Total labour hours for a FG
I have one finished good A which has a multi level bom.
I want to see the total labour hours required to manufacture this material A.
i.e. total of all the labour hours of all the subassemblies
under A.
In which transaction can I see it.
I have tried CK13N but am not able to find the total hours required to manufacture A.
Hi Amit,
You can do this via routing itself,
goto CA02
there you enter header detail screen
goto
extras
scheduling
there you can put the quantity as required
There there you will see the results of scheduling the labor Hrs
But for that you need maintain your work center scheduling category as labour.
Regards,
R.Brahmankar
Similar Messages
-
T-codes to get total runnig hours for machine and lab
Plz tell any one t-codes to get total runnig hours for machine and labour against the prodduction order or work center wise ..
Thanks & Regards
Punit SInghHi pjd,
I'm sorry to hear of your problem getting help with your issue. Have you checked this thread to see if there's any useful information in it that would help you get this resolved??
If the information there does not help, please advise and I'll try to get you to the proper department to get this resolved for you.
Regards,
KaLin
Verizon Forum Moderator
If a forum member gives an answer you like, give them the Kudos they deserve. If a member gives you the answer to your question, mark the answer that solved your issue as the accepted solution. -
Total Planned and Total Actual Hours for service order
Hi,
Is there is any table in which I can directly find the Total Planned and Total Actual Hours for service order.Pl suggest.
Regards
SBSorry SB, didn't read your post properly... I thought it was costs you were after...
AFVV holds the total actual work at operation level.
PeteA -
Operation wise total required hours for planned order in given date range
Hello Experts,
My client wants the report to check the capacity utilization of the work centers for the all planned order in particular date range.
Is their any standard report which gives the work center wise operation wise total required hours? or which table should I use to make the customize report so that I will get total required capacity & available capacity.
Thanks in advance for use valuable suggestions.
SagarHi Mario,
Thanks for your reply,
In CM01 or CM05, we are getting requirement on weekly basis.How to get that report on daily basis? I want to give the input as a date range of the planned order.How to go for that?
Edited by: SAGAR GOLIWAR 226 on Jul 3, 2011 8:16 AM -
Hi,
I am using Project Server 2010. I have a project schedule that has been baselined and no actual work has been charged to it. The project has 3 resources. I am in the Resource Usage View. With 2 of the three resources, the hours in the Baseline Work Column
on the left side of the view do not equal the sum total of weekly hours in the Timephased Grid. For instance, for resource JB the Baseline Work hours column says 1,392. When I total his weekly hours in the timephased grid I get 1368 hours; a variance
of 24. Resource RS has 794.5 hours in the Baseline Work column but the sum total of his weekly timephased grid hours is 710.5, a variance of 84 hours. In both cases, the sum of the hours in the timephased grid is less than the hours in the Baseline Work column.
What would be causing this? (I am cutting and pasting the weekly hours in the timephased grid into Excel and using the Excel sum function total). Is there a better timephased view I should be looking at to try to find the "missing
hours"? I have seen this before in project and it really has me stumped. Thanks.
Judy WashingtonHi Judy,
I could not reproduce your issue. Is your Project Server patched with the latest SP and CU?
Also can you reproduce this unexpected behavior with another project?
Can you split your screen from the resource usage view, display the resource form and click right on the grey part selecting "schedule"? Then you'll have the scheduled start and finish dates for the resource's assignments. This is to be sure that
you are not missing any parts of the assignments due to a wrong zoom in the timephased grid.
Hope this helps,
Guillaume Rouyre, MBA, MCP, MCTS | -
Need total worked hours of each employee
Hi all
I need the total work hour for each employee
create table pde(empno number(10),act_hour varchar(10 byte));
Table created
insert into pde values(211,'12:20');
insert into pde values(211,'06:00');
insert into pde values(213,'07:00');
insert into pde values(213,'07:20');
WITH got_total_hours AS
SELECT SUM ( TO_NUMBER (SUBSTR (act_hour, 1, 2))
+ ( TO_NUMBER (SUBSTR (act_hour, 4, 2))
/ 60
) AS total_hours
from pde
SELECT TO_CHAR (FLOOR (total_hours))
|| ':'
|| TO_CHAR ( MOD (total_hours, 1) * 60
, 'fm00'
) AS hh_mm,empno,act_hour
FROM got_total_hours ,pde
this is the output i am getting
HH_MM EMPNO ACT_HOUR
32:40 211 12:20
32:40 211 06:00
32:40 213 07:00
32:40 213 07:20
i require HH:MM EMPNO ACT_HOUR
18:20 211 12:20
18:20 211 06:00
14:20 213 07:00
14:20 213 07:20
kindly help meThanking in advance
regards,
oracleuserHi Ravi,
Your solution works perfectly fine but there is a prob when i incorporate ur solution in the main query
WITH temp AS
(SELECT employee_number,
act_hour ,
SUM(to_number(regexp_substr(act_hour,'[^:]+',1,1))*60+to_number(regexp_substr(act_hour,'[^:]+',1,2))) over (partition BY employee_number) tot
FROM nap_PUNCH_DATA_EMP_LIST trn where DATE_ENTRAY between '23-Aug-2009' and '24-Aug-2009'
SELECT employee_number,act_hour,ROUND(tot/60)||':'||mod(tot,60) tothours FROM temp
o/p i am getting is
EMPLOYEE_NUMBER ACT_HOUR TOTHOURS
408 06:31 07:31
408 00:00 07:31
410 18:12 30:59 ------SUM of 18:12 and 11:47 should be 29:59
410 11:47 30:59
this is working correctly for majority of employee_numbers with exception of some employee_numberskindly help
regards,
oracle user
Edited by: makdutakdu on Jan 4, 2010 12:45 PM -
Hello,
I have removed the routing from my PO and also from the routing tree for that materials,even after removing some of the Partial Stage labour hours are Picking??,How it is Picking the labour hours for the removed routing,but i have found few materials issued in that stages..whether the Labour hours liked with the materials??Pls clear...
Whether Labour hours are assigned to the materials or for the Process,if it is for the Process then how the LAbour hour is comming while doing cost analysis as the full material is not consumed in that Particular stages.
regards
NandhuHello Abbas,
I did not completely understand your question but confirming on the labor item for BOM. It should be defined in the Item Master of type Labor. In the Inventory data tab set the valuation method to Standard and define a cost for the labor. A labor item in the BOM definition should be defined with issue method Backflush.
Suda -
Planned and Actual Labour hour
Hi,
Pl. let me know the table and field name for the following.
1) Planned and delivered date for the production order.
2) Planned and Actual labour hours for the production order.
3) Work centre for the production order operation reference.
MadhavaHi,
Find the below related tables
AUFK Production order headers
AFIH Maintenance order header
AUFM Goods movement for prod. order
AFKO Order header data PP orders
AFPO Order item
RESB Order componenten
AFVC Order operations
AFVV Quantities/dates/values in the operation
AFVU User fields of the operation
AFFL Work order sequence
AFFH PRT assignment data for the work order(routing)
JSTO Status profile
JEST Object status
AFRU Order completion confirmations
Regards
SANIL -
How to find out exact labour hour and expenses for each labour attached to
Team,
How to find out exact labour hour and expenses for each labour attached to machine
We are planning to go with CATS.
But in Cats how Production Planning department get the exact labour coust
(which includes labour accomodation building , EB etc. paying by comp)
How to do this in CATS
REXhai
generally the schemas are named X000 which stands for common schema nomination
x replaced by respective country like for india it is IN00 for US U000etc
it is not given according to the group of emplyees but according to the country grouping for your org units
time schemas are country independent they work for all the countries
regards
nalla -
Total operation hours in routing
Dear Experts,
Please suggest me what is the way to tackle the following scenario :
We are having 3 Work Centers say WC1, WC2, WC3 to carry out the different operations. Each work center requires 6 hours. It means if I use the standard sequence then total required hours will be 18 hr to produce 1000 pcs of FG X. But My client is producing 1000 pcs of FG X in 8 hours as second operation at WC2 begins when 1st operation on WC1 is being carried out on some quantity say 100 pcs. 7 same for the WC3.
How to control this situation as I am using the lead time scheduling in MRP run,this data gets coppied to planned order giving wrong finished date.
Thanks in advance.
Regards,
SagarDear,
In Routing work center is maintain for an operation and each operation has different base quantity or production rate.
Work center Operation detail Production rate
W1 Operation 1 200 Each/Hour
W2 Operation 2 100 Each/Hour
W3 Operation 3 90 Each /Hour
Now select first two operations and go to operation detail, In detail find a radio button Overlapping required and mark as required.
For first operation
Now maintain Minimum overlap time 30 Min
and send ahead quantity 100 Each.
For 2nd operation
Now maintain Minimum overlap time 30 Min
and send ahead quantity 50 Each.
I hope this will solve your issue.
Thanks
Muhammad Ashfaq -
How to update routing labour hours by material origin group?
Hi,
I have a requirement to update the routing labour hours by material origin groups to save time of updating each and every material. Is there a way to do this?
For example if 3 materials belong to origin group A then if all 3 materials use labour hours of 5 hours, then the user has to enter only the origin group and 5 hours once to update all 3 material routings. Is this possible?Dear Raja,
Can you let us what do you mean by origin Group ??
if you mean updating the results in Material master
then check T-code CA97
Regards
Madhu -
Adding a Column of Labour Hours in MCIS -S818 Report
Hello Friends,
I have a requirements to add a coloumn of Labour Hours in MCIS-S818 report. Can you let me know how can I go about this?
Thanks in advance.Hi Pratap,
Yes I want to add one more coloumn in existing MCIS report which will display me the labour hours consumed for that particular order along with the other details.
What I want is to add a key figure of Labour Hours. Is this possible? If yes then how can I configure this, please help.
Edited by: Nilesh Panchal on Jun 28, 2010 7:25 AM -
Whare dose the total lop hours will be stored?
Can any tell me in which place will the total lop hours will be stored for a employee.
kindly tell me asapcheck XT00 schema in that check TC00
DZL table DL table
yes wht ever the method it will get sotred there only
Edited by: Sikindar on Oct 16, 2008 11:44 AM -
Hi All,
I need to find out the total man hours worked in a timeline in Plant Maintenance. Can some one please let me know as to how we can do this?
Thanks in advance for your help,
Kanthi.Greetings Kanthi,
IW47 will give you the hours of actual work that have been Confirmed against PM orders
Or if you have a process where you don't confirm hours manually, try Planned hours for Operations in IW37N
Also http://forums.sdn.sap.com/thread.jspa?threadID=2014538&tstart=0 -
Ignore working hours for a specific route
Dear SAP Gurus,
I'm on to maintain a route for 0 days and 0 hours. Therefore I customized a new route, and set the Delivery and Transportation Scheduling of my shipping point to "route dependent". So far, this works fine, but although I entered a total time of zero in my own - created route, the system calculates the next day as delivery date because of the customized standard working hours of our company.
Therefore I'm searching for a way to ignore those working hours in the calculation for this specific route (it's fine to use these working hours for the calculation of every other route). I'd like the delivery date and time being the same as the goods issue date and time, loading time, etc..
How to handle this one?
Thanks a lot for any suggestions / ideas.
MatthiasHi Matthias
1)Don't maintain any factory calender , pick / pack time , material availability time etc in shipping point
2)Even don't maintain the Factory calendar in the sales orgn details
3)Don't maintain Factory calendar the shipping point data
4)Finally as you have maintained route remove the factory calendar in the your route determination .
Then your requirement can be fulfilled
Regards
Srinath
Maybe you are looking for
-
How Safe Is It To Jump From OSX 10.5.2 To 10.5.8 In One Go?
I am still using 10.5.2 because until yesterday my broadband connection was so slow and incredibly unreliable that I dare not try to download the huge OS updates. I have changed ISPs and am now on a very fast connection so downloading is no problem.
-
Understanding and resolving errors in HFR
Hello Guys, Can anyone please tell me how to understand the error thrown while running the HFR reports in workspace like the one shown below: 5200: Error executing query: ;hasPovDims=1;povXML=<?xml version="1.0"?><datasources><datasource name="FinRpt
-
Looks fine in FF and Safari, disaster in IE8
http://www.jdcdemo.com/d4/index.html This site displays as I set it up in FF and Safari for Windows. In IE8, it is a disaster. The menu spacing is doubled and the main image is way down in the page. I'm guessing it is a CSS and/or Doctype problem, bu
-
Association rule in SQL Server Data Mining
I have been working on a problem on association rules in SQL Server Data Tools (Visual Studio 2008) for quite a while but have not yet been able to figure out the solution. The problem is: I have a table named Sales_history in my SQL database. This t
-
Windows 7 not genuine problem, to upgrade windows 10?
windows 7 not genuine problem, to upgrade windows 10? or can i install it over windows 7 that is not genuine?