Wrong Planned Order dates - MRP Run

Dear Experts,
Please guide to resolve the following problem:
I have uploaded the PIRs for 3 months. When I take the MRP run, the system is scheduling the planned orders for first 2 months only. For the 3rd month's PIR the planned order are created for the PIR dates only. 
For example, if the PIR (for 3rd month) is maintained on 25th of the month. The planned orders for FG & SFGs are being created for 25th only. While for 2 months the Planned orders are properly scheduled.
What could be the reason for such behavior.
The planning horizon is 90 days.
Regards,
Rohit.

Dear Rohit,
If you are running MRP with NETPL, then the Lead time scheduling will be carried out only for the planning harizon.
Try executing MRP you can select NETCH key.
or
If you want to run MRP with NETPL key, then please give In-house production time in workscheduling view as per the routing values. For example 1 day is the processing time and give the quantity for for 24 hr production. Then the sceduling will be carried out as per this values.
And change the planning harizon for detailed scheduling in OPU5 transaction.
Thanks and regards
Murugesan

Similar Messages

  • Production orders in place of planned orders in MRP run

    Hi,
    Please help me with this senario,
    we receive saleorders through CRM interface then these are chnged to redistribute to different plants by changing the plants in saleorders.
    we want to run and create production orders directly for these saleorders without creating planned orders.
    I tried using strategy 82 but it makes the production order online, but we want it to be created after mrp run.
    Is there a way to create production orders instead to planned orders in MRP run.

    Hi You used Right strategy only.Use Strategy '82',  Transfer requirement from CRM and execute MRP run in Background.It will generate Production order.But i didn't understand what you mean by 'Online' 3
    Pl.  Correct me If I am wrong.
    Edited by: Velmurugan S on Mar 4, 2008 10:02 AM

  • Problem when creating planned order with MRP run

    Hello,
    I create a material with a fix reorder point, MRP type VB. When I run MRP with MD03 on this material I have several problems :
    - planned order is created with an opening date in the past, so I have error 'Opening date in the past' in MD04. How can I generate a planned order with opening date not in the past
    - when changing manually opening date, after running again MD03, I have error 'No BOM selected'. Material is configurable, has a text BOM, a routing and a configuration profile. What is the problem? When modifying planned order, I have message :
    Material requires configuration
    Message no. 61259
    Diagnosis
    Orders and requirements for a configurable material must have characteristic values.
    Usually, you should create a variation for configurable materials managed in inventory management which has the default variant configuration.
    System Response
    MRP: Requirements without characteristic values for a material cannot be planned in MRP.
    Procedure
    Check requirements or orders.
    Create a configuration evaluation for the material in the material master record if necessary.
    Thanks in advance.

    Hi
    I am facing the problem. Could you please tell me if you have resolved the above problem? If yes, Could you please provide me as how you resolved? Thanks in advance.
    Thanks
    Nagesh.

  • Creating purchase requisitions instead of planned orders after MRP run in MDBT

    When running regenerative planning in MDBT for plant with following details ,The system has to provides planned orders for the materials .
    Processing key:NEUPL
    Create Purchase requisition :3
    Schedule lines:3
    Create MRP list:1
    Planning Mode:1
    Scheduling :1
    But sometimes it provides purchase requisitions for certain materials.The problem happens for different materials at different times.
    I checked the material master and found that procurement type is external procurement.Business need to create planned order for the materials and then want to convert it to purchase requisition.
    MRP group is assigned to the materials but no creation indicator maintained for the MRP group.
    Please tell me why this run creates purchase requisitions suddenly and in the next run it disappears?

    Hello
    Maybe someonelse is running MRP in another transaction, such as MD02, with a different parameter. Check on transaction MD05 when was the last MRP execution and the user that ran it.
    Also check if there is any active implementation of BAdI MD_MRP_PARAMETERS.
    If you don't have a cretion indicator, maybe it would be useful to set it for your MRP group, with the parameter 3, in order to make sure that planned orders will be created.
    BR
    Caetano

  • Multiple planned orders in MRP run

    Hi All
    I have a requirement where I need to create multiple planned order for the same material during MRP run. I understand that once I run MRP a planned order creates. If I run again for the same material, the quantity will be changed for the same planned order. Do we have any configuration so that system creates multiple planned orders for same material for each MRP run.

    Hi Adithya
    Planned orders may be changed by MRP until they are firmed. Therefore, what you need to do is to firm the planned orders after the MRP execution.
    You can use for example, transaction MD19 to mass firm planned orders after each MRP run.
    Otherwise, you can user BAdI MD_PLDORD_CHANGE to automatically firm the planned orders created by MRP.
    BR
    Caetano

  • Generate Plan Order from MRP Run (MD51) by WBS Element

    Dear All,
    1. I have created sales order with assigment WBS element (VA01)
    2. Then I created Routing & BOM for Material (CA01 & CS01)
    3. Generate MRP Run (MD51)
    The problem the generated mrp run doesnt consume planned order .. i have set the planning strategy 21 or 40, but still doesnt works.. is there any other parameter that i should configure..???
    Help Me...
    MamaRara

    Hello,
    Hopefully, the following link can assist you.
    - Re: After firming planned order, new planned order is generating in MRP run
    - Basic Scheduling in MRP run
    - Re: MRP run
    - During MRP run unwanted plant and storage location include and exclude
    - MRP run does not consider the common stock
    Thanks & Regards
    JP

  • Confirmed date in sales order influenced by planned order dates

    Hi,
    My requirement is that the after the MRP is carried out and planned order is generated, the changes in the dates of the planned order, when carried out, shall accordingly influence the confirmed date of the sales order line item when the availability check is carried out in the sales order.
    Say, the sales order has confirmed a line item for 25.05.2009. Once the MRP is carried out and planned order is generated and owing to unavailablility of a component, the planned order date (finish date) is manually re-scheduled to say 28.05.2009. My requirement is that the sales order confirmed date shall accordingly be re-scheduled when the availability check is carried out.
    Additional Info : Strategy Group - 20,
                           Make-to Order scenario is employed,
                           Standard Item category TAN,
                           Requirement Class - 040.
    Is this possible in standard SAP? If not, please suggest any custom developments that may be required. Looking forward for helpful replies.
    Do revert back if more info required.
    Regards,
    Anil Kumar

    Hi Anil,
    As Suggested in Above reply to your question.
    If Materail component was not available and due to that you had to reshedule the planned order date manually, that definately will affect the material availability date, but i think if material availability will be run once again in Sales Order it will determine the new material availability date, and i dont think there is any need to carry out any enhancement.
    Guru's Please correct me if I am wrong.
    regards,
    Paresh

  • How to trace planned order data after it has been converted into production

    Hi, There,
    The planned order has been converted into production order.
    However, I need to trace if this planned order is generated by MRP
    run or created manually. I can't get any planned order info from
    table PLAF. Any input?
    Regards,
    Nancy

    Hi,
    Once fully converted, the Planned Order data will not be available in the Table : PLAF.
    If it is available, then You can have the details with the Time Stamp and User data from PLAF.
    But, the refrence will be available in the Production Order.
    You want to make a Track of the Planned Order details and the Quanity, then you need to have/create Z tables so that the data will be availabe.
    This is how most of the Organizations keep a track of the Planned order data.
    Hope this helps..
    Regards,
    Siva

  • Issue about planned order date of ROH.

    Hi Experts,
    In MD04 , system is displaying planned order date of ROH after the planned order date of FERT i.e., for FERT---- planned order date is 21/01/2009 But for ROH -
    planned order date is 23/01/2009.
    can anyone tell me y its happening here.
    regards,
    sap pp
    Edited by: sap  pp on Jan 22, 2009 11:42 AM

    Dear,
    Go to the BOM of FERT and check the in component details and check Lead-time offset. Make it blank
    In OPU3 and OPU5 Adjust dates in lead time scheduling should = 1 Adjust basic dates to order start date.
    Then run the MRP in MD02 with planning mode 3 deleted and recreated and check your result.
    Regards,
    R.Brahmankar

  • Planned order dates

    Hi Guru's,
                  please explain how the planned order dates are calculated.
    in MTS scenario if a delivery exists and another planned order is raised the system is not calculating dates as per dates given in the Material master.it is cheduling the order depending on the previous delivery date.
    Please explain me How it is calculating the dates in planned order
    Thanks
    Satya

    Hi,
    The scheduling is based on your MRP parameters. If you select the basic dates scheduling while running MRP, the system will consider the material master in house production time. It will not consider the routing standard values.
    If you select the lead time scheduling, the system will explode the routing and it will calculate the operation time based on the standard values which we have maintained in the routing.
    Always there will be some difference between these two type of scheduling. Lead time scheduling will be more accurate than the basic date scheduling.
    Regards,
    V. Suresh

  • Creation of production order while mrp run

    hi
    ppgurus
    can any body explain how to create a production order by mrp run
    ie
    sysytem should create the production order directly while mrp run not PLANNED ORDERS
    what settings i need to do for  this plz explain
    urgent requirement
    regards
    sasikanth

    HI
    you gave a good way to solve the problem
    if it is a make to stock REM
    i  need not convert planned order to production oreder right
    plz suggest in  that scenario where i need to  do availability check
    in REM for which oder type (say PE IS STANDARD)
    to be assigned for availability  check
    plz suggest because in spro (t -code opjk) at order controll
    i dint see the order type PE
    the order controll (opjk) in discreet  :- avialability checking rule assigns
    in which setting this setting to be done in REM

  • Sales order while MRP run

    Hello friends;
    My requirement is such that when i run mrp in MD02, system should not consider those sales order that are planned in previous MRP run. System should consider new sales orders that are created after MRP run.
    Waiting for reply.
    Thanks.

    Hi,
    One solution is go for individual Sales Order/Line Item MRP run using T.code MD50.
    But I can't understand problem with use of MD02.If Receipt element(Plan order)is there which contains the Account Assignment of that Sales Order line Item then I don't think system will replan for same Sales Order Line item.
    Regards,
    Dhaval

  • Problem with scheduling planned orders in MRP

    There is a problem with scheduling planned orders in MRP. SFG is assigned to the BOM of FG. No inhouse production time maintained in the material master of SFG & FG. routing maintained for both . In OPU5 scheduling & capacity reuiremnts tickmarked for detailed scheduling. Scheduling level - via detaied scheduling. Scheduling type - backward. Adjust basic dates , adjust dep. req. to order start set. In MD02 , scheduling is via ' lead time scheduling'.
    My problem is the start date & time & finish date & time is same for planned orders of FG & SFG in the detailed scheduling tab of the planned orders. (Duration is same because of same capacity requirements on the same work centre. But how is the finish date same for both SFG & FG?)
    (Capacity requirements are being generated.)
    What could be the problem ?

    Dear,
    By scheduling the routing and maintain lot size dependent time in material is best practice and result of scheduling will be consistent.
    If you want SFG before FG you need to define lead time offset in BOM or need to maintain the floats before production.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Process Orders and Planned Orders data

    Hi,
    I am working on extracting process order and Planned Orders data into BW. I could not find any standard DataSources available for my req, so I want to develop generic extractor. the main key figures are Actual Labor and Machine Hours, Target Labor and Machine hours.
    Please help me if there are any standard datasource available or ECC tables to pull the data or any standard function modules available.
    Thanks,
    Reddy

    Hi Sanath,
    Thanks for your reply. I want to pull Actual Machine hours, Target Machine hours, Actual Labor hours and Target Labor hours.
    these fields are not there in PLAF table.
    I am looking for a table or datasource which can give those details.
    Thanks,
    Reddy

  • No planned order created when run MRP for Sale Order

    As I have told on the subject. My problem is system does not generate planned order for components in BOM
    Some more information is: requirement class in SO is 043
    I have choose "2" in tab MRP 4 for individual/collective and all component and finish product have MRP type is PD and Strategy is 20 - make to order
    Please help me to solve this
    Thanks

    Hi Hoai Vu,
    Please check in OPPQ plant parameters in SPRO weather you maintained for the plant conversions of planned order to production order.
    SPRO-> Production> material requirement planning> plant parameters--> carry out plant parameters or over all maintenance of plant parameters (OPPQ)
    Then check the for the material did you maintained the work scheduling view or not.
    I hope helps you any queries please revert me back.
    Regards,
    Madhu.G

Maybe you are looking for

  • Color washed out when using image processor in Bridge CC

    Hi, When I use the image processor - Tool>PhotoShopS>Image Processor, via bridge my colors appear wrong and washed out. When i choose "Include ICC profile" in the process dialog it has no effect - the colors are still wrong. In PhotoShop my profile i

  • How do I make a custom Forward button and Back button?

    I've got an almost completely custom theme and it's working great with one exception: The forward and back buttons (used to move between menu pages) are from the original theme I based mine on, and they are now white on white = invisible. I tried sho

  • TFTP transfer problems

    I am trying to upgrade multiple 1841 routers with a new ios which is IOS Software-12.4.24T5 advanced security. The Routers have 256 dram and 64 flash Min Requirements are 192/64 for the new ios. the ios file is about 32 mb in size and i have made at

  • Commerce Server 3.5 license

    When will the license on your site be updated, it ran out yesterday ?

  • Possible to edit action script permanantly from outside of flash?

    More specifically is it possible to permanantly add strings, for instance, to an array using an input text field and having that text field push the text into the array?