Variant Configuration: Update of Production Order Configuration

We have a requirement, where sales order configuration is changed, this configuration change should get updated
in the production order {updated configuration change is inturn used for printing of shop floor papers}.
Currently, Based on sales order configuration change, configuration change is not updated in the production order,
leaving us no choice but back out the production orders and redo it again {something we would like to avoid}.
In the production order, under  header, there is CHANGE CONFIGURATION menu, which is greyed out, can this be activated?

please investigate the use of OCM (order change management).  It seems to provide solution to your requirement.
[http://help.sap.com/saphelp_erp60_sp/helpdata/en/a5/63198843a211d189410000e829fbbd/frameset.htm]
Please note that there is a few steps in configuration to be made before it is working.  Namely, Overall change profile (OPL9), and Change profile (OPL7).
Rgrds,

Similar Messages

  • Activity price not getting updated at Production order

    Hi All,
    I have made activity dependent planning at cost centre and calculated the activity rate. The activity rate is showing correctly for the cost centre in KP26, but while confirming the production order (CO11N) the the activity price is not getting updated in production order. But material price is getting properly updated at production order.
    Plz help me in identifying the possible areas of mistakes.
    Regards,
    BKD

    Hi,
    Please check the Period for which you have created the ht activity price is same as the period in the conformation. In the workcenter in which you are confirming please check whether the activities are assigned to the work center.
    Bye,
    Ramesh

  • Measuring point update by production order confirmation

    Hi friends,
    I created a prt as equipment and assigned it to the routing. I created a production order and when i confirm the same i am getting following error as:
    Document MeasUnit has a different dimension to the characteristic unit
    Message no. IR071
    Diagnosis
    The measurement unit on creation of the measurement document must have the same dimension as the measurement unit of the characteristic of the measuring point.
    In this case, the measurement unit % does not suit the character unit EA of the measuring point 103.
    System Response
    Processing will not be continued.
    Procedure
    Use the possible entries help.
    Please suggest the solution.

    Hello Sir(s)
    i have gone through entire post for the subject related to measuring point auto update from production order confirmation.  I have tried the same but i dont know what i am missing.
    if i put some value like 1 or 2 and appropriate UOM then only my measuring document is being updated with the same value not with the actual confirmed quantity..  i have already maintained standard formulla in prt view.
    my basic requirement is to get actual value of produced quanity as counter update. means if 20 pieces have been produced and confirmed in co11n, then counter must bhe updated with the value of confirmed quantity.
    please advice what value should i put as usage in routing master to get actuall counter update.
    Will Highly appreciate your quick reply.
    Snapshots
    Regards.
    Mohammad.

  • ABAP Update to Production Order Sequence

    Good afternoon PP Gurus,
    We are creating an inquiry that shows all production orders for a given work center.  What we want the inquiry to do is then allow the user to change the sequence AFKO-CY_SEQNR and then save the new value back to the order header AFKO.
    Example Inquiry.
    Work Center: 123
    OrderNumber  Part   Description  Sequence
    100001           123   Part123             _
    100002           456   Part456             _
    100003           789   Part789             _
    100004           000   Part000             _
    So we need an ABAP object that would take production order as the key and allow a change to sequence number CY_SEQNR.
    We're running an older R/3 version 4.7.
    Thanks in advance for any information that you might share.
    Chad

    Don't sweat this one gang.
    Our current version of R/3 does not contain any native ABAP that allows for us to update the production order.  We came up with our own FM created off a recording of CO02.
    Thanks,
    Chad

  • Actual activity price not updating in production order

    Hi All,
    I am facing one problem, that actual price for activities are not updating in production order while plan price are updated. Earlier both plan and activity prices were getting upadated but now actual price is not updating for any material. I have tried at the same material also but it is not getting updated. Actual hours are updated in confirmation of production order but not price. If somebody could suggest the reason it will be great.

    Dear Nitin,
    Thanx to all for valuable input. Problem is solved.
    Nice to see That your problem is solved
    But Can you let the Forum Members know
    where was the exact problem & how it is solved
    Regards
    Madhu Kumar

  • MRP-Delivery Schedule for Sales order is not updating in Production order

    Dear Experts,
    I have created Sales order and maintained delivery scheduling, Then Run MRP through MD50,
    We received Planned order then through this we have converted to Prodcution order.
    When we observe the delivery schedule for sales order under assignment Tab in Produciton order which is showing zero instead showing line item of Delivery schedule.
    I am able to see Sales order and Line item but i am not abel to get any delivery schedule line item.
    Please suggest where settings are missing.
    Thanks in advance
    Regards
    Don

    Dear Experts,
    Please provide me solution.
    after Running MD50 transaction against Sales order.
    If I maintained different Scheduling Line Item for First Line item of Sales order.
    The Respective Scheduling Lines should update against Each Production order which has converted from Planned order.
    Thanks in advance.
    Regards
    DON

  • Revaluation of Activity type is not getting updated in Production Order

    Hi,
    I have run KSII , for actual activity price calculation. After this , the revalution of production orders was done.
    But I am not finding any entry in Production order with a value of variance between Actual Price and Plan Price of the Activity type.
    It sould come in the production order.
    What can be the reason?
    In OKEQ, for the Version '0' and the fiscal year, Revaluation has the entry ' 1.Own Business Transaction'. I hope this is correct.
    But still the revalaution line item is not showing in Production Order.
    Please help.
    regards
    Kamlesh

    Hi Paolo,
    Yes, MFN1 ran perfectly and I am also able to see the details in the screen.
    My concern is, this revaluation should also have affect on Production order, thats what not happening.
    Or let me know where can I see the affect of revaluation on Production orders.
    regards
    Kami

  • BOM updation in production order

    Dear All
    I have created production order against one specific BOm
    Then i changed the BOM line items & again i have created one more production order but new BOm items are not updaetd in the new production order
    pl help
    regards
    Kiran

    Kiran,
    I would suggest you to check the Valid from Date of specific component you are taking about, probably you would have added with effectivity date 10.01.2008. Now when order is exploded it is looking for valid components as on 03.01.2008, this may be the problem.
    A simple suggestion here is that you execute Read PP Master data for this order in the change mode(CO02), from the menu bar Functions--->Read PP Master Data. You would get a Pop-up screen Read PP Master data.. here in the screen "Cont." button. One more screen pops up, here in the BOM explosion date you give it as 10.01.2008. Hope you will get the new component also in your production order now.
    Regards,
    Prasobh

  • Actual Cost is not updating in Production Order & WIP

    Dear All,
    I have issue in production order and Work in Process not getting Target Actual cost in costing view CO03 & KKAY.
    Is there any settings or transaction missed out? Please guide me how to sovle the issue.
    Thanks & Regards,
    Venkat.

    Dear,
    Please check,
    For Target cost
    1. Your std cost must be released before Goods Receipt
    2. There must be goods receipt posted on the prod order
    3. You must calculate variances in KKS1/2
    For Actual Cost
    1. Post Goods receipt and Goods issues
    2. See if any mat movements are pending in COGI
    3. Ensure that operation is confirmed in PP and no entry is lying in COFC
    Also in CO03GotoCost-Analysis--Here change the lay out and check it.
    Regards,
    R.Brahmankar

  • Serial Numbers update on Production Order

    Hi All,
    Is there any user Exit by which I can upload serial Numbers of Final product to production orders. There are certain production orders which have serial numbers but many of them don't. Now I need to upload serial numbers on those production orders of particular finish product?
    Regards,
    Pradeep

    If these order are created with order type having internal number ranges assignement then you can not assign number externally to these orders or else you can give numbers manually or created LSMW for them..

  • Target cost Not updated in Production order

    Dear All,
    when I save & release the production order system is not showing tgt cost. But once GR thas been done it is showing target Cost.
    How can system should will show target cost without doing GR.

    Dear Sainath,
    It is the standard behaviour of SAP,that only making a GR for a production order you will be able to see the target cost in CO03 -
    -->Goto >Cost-> Analysis.
    IF the order is only created or released you will be able to see the data under cost --->itemization or else cost component
    structure.
    Under Analysis you will not be able to see any data.you can see the data's after making GR.I dont think some option to make the
    data's visible before this.
    Correct me if I'm wrong.
    Regards
    Mangalraj.S

  • Using DTW to update existing production order

    Hi , we are using SAP B1 2005.
    Is it possible to mass changing existing production using DTW ? ( We can use DTW to upload production order)
    if can , how to proceed?
    thanks!

    Hi.....
    If you don't find the template of Production Orders in the mentioned path (C:\Program Files\SAP\Data Transfer Workbench\Templates) then you can create its template through DTW tool itself....
    For creation of template please check this link......
    http://wiki.sdn.sap.com/wiki/pages/viewpage.action?pageId=64258757
    Regards,
    Rahul

  • Why don't  we do the confirmation in variant configuration?

    Hello guys,
       As far as i know that in variant configuration we don't do the confirmation, we directly do the goods receipt.Is it right?If yes than why?
      Following are the steps we  do while doing the variant configuration scenario:
    1)First we create the characteristics and give the values inside it.
    2)Then we create the class of class type 200 and give characteristics defined in it.
    3)Then we create the variant of class type 300 and give all the characteristics inside it.
    4)Now we create the configurable material with Basic data 1,2, MRP 1,2,3,4 , Classification view ,workscheduling view.
      In classification view, we give the variant of class type 300.So it shows all the characteristics and its value over there.There we select all the values.
    5)Now we create the super bom of configurable material and in class tab we give all the classes of class type 200.Here even we can maintain the dependencies if we define all the characteristics value in item tab.
    6)Then we create the super routing and inside it we give all the possible operations inside it.Right now my routing contains operations  which are necessary all the times.
    7)Then we create the configurable profile for configurable material of class type 300.
    8)Now we give the requirement in md81 for configurable material and there we select the characteristics values which we want.
    9)After that we run the mrp for configurable material and it generates procurement proposals(planned order) for it.
    10) Afer this we convert this planned order into production order and release it and save it.
    11) After this we do the goods receipt for the production order in mb31.Because of this it shows the stock of sales order as production order qty.
                This procedure my tutor has taught me.Have i missed any steps or am i wrong somewhere?If that the case than plz guide me.

    if you can generate a production order then you can always confirm it according to SAP PP logic.
    we use variant configuration for the manufacturing of complex products. once the component quantities and
    operation are selected for a particular variant and copied to Production order, the rest of the process is same
    as normal Production Control. Revert back with any queries you have.
    Regards,

  • User-exit to update material component in a production order with a batch

    I am looking for a solution to update a production order material component with a batch number what is stored in the configuration of a sales order. The production order is defined for salesorder related production. How can I update the field RESBD-CHARG in the production order.
    Tried already the exits PPCO0001, PPCO0008, PPCO0021. Also looked for a solutions with batch search stratgegies, but I have no idea kind of possiblities I have here. Other problem is that we are stil on release 4.7.
    Hopefully some can help me with a solution.
    Regards,
    Peter Geurts

    Dear
    You have to update the batch in a production order component via RFC Call of BAPI_ALM_ORDER_MAINTAIN.You should also pass operation number to T_COMPONENT and T_COMPONENT_UP
    T_COMPONENT-ACTIVITY = Operation Number
    You need to pass the following tables
    IT_METHODS should have 2 values
    Refnum - '000002'
    Objecttype - 'COMPONENT'
    Method - 'CHANGE'
    Objectkey - 300054 (Prefix the zero's)
    Append IT_METHODS
    Method - 'SAVE'
    Append IT_METHODS
    T_COMPONENT should have the following values
    RESERV_NO - Reservation number ( you can see in production order)
    RES_ITEM - Reservation item ( you can see in production order)
    BATCH - populate the required value
    APPEND T_COMPONENT
    T_COMPONENT_UP should have the following values
    BATCH - 'X'
    APPEND T_COMPONENT_UP
    Or else look at BAPI 'BAPI_MATERIAL_GETBATCHES'. This might help you.....
    CALL FUNCTION 'BAPI_MATERIAL_GETBATCHES'
    EXPORTING
    material = MATERIAL
    BATCHNUMBER =
    plant = PLANT
    expirydatefrom = DATE
    Hope this will be useful
    Regards
    JH
    Edited by: Jiaul Haque on Sep 12, 2010 11:14 PM

  • Problem in updating Production Order

    Dear All,
          When I try to update the Production Order I am getting the error message as  "Invalid user OWOR.UserSign ".
    Help me to resolve this problem.
    Thanks,
    Lingam.
    Edited by: miplkutalingam on Feb 13, 2012 3:22 PM

    Dear Lingam,
    Welcome you post on the forum.
    Something must be wrong in the document. The user who created the PO may be deleted somehow. B1 does not allow the deleting of the user but manual deletion may be occurred in your database.
    Try: SELECT UserSign FROM OWOR T0 WHERE T0.DocNum = '[%0\]' to find out.
    Thanks,
    Gordon