.day_of_week IS NOT NULL AND holi.dt IS NULL
THEN dara.dts + HR1/(60*24)
ELSE dara.dts
END AS start1
, CASE
WHEN sowo.day_of_week IS NOT NULL AND holi.dt IS NULL
THEN dara.dts + HR2/(60*24)
ELSE dara.dts
END AS end1
, CASE
WHEN sowo.day_of_week IS NOT NULL AND holi.dt IS NULL
THEN dara.dts + HR3/(60*24)
ELSE dara.dts
END AS start2
, CASE
WHEN sowo.day_of_week IS NOT NULL AND holi.dt IS NULL
THEN dara.dts + HR4/(60*24)
ELSE dara.dts
END AS end2
FROM date_range dara
LEFT JOIN schedule_of_work sowo PARTITION BY (sowo.id) ON sowo.day_of_week = TO_CHAR(dara.dts,'FMDay','NLS_DATE_LANGUAGE=English')
LEFT JOIN holidays holi ON holi.dt = dara.dts
SELECT
CASE
/* This means that we need to go into the second shift (start2-end2) to calculate the end date */
WHEN work_remaining > end1 - start1
THEN start2 + work_remaining - ( end1 - start1 )
/* This means we can complete the work in the first shift */
WHEN work_remaining < end1 - start1
THEN start1 + work_remaining
END AS finish_time
FROM
SELECT b.*
/* Determine how much work is remaining from the previous days value */
, job_length - prev_work_time AS work_remaining
/* Calculate the smallest delta value to pick the right day of the week
to calculate the end date
, ROW_NUMBER() OVER (partition by B.ID ORDER BY DELTA desc) AS RN
FROM
SELECT a.*
/* This computation is used to determine which day of the week we need to use
to determine the end date of the task
, job_length - effective_work_time AS delta
/* retrieve the previous effective_work_time. This will be used above */
, LAG(effective_work_time) OVER (PARTITION BY ID order by start1) AS prev_work_time
FROM
SELECT job_start_date
, job_length
, id
, day_of_week
, start1
, end1
, start2
, end2
/* Compute the amount of time an employee can work in any given day. Then take a running total of this */
, SUM
CASE
/* When the job_start_date is the same day as the first eligible work day we need to diskount (spam filter misspelled on purpose the
* effective work hours because the job could start in the middle of the day.
WHEN TRUNC(job_start_date) = TRUNC(start1)
THEN
CASE
WHEN job_start_date BETWEEN start1 AND end1
THEN (end1 - job_start_date) + (end2 - start2)
WHEN job_start_date BETWEEN start2 AND end2
THEN (end2 - job_start_date)
WHEN job_start_date < start1
THEN (end2 - start2) + (end1 - start1)
WHEN job_start_date > end2
THEN 0
END
ELSE (end2 - start2) + (end1 - start1)
END
) OVER (PARTITION BY ID order by start1) AS effective_work_time
FROM schedule_as_dates
CROSS JOIN parameters
) a
) b
/* Only interested in delta less than zero because the positive deltas indicate more work needs to be done. */
WHERE delta < 0
WHERE RN = 1I got slightly different results then you. My query got me 1/24/2011 at 13:12. I double checked the math and I think that's right.
Hopefully this works out for you. My apologies for any mistakes.
EDIT
Query is fully posted now. -
I have one finished good A which has a multi level bom.
I want to see the total labour hours required to manufacture this material A.
i.e. total of all the labour hours of all the subassemblies
under A.
In which transaction can I see it.
I have tried CK13N but am not able to find the total hours required to manufacture A.Hi Amit,
You can do this via routing itself,
goto CA02
there you enter header detail screen
goto
extras
scheduling
there you can put the quantity as required
There there you will see the results of scheduling the labor Hrs
But for that you need maintain your work center scheduling category as labour.
Regards,
R.Brahmankar -
Operation wise total required hours for planned order in given date range
Hello Experts,
My client wants the report to check the capacity utilization of the work centers for the all planned order in particular date range.
Is their any standard report which gives the work center wise operation wise total required hours? or which table should I use to make the customize report so that I will get total required capacity & available capacity.
Thanks in advance for use valuable suggestions.
SagarHi Mario,
Thanks for your reply,
In CM01 or CM05, we are getting requirement on weekly basis.How to get that report on daily basis? I want to give the input as a date range of the planned order.How to go for that?
Edited by: SAGAR GOLIWAR 226 on Jul 3, 2011 8:16 AM -
T-codes to get total runnig hours for machine and lab
Plz tell any one t-codes to get total runnig hours for machine and labour against the prodduction order or work center wise ..
Thanks & Regards
Punit SInghHi pjd,
I'm sorry to hear of your problem getting help with your issue. Have you checked this thread to see if there's any useful information in it that would help you get this resolved??
If the information there does not help, please advise and I'll try to get you to the proper department to get this resolved for you.
Regards,
KaLin
Verizon Forum Moderator
If a forum member gives an answer you like, give them the Kudos they deserve. If a member gives you the answer to your question, mark the answer that solved your issue as the accepted solution. -
Total Planned and Total Actual Hours for service order
Hi,
Is there is any table in which I can directly find the Total Planned and Total Actual Hours for service order.Pl suggest.
Regards
SBSorry SB, didn't read your post properly... I thought it was costs you were after...
AFVV holds the total actual work at operation level.
PeteA -
Hi All,
Could you please let me know the best practice to calculate man hour cost in mainteance order.
Finance team define the activity price rate using t-code KP26 based on what ? If it is based
on employee salary posted to a cost center,then at the time of settlement of maintenance order's
man hour cost ,again we are posting the cost to the equipment cost center .May be that equipment
belongs to same cost center where salary was posted ,so we are posting two times same cost .
Can anybody please clarify my doubt ? Thanks in advance .
rgds
PranjalHello
Man hour cost nothing do with salary paid to resource.Its business understanding as per their experience what are the rates resource belonging such as if some one hire from outside firm rate will be more so business decides the rates in accordance with rates which is charged for outside resource.So internal resource may have less rates compare to outside resource.also how much work complex and trunky work involve for activity type will also play imp role while deciding the rates.so summarily its just way how the FICO or Maintenance Manager would like to have rates per resource based on activity type.
Br
Rakesh -
FORMULA=USING/TOTAL IS NOT WORKING IN BPC NW.
Hi,
I am doing Migration project from BPC MS to BPC NW 7.5. In this I am not able test the Allocation formula.
FORMULA=USING/TOTAL.
Here in this Total is not working. The final result same as USING combinational value. The formula is working for USING combination like FORMULA=USING/100,USING*100....,
WHERE=WHAT* USING/TOTAL.Let me know is there any solution for this.Could you please update me on this.
Find the below sample code for the Allocation Logic.
LOGIC:
*RUNALLOCATION
*DIM P_ACCT WHAT=CE0004010; WHERE=CE0004020; USING=CE0004030; TOTAL=CE0004210
*DIM CATEGORY WHAT=PLAN; WHERE=PLAN; USING=PLAN; TOTAL=PLAN
*DIM P_CC WHAT=India; WHERE=India; USING=India; TOTAL=India
*DIM P_DATASRC WHAT=UPLOAD; WHERE=UPLOAD; USING=UPLOAD; TOTAL=UPLOAD
*DIM P_ACTIVITY WHAT=Repair; WHERE=Repair; USING=Repair; TOTAL=Repair
*DIM RPTCURRENCY WHAT=LC; WHERE=LC; USING=V; TOTAL=LC
*DIM TIME WHAT=2009.JAN; WHERE=2009.APR; USING=2009.MAR; TOTAL=2009.MAY
After exccuting this formula and by observing the Formula Log one record write back message displayed.
Thanks and Regards,
VC kRISHNA.Hi,
Please find the below Allocation logic. Here in this case also getting the same out put. The whare combinational value same as using. This Allocation Logic and the previous one is working with out fail in the MS version. Let me know is this may be a product issue. Could you please update me in this.
Logic:
*RUNALLOCATION
*FACTOR=USING/TOTAL
*DIM PROJECT WHAT=BAS(CorpBudg_Project); WHERE=[SCTSQ1]="Y"; USING=<<<; TOTAL=No_PPC
*DIM ENTITY WHAT=PC10102106; WHERE=NO_PCENTER; Using=<<<; TOTAL=NO_PCENTER
*DIM ACCOUNT WHAT=BAS(Corp_Budg_Accnts); WHERE=880014; USING=<<<; TOTAL=<<<
*DIM DATASRC WHAT=INPUT; WHERE=<<<;USING=<<<; TOTAL=<<<
*DIM RPTCURRENCY WHAT=LC; WHERE=<<<; USING=<<<; TOTAL=<<<
*DIM CLIENT_GROUP WHAT=1010; WHERE=<<<; USING=<<<; TOTAL=<<<
*DIM CATEGORY WHAT=BUDGET; WHERE=<<<; USING=<<<; TOTAL=<<<
*DIM INTCO WHAT=Non_InterCo; WHERE=<<<; USING=<<<; TOTAL=Alloc_PC10102106
*DIM TIME WHAT=BAS(2011.TOTAL); WHERE=<<<; USING=2011.BSS; TOTAL=<<<
*ENDALLOCATION
*COMMIT
Thanks and Regards,
Krishna. -
Need to get the overtime hours worked for Report
Dear Experts,
We have configured Overtime for client and it is working fine.
But for custom report development we need to get the overtime hours worked.
We have searched in B2 cluster and not able to identify exact overtime table.
Request your suggestionsu2026u2026..Hi,
after time elavualtion use t code PT66, in this t.code double click on the each month(period) then you can get the internal table like ZES, SALDO, ZKO. again double click on the each internal table, you can get the information through the time types. Like , now you want the overtime hours, 0903, 0904 with this time types you can get the each employee no. of. overtime hours.
ZL, ZES, SALDO, TIP entries are internal table , you could not get any results from this table with using se11, se16.
With PT_BAL00 with this report also we can get the overtime hours with the help of time events.
Good luck
Devi -
Man-Hours Estimation template for BW objects
Hi,
I tried to search for specific templates relating to Man-Hours Estimation for the development of BW objects like Extractor programs,datasources, infosources , Info Providers , Queries , Web reports etc. But I was not that successful.
It would be great if anybody helps me in finding/making such template or the root/means(Links or documents) of creating the template.
I'm sure everyone uses it in the projects.But looking for an optimized,easy-to-use, close-to-reality estimation template.
Thanks in Advance
- PriyuHallo Priyu,
for our tasks concerning our BW-SEM system we use an Excel list with the following columns: Area (e.g. data basis, operation,...), No. (serial number), Category (e.g. to-do, point at issue), Error(E)/Revision(R), Date of Admission, Description (e.g. technical name of BW object), Priority, Responsibility, Contact Person, Expense (man hours), Status (e.g. open, in process, done), Next Activity from, Date of Completion, Remarks.
If you like to use this template, I could post it to your email adress.
Regards,
Martin Lehmann -
SAP Transction to see the Man Hours/ Order
Hi Experts,
In process Order we had a standard Value Man Hours. Is there any Standard Transaction through which i can see the man hours per Order.
Or
Any body having any ides about the BADI. So through BADI I can fetch the field of man hours and see the output in COID.
Regards,
AmitHi
Chk the Std report - COHVPI with Operations in the list and Profile as Standard Profile. In the change lay out select the fields relevant for the activities (Confirmed activ. 1 (ILE01))
Regards
Brahmaji -
HR tables that store hours worked on holidays
Hi All,
I am trying to calculate the number of hours an employee worked on holidays in a payroll period.
Can anyone give me the name of tables in HR that store the number of hours worked on hoildays?
Thanks in Advance..
Sonali.Check with below Tables :
View : V_T559P
Tables : T511K
T510s
Thanks
Seshu
Maybe you are looking for
-
Attachments on playbook emails won't open
Attachments on my emails on my playbook won't open in either "docs to go" or anywhere else I get the message (file corrupted)
-
Run time error while creating sales order in VA01
Dear all, In our develpment server(ecc 6.0),while creating sales order in VA01 for a sales area, when ever entering material number and quantity and press enter, it is giving error and taking to Runtime error long text showing syntax error in program
-
Updating printer driver for laserjet 2100tn
I have recently updated my Mac Mini (PawerPC) to an iMac with Lion. HP says that the printer driver update is through Apple, and nothing I do seems to call the Print/Scan dialog to notice it. Thoughts? David
-
I have created app using Jdeveloper 10.1.3 and ADF BC and deployed to the oracle application server 10.1.3. The app is being used since September last year. Now some of the users encounter "500 Internal Server Error" when they are tring to login to t
-
Web module generator security conflicts with DAD
Hi, using the WSGSEC package for web module security, I'm running into issues related to the mod_plsql configuration. There are 3 values for setting session state behaviour (PlsqlSessionStateManagement) following to the dads.README: 1. StatelessWithR